“The price of work done to that date plus other amounts to be paid to the contractor less amounts to be paid or retained from the contractor ...”
“CE60 - interest due in respect of the late certification (CE1 to CE93)”
“At the dissatisfaction meeting on29th September 2003 you requested that we provide you with our views on the relevance of clause 65.1 of the contract to our entitlement to payment in respect of compensation events.”
“This does not affect the contractor’s entitlement to get paid for work done, the date upon which such payment should be made and the date from which such interest should run if payment was not made”
“CE60 - interest due in respect of late certification (CE1 to CE93)”
“Your analysis of the operative date for payment for works carried out and the process of compensation events appears to disregard the effects of clause 63.8”
“The project manager implements each compensation event by notifying the contractor of the quotation which he has accepted or of his own assessment. He implements the compensation event when he accepts a quotation or completes his own assessment or when the compensation event occurs, whichever is the latest”
“Firstly, the submissions are selective. The narrative only deals with a selection of compensation events. At present we have no factual submissions with regards to the majority of compensation events identified by McAlpine. Transco are faced with the prospect of understanding McAlpine’s case for the first time in their Reply. We reserve our position with regards to this course of conduct including without limitation issues of natural justice”
“41. The schedule attached to McAlpine’s letter of6th October 2003 is drafted not on the basis on which the compensation event occurred but on the basis of the date upon which the work was undertaken. This does not fall within the carefully drafted definition set out in clause 65.1.”
“Accordingly, Transco have limited the evidence that they have submitted on this issue as McAlpine have provided no evidence and have not referred a dispute on the basis that there has been a breach of contract by Transco in respect of the assessment process itself.”
“It has been necessary to send these attachments as evidence to deal with the responding party’s assertion that the referring party has failed to provide any detail of the factual background for the compensation events in relation to which interest is claimed. As you will note from the Reply document itself, the documents were not originally included with the Referral as our client did not believe that there was any disagreement between the parties on the factual background until it was raised by the responding party in its Response”
“31. In relation to paragraph 53 of the Response, the referring party did not provide particulars of the factual background in the Referral or the dates upon which the work was actually undertaken as these issues were not in dispute. The referring party still understands this to be the case. Be that as it may, to assist the adjudicator, the referring party has prepared histories by way of example of the applications and payments in respect of the following compensation events - 01, 04, 05, 14, 22, 24, 38, 39 and 58 (which includes 62 and 66) ....”
“(1) McAlpine’s case set out in the Referral was simply that payments in respect of various compensation events had not been certified when they ought to have been. No details were given to prove the claim - dates of notification of the compensation event, provisions of or requests for a quotation, request for and/or provision of further information, period of negotiation etc.”
“I consider it proper that I should be in possession of the available evidence to enable me to reach the best decision”
“The timetable for adjudications is very tight (see section 108 of the Act), many would say unreasonably tight and likely to result in injustice. Parliament must be taken to be aware of this.”
“What constitutes a dispute will depend in each case on the circumstances and the context in which the referral is made. In some cases the issues are very specific. In other cases, it is clear that the issues are more general and have been so treated by the parties and that there is significantly more room for the case to be developed. The test in each case is, first, what dispute did the parties agree to refer to adjudication? and, secondly, on what basis? If the basis which is argued in the adjudication is wholly different to that which the defendant has had an opportunity to respond to in advance of the adjudication, this may constitute a different dispute not referred to the adjudicator or, put another way, in so far as the adjudicator reaches a decision on new issues, it is not responsive to the issues referred to him.”