“Mr Cunningham’s credibility should be judged on the matters before the court in this hearing and not against the background of the procedural history which was not canvassed in the evidence, nor in relation to side-swipes made about other litigation involving Mr Cunningham, the merits of which are not before the Court.”
“We will need the services of a structural engineer when the works are being opened up to enable the contractors to submit calculations to the building control officer for approval. We have a quote from David Burle, who has experience of this type of work, and he suggests an hourly rate of£185 , as the scope of the work is small but unpredictable...”
“The remaining issue for negotiation with whoever is appointed [as main contractor] will be surety and this will have to be discussed and agreed in person with yourselves and the contractor, we will of course be present and advise you of any pitfalls during this discussion.”
“Contract 2.01 Priorities The contract shall be an amended form of MW 98 with additional sections to cover artisans and sub-contractor design for the plumbing and electrical works. The adjudication clause was agreed as being included in the contract. A letter of intent is to be produced by Gelande by the3rd February 2003 in the sum of£50,000 to enable design works to commence for M and E works and erection of scaffold. [That was actioned for Gelande] [Mr Cunningham] stated that the critical elements were the quality of the finished product and maintaining the works within budget [Mr Cunningham] asked for proposals to reduce the budget to£525,000 from the current tender price of£605,000 . [Mr Cunningham] asked for some of the principle (sic) ground floor rooms to be ready by the third week in June 2003. 2.02 Handover of Production Information Initial production information will be provided by [the Defendants] at the first site meeting. Further information will be provided following opening up and input from the structural engineer. 2.03 Commencement and completion dates It was agreed that the works would commence on21 February 2003 and would take 26 weeks completing on25 August 2003 . A pre-contract meeting was arranged for5 February 2003 , 10 am on site. … 5.0 Consultants’ Matters 5.01 Structural A structural engineer is to be appointed by Gelande as soon as contractual matters are resolved. 6.0 Quantity Surveyors’ Matters 6.01 Adjustment to tender figures Tender figures had been adjusted once already, by A. Richardson and M. Farmer at a meeting on3rd December 2002 . Further savings (approximately£75,000 ) are required and suggestions for these savings are sought.”
“Re: Refurbishment works to Bengeo Hall, Herts. – Letter of Intent Dear Sirs We are pleased to inform you that Gelande Corporation Limited (“GCL”) (“the Employer”) acting for Rob Cunningham and Catherine Good has instructed Collett and Farmer to appoint Eugena as main contractor for these works. This letter confirms the Employers’ appointment of Eugena and acceptance of the terms of your revised agreed tender return of the7th November 2002 , in the sum of£605,772 (tbc) with a 23 – week programme commencing on site. Several items are still being revised/reviewed and these amendments will be incorporated (when they are finalised) as variations in the tender return. We have instructed Collett and Farmer to send the contract documents to you for signing. At the meeting with Eugena and Collett and Farmer on Friday31st January 2003 , it was agreed that this letter would authorise expenditure on preliminaries and specialist design works up to a value of£50,000 , but that this letter of intent does not cover construction works which will be the subject of a separate instruction. It was also agreed that the Client would provide an initial payment of£40,000 on account of the works and that an escrow account would be established to hold one valuation on account during each monthly period of the works. It is our understanding that Eugena will provide suggested wording for this agreement. We would like to arrange payment by credit transfer. Can you therefore please provide detail of your bank account, sort code etc. It was agreed that an early start to the works is required and Eugena is to arrange for site operations to commence on21st February 2003 . Eugena confirmed that it was arranging the insurances required by the contract (MW 98). It was also agreed that Eugena would provide a quote for the insurance of the building during the works, which has now been delivered and is receiving our urgent attention. Please confirm that these matters are in hand and kindly provide the name and contact numbers of the proposed site manager. Yours Faithfully Rob Cunningham Gelande Corporation Limited.”
“It has become increasingly common in recent years in the construction industry for a form of “letter of intent” to be employed which, while it does indeed contain a request to a contractor to commence the execution of works, also seeks to circumscribe the remuneration to which he will be entitled in respect of work done pursuant to the request in the event that no contract is concluded. Typically the “letter of intent” will seek to provide that the remuneration of the contractor will not include any element of profit in addition to out of pocket expenses incurred in doing the relevant work or that the remuneration payable will be ascertained by someone like a quantity surveyor employed by the person making the request for work to be done. It is also likely to request that the addressee indicates his agreement to the terms set out in the “letter of intent”
“(a) The risk of delays due to lack of information, and (b) The risk that if the contractual terms (including the price or the terms of the escrow ) took longer than envisaged to agree, the client would become liable to a delay claim once the MW98 was signed because the Defendant intended to administer it so as to have retrospective effect.”
