“Given Mr. Buckingham’s submissions on jurisdiction set out below, he will not respond to the substantive issues and/or the individual paragraphs contained in the Referral in this adjudication … Furthermore, Mr. Buckingham is in the process of preparing final proceedings against Allen Wilson, which will be commenced shortly for delay and defective works and the additional costs of having to complete these incomplete and defective works.”
“If any dispute or difference arises under this Contract, either party may refer it to adjudication in accordance with Clause 41A.”
“With reference to the letter of intent dated8th November 2004 and my reminder letter of 1st December, I note that you have still not yet returned it signed, as requested. Please can you respond to this urgently.”
“We are of the view that because of the continuous breaches of our payment agreement that we are not bound by the contract terms and conditions.”
“29… The Adjudicator’s jurisdiction is determined by and derives from the dispute that is referred to him. If he determines matters over and beyond the dispute, he has no jurisdiction. But the scope of the dispute was agreed, namely as to the Employer's obligation to make payment and the Contractor's entitlement to receive payment following receipt by the Employer of the Contractor's Applications for interim payment Nos 4, 5 and 6 … In order to determine this dispute the Adjudicator had to resolve as a matter of law whether Clauses 30.3.3-6 applied or not, and if they did, what was the effect of failure to serve a timeous notice by the Employer. Even if he was wrong on both these points that did not affect his jurisdiction. 30. It is important that the enforcement of an adjudicator's decision by summary judgment should not be prevented by arguments that the adjudicator has made errors of law in reaching his decision, unless the adjudicator has purported to decide matters that are not referred to him. He must decide as a matter of construction of the referral, and therefore as a matter of law, what the dispute is that he has to decide. If he erroneously decides that the dispute referred to him is wider than it is, then, in so far as he has exceeded his jurisdiction, his decision cannot be enforced. But in the present case there was entire agreement as to the scope of the dispute, and the Adjudicator's decision, albeit he may have made errors of law as to the relevant contractual provisions, is still binding and enforceable until the matter is corrected in the final determination.”
“The terms of the contract were decided upon by Mr. Beckingham’s agents, who are chartered surveyors, and Mr. Beckingham had, or had available to him, competent and objective advice as to the existence and effect of the adjudication clause before he proffered and entered into the contract. Westminster did no more than accept the contract terms offered and had no reasonable need to draw to Mr. Beckingham’s attention the potential pitfalls to be found in the adjudication clause and in its operation during the course of the work. The clause did not therefore contravene the requirement of good faith (see especially the speech of Lord Bingham in the case of Director-General of Fair Trading v. The First National Bank Plc [2002] 1 A.C. 481).”
“While it may be going too far to say that a building contractor who merely, without more, accepts a proposal from a ‘consumer’ as to the terms of the contract to be made between them could never contravene the requirement of good faith, it is difficult to envisage circumstances in which the criticism could properly be made that the contractor had acted contrary to the requirement of good faith in such a case.”