“Draft Interim for Phase 2 Variation: Please complete the Phase 2 Fit Out Works for this contract in accordance with the following documentation currently being prepared for imminent issue: 1 Bills of Quantities previously prepared by Jackson Coles and priced be Hallamshire Construction and now being revised to produce reduced costs. 2 Drawings and Specifications previously prepared by Sansone Hall Architects, WS Atkins, Malcolm Chard Associates and Sandy Brown Associates and now being revised to reflect the amended items of the Bills of Quantities. All Terms and Conditions to be as existing Contract dated11 June 1997 between South Holland District Council and Hallamshire Construction with the following exceptions: 1. Contract Completion Date to be revised to Sunday30 November 1997 . 2. Contractors compound to be removed and Double Street to reopen on31 October 1997 . (Note: Road alignment works to Double Street to be the subject of a separate variation) Jackson Coles have agreed a full and final settlement of any and all claims in connection with prolongation/disruption, etc, up to and including the date of this Instruction and the Contractor has agreed that no further claims will be made in connection with the items previously noted as being responsible for delay in the Contractor’s Progress Reports tabled at the monthly Project Meetings. All costs in connection with this variation to be agreed at fair and reasonable costs by Jackson Coles.”
“the rates and prices in Bill A that were not changed in Bill B were agreed by offer and acceptance ... the rates and prices, other than mark up, in Bill B that are different to those in Bill A, by revision of Bill A, were agreed orally by negotiation in August 1997 and at the latest in November by conduct thereafter.”
“the percentage mark up for overheads and profit was agreed, by offer and acceptance, on receipt by the claimant of a copy of the Final Account in November/December 1999.”
“Whether the Parties ever (and if so, when and in what circumstances) agreed a bill of quantities, whether in whole, or in part, for the purpose of valuation of the work carried out by the Claimant under architect’s instructions 51 and 52.”
“applying the basic principles of offer and acceptance, there was no agreement as to the cost of the work to be undertaken since neither party accepted an offer made by the other.”
“all costs in connection with this variation to be agreed at fair and reasonable costs by Jackson Coles.”