“1. Whether or not the certificate issued by the architect on29 March 1999 was validly issued in accordance with clause 30.8 of the contract conditions. 2. Whether or not the certificate issued by the architect on29 March 1999 is the final certificate for the purpose of clause 30.9 of the contract conditions.”
“We have been issuing instructions under contract clauses .3.2.2 and 13.2.4 which empowers us to do this but this does not mean that we have agreed any costs or liability or payment, merely that the variations and alterations have occurred factually.”
“Agree to your final account as attached. Please could you or Ray Harris [of Hollins, the Architect] advise when the final certificate will be issued.”
“It is my duty, under the terms of the Contract, to identify all the variations, which we have done, copies of which you have had, and prepare a final account statement, in which we have been aided by Messrs Hyams and Partners [the quantity surveyor appointed by the Architect]. I now report to you that this figure is£548,799 25. Under Clause 30.7 I enclose a Certificate which authorises payments to nominated subcontractors, when fair proof of payment from [the respondent] has been received we will issue the final certificate. I enclose copies of the final account documentation from Hyams for your information.”
“Hollins Architects and Surveyors Planning Consultants Certificate for Payment Job No 95173 Certificate No B536/95173/12 25. Issue date29 March 1999 Employer Contract sum 494,682.22 Less contingencies (10,000.00) B R & E P Cantrell Foxearth Lodge Nursing Home Little Green Saxtead Add variations 50,509.62 548,799.25 Less items paid by client: Lift (12,115.00) Nurse station (2,160.00) Lift (6,939.81) ----------------------------------- ------------------------------------- -------------- Site address TOTAL£527,584.44 ------------------------------------- -------------- New EMI Unit (Phase 1) Foxearth Lodge Nursing Home Gross amount due 527,584.44 Less retention Nil ------------------------------------- -------------- Net amount due 527,584.44 Less previously certified 477,074.82 ----------------------------------- ------------------------------------- -------------- Contractor Wright and Fuller Ltd Strawberry Field Main Road, Willisham Ipswich IP8 4SP Payment now due 50,509.62 VAT@17½ per cent — ------------------------------------- 50,509.62 We certify that the sum of Fifty thousand five hundred and nine pounds 62p due to the above Contractor as a final payment for works completed and under the terms of the Contract payment is due within 14 days of issue above. Signed: for Hollins Architects and Surveyors 4A Market Hill Framlingham Suffolk IP13 93A CR Tanner FRICS RAE Alexander Dipl Arch (Oxford) RIBA Consultant Architect SP Reid Planning Consultant”
“Dear Mr Cantrell New EMI Unit - Phase 1 I now write to enclose the final certificate as per the contract sum, variations and omissions I believe this now discharges our obligations under the contract. I would respectfully remind you that you would be advised to check that the sub-contractors have been paid their due amounts before you make any final settlement. Yours sincerely C R Tanner”
“By copy of this letter to Warrington Martin [the respondent’s quantity surveyor] we set out above [the claimants’] position and look forward to receiving reimbursement from the Contractor in the form of a cheque for£22,737.75 payable to ‘Foxearth Lodge Nursing Home’ within the next 14 days of the date of this letter failing which we shall take such further action as is deemed necessary.”
“is this contention advanced by the claimants correct: because the Final Certificate was not issued on or before23 October 1998 , no valid Final Certificate could have been issued on29 March 1999 ?”
“That clause required him to ‘certify’ in writing. While no set form of certificate is provided, unlike that under clause 21(a) and (b), it must clearly appear that the document relied upon is the physical expression of a certifying process. One should, therefore, have some regard to the factors of ‘form’, ‘substance’ and ‘intent’ of which Mr Justice Devlin spoke in admittedly different circumstances of Minter Trust Ltd v Traps Tractors Ltd. Or to borrow a passage in Hudson (10th edition, page 479), the document should be ‘the expression in a definite form of the exercise of the ... opinion ... of the ... architect in relation to some matter provided for by the terms of the contract’. And, as Mr Garland [counsel for the employer] accepted, it must be free from the ambiguity.”