“My decision was, after a quite lengthy debate with Eugena about what the ramifications were in terms of timing, programme, in terms of cost, mitigation of liability, risk that we could proceed, but we did so on the understanding given by Mr Farmer that a contract could be signed in two weeks and that he did not anticipate anything holding up – holding the progress up, so if we went along with the letter of intent which effectively limited our risk to£50,000 we were given comfort by Mr Farmer that there were no matters that were going to hold that up, that there would be a smooth transition from the letter of intent into the project.”
“It is vitally important that you pay Eugena the£40,000 deposit agreed with them and resolve the escrow account wording in order to avoid them getting nervous or delaying their start on site.”
“Adjustment to tender figures. [The Defendants] and Eugena are to meet to consider costs savings to reduce the overall budget to£525,000 . [The Defendants] to issue a revised scope with annotations indicating how the original tender return was reduced to£605,000 .”
“The current delay in agreeing both the Escrow account and signing the contract, in the absence of a further letter of intent, is currently preventing Eugena from confirming appointments of sub-contractors and I am expecting a further claim in this respect. I cannot stress too greatly the urgency of these contractual matters and ask that the account be set up and the contract agreed and signed as a matter of urgency.”
“The nature of the potential delay due to contractual matters remaining at large is not easily quantifiable. Currently, Eugena cannot place orders for sub-contract work and materials and this may have an immediate effect as the sub-contractors are on two weeks lead in and have already been lined up to start.”
“We are in receipt of your email dated27 March 2003 enclosing proposed amendments to escrow wording issued to you some eight weeks ago. The amendments you propose are unreasonable and it is unrealistic for you to seek to impose them on us at this late stage. For the avoidance of doubt, we are only prepared to enter into the escrow agreement the wording of which was issued to you some time ago.”
“We need to meet, at your offices, as early as possible next week to try to resolve these matters and get this contract back on course. I am very concerned that a listed building is now opened up with partial demolition and windows removed, with no work ongoing. If we fail to bring Eugena back onto the job, the delay in appointing another contractor will be detrimental to the fabric of the building and the increased costs may compromise the viability of this project.”
“Mr Cunningham stated that neither he nor Gelande were in any way responsible for any delay to this project and that under no circumstances would either he or Gelande pay any additional monies for delay or legal fees. Eugena stated that they were unable to proceed without agreement on these costs. Agreement could not be reached in respect of these costs and, by mutual agreement, it was decided that Eugena would carry out no further works as specified in the contract, but would return to site to fulfil their existing obligations, the valuation of which would be carried out and certified in accordance with the contract.”
“particularly unfair and unreasonable of you to withhold payment without stating openly that you intend to withhold payment, or giving reasons for not paying our fee application.”
“Despite the limited nature of the works envisaged by the letter of intent, the machinery of MW98 was perfectly workable in its application to those works, as was demonstrated by the way it was actually operated in the weeks which followed.”
“(a) the need to re-tender; (b) the need to change to the JCT IFC in place of the MW98; (c) the need to reduce the number of provisional sums and produce proper construction details, work which should have been carried out by the Defendants.”
“The fee will be calculated as follows: 1 Fee payable on contract sum of£525,000 at 11.75% equals£61,687 plus VAT and expenses. 2 Any increase to tender price to be payable as a flat rate of 10% for the sake of simplicity. 3 Total maximum fee payable for works to main house, boundary fence and garden wall is£70,000 plus VAT and expenses. The final contract value for this scope will form the basis of our final fee calculation, subject to a minimum fee of£61,687 plus VAT and expenses. Any addition to our scope of works will be charged at the hourly rates stated in our original agreement, and will be clearly identified as a separate item. January£2,750 February£2,750 March£2,750 April£2,750 May£2,750 June£2,750 July£2,750 August£2,750 (to be adjusted plus/minus as noted in points 1,2 and 3 above)”