"9.1 CONTRACTOR shall commence performance of the WORK, continue and complete the WORK in an expeditious and timely manner and in accordance with the PROGRAMME cited in EXHIBIT C together with the specified Key Dates and Milestones. CONTRACTOR acknowledges that the timely performance of its obligations hereunder are vital, fundamental and essential for the exploitation of the FIELD. Consequently time is of the essence of this CONTRACT, as delays in the performance of the WORK would cause most substantial prejudice to OWNER. CONTRACTOR shall be entitled to schedule the performance of the WORK so as to maximise efficiency, providing always that the key dates and milestones are not delayed."
"4.11 In the event that any offshore WORK is delayed beyond the1st November 1998 due to causes attributable to OWNER, OWNER shall in those circumstances only be liable to pay for all "
"6.1 Up to 45 days prior to the FPSO arrival in field "target date" of September 2nd 1998, OWNER can change the target date provided a minimum of 45 days remains from the new target date for CONTRACTOR to plan for the remaining work. The pricing for the work will not change other than as described in the foregoing sections or the following requirements/clarifications: 1) CONTRACTOR can plan, schedule and execute the workscope at any time throughout the year provided that the work is complete 15 days in advance of the "target date". 2) The pricing mentioned herein is subject to the currently notified PGS delivery dates which are contained in Appendix A and Appendix B. 3) The price mentioned herein for the FPSO hook-up will be held firm up and until1st November 1998 . 4) In the event the FPSO arrival in the field is later than1st November 1998 or the work continues beyond this date then all weather downtime incurred during mooring hook-up activities shall be to PGS account."
"PGS confirms that DSND has no responsibility or liability with respect to the design of the RTIAs. Any delays or consequence that may occur during performance of the workscope caused as a result of the RTIA design shall be borne by PGS."
"...all of the obligations of PGS under the CONTRACT 97003 are in place, valid for all construction activities and also naming DSND as additional assured. PGS has and will continue to comply with the requirements of our BAR policy and accordingly you are instructed to commence forthwith the RTIAs assembly and thereafter the installation at the FIELD"
"all contractual issues are to be subject to further discussion/agreement prior to proceeding with the work"
"....as long as PGS has endeavoured to ensure that the contractor complies with the terms and conditions of the All Risks Insurance Policy, whether that be recommendations of the warranty Surveyor, implied or expressed warranties, if any, or the specific or general conditions of the policy, then the All Risks Insurance Policy extends to the contractor subject to any exclusions or limitations contained in the aforesaid police."
"please advise if this is sufficient"
"many thanks for your cooperation in achieving this in such short time"
"...the Defendants aver, in respect of each of the documents identified above that it necessarily followed from the Claimant's statements that (i) the Fennica would be able to perform riser installation in sea states up to Hs=3, and (ii) that the risers themselves could be safely, and would be, installed in sea states of up to Hs=3 (save in respect of the section containing buoyancy modules which were limited to Hs=2)."
"In particular, unless one knew the procedure and the assumed sea state applicable to the RAOs and the spectrum of the wave, it was impossible to reach any meaningful conclusion as to the vessel's suitability for the work."
"Determine maximum speed of Fennica transom resulting from combined heave and pitch relative to Banff sea conditions"
"DSND now consider that single wire installation or risers