“It is important to appreciate that the architect, when acting or purporting to act under either conditions ... or indeed under any other empowering clause or condition in this contract, is exercising a power which affects the contractual rights of the parties to the contract by varying those rights in one or more ways as the parties have agreed should be the case. It is therefore of crucial importance that the exercise of power by the architect should be done clearly and unambiguously so that the parties know where they are and should not be left in doubt or indeed in dispute as to their consequent mutual rights and liabilities after the exercise or purported exercise of this power. I respectfully agree with and adopt what was said by Mr Justice Devlin in Minster Trust Ltd v Traps Tractors Ltd. The learned judge said: ‘I think that a certificate of this sort must, to satisfy the contract, be unambiguous and readily understandable. When a document is tendered under a contract, the recipient has often to make up his mind whether he is going to pay out money upon it or accept or reject goods; he has no right to clear up doubts.’” ‘I think that a certificate of this sort must, to satisfy the contract, be unambiguous and readily understandable. When a document is tendered under a contract, the recipient has often to make up his mind whether he is going to pay out money upon it or accept or reject goods; he has no right to clear up doubts.’”
“29. I cannot accept that the contract terms, properly construed, prohibit the provision and receipt of further information, documentation or details about direct loss and expense after the six month period following practical completion Such a stringent time-bar would in my view require to be expressed in clear and unambiguous language which I have been unable to find in the contract terms. On the contrary, the wording of [the clause in question] suggests that [the sub- contractor) are correct in their contention that the statutory [sic - the learned judge clearly meant contractual] provisions simply provide a time table to which the parties are expected to adhere.”
“And it is said that this certificate was issued very much out of time. It should have been issued, according to the terms of the contract, I think I am right in saying, within six months of the end of the defects liability period. It matters not. It should have been issued some years before it actually was. According to the terms of the contract - I forbear from reading them; they appear in the papers and in the judgment of the learned judge - the certificate should have been issued earlier, and it was the duty of the architect to issue it. But on the facts of the case what happened was this: the contractors called for the certificate, the [employer] asked the architect not to issue it, there was still some electrical work to be done, and it was not until May 1973 that the [employer] agreed on the advice of the architect, that the certificate could be issued. In the correspondence between the [employer] and the architect relating to this matter they speak of the issue of the final certificate; and into the covering letter enclosing the certificate with which we are concerned the [architect] say to the contractors ‘We are enclosing the final certificate’. I take the view that the [employer], in an action brought by them against a main contractor, could not have been heard to say that this document was not a final certificate. It goes against all commonsense. In my view it goes against the rules of law, too. They would have been estopped from so contending, in my view. The fact that the words ‘Final certificate’ did not appear upon it seems to me to be wholly irrelevant in the present circumstances. They appeared so strongly in the covering letter that the two must be read together.”
“17. Clearly a certifier or other decision-maker must have the necessary contractual authority to act for otherwise the certificate or decision will be invalid. If the person has gone outside the limits of the decision-making authority conferred by the contract, ie the person does not have the power or jurisdiction to make the decision or to issue the certificate, the certificate or decision will be unenforceable and will be liable to be set aside. The parties may of course agree to accept the act and in effect to ratify it and, by waiver or otherwise, accept the certificate or decision as valid so that it is not always useful to describe it as a ‘nullity’.”
“24. In my judgment the provision of a copy of the ascertainment, and of a statement, of the AFS is not a condition precedent to the issue of the final certificate so that a failure to provide them before the final certificate does not affect the Architect’s authority to issue a final certificate.”
“23. Furthermore, clause 30.7 may be satisfied much earlier Mr Blackburn [counsel for the Employer] adopted in argument the illustration of a piling sub-contractor whose work and its measurement and valuation will almost invariably be finished and completed well before practical completion so in such an instance effect would be given to clause 30.7 by an interim certificate issued much earlier than 28 days prior to the issue of the Final Certificate. In any event the purposes of clause 30.7 are those given by Mr Blackburn (and accepted by Mr Stimpson [counsel for the Contractor]), namely to enable the Contractor and Nominated Sub-Contractors to have advance notice of what was going to be certified so that, if necessary, steps can be taken to avoid the effect of the Final Certificate and to establish multi-party arbitration and to enable the employer to pay a sub-contractor direct and to recover the amount from the balance of the Final Certificate (where there was a sufficient sum available). It is not a condition precedent to the issue of the Final Certificate.”
“2.06 ... the [claimants] submits that the Certificate for Making Good Defects and/or the Architect’s statement under clause 306.1.2.2 are conditions precedent to the issue of a Final Certificate, which have not yet been met. (In fact more correctly, it is the Quantity Surveyor who is referred to, in the Contract, .not the Architect, although Hollins is referred to, in the Contract, as Architect and Surveyors and under Article 4B are to undertake the function of Quantity Surveyors, the error is probably irrelevant).”
“empowers us to do this but does not mean that we have agreed any costs or liability for payment, merely that the variations and alterations have occurred factually.”
“I believe this now discharges our obligations under the contract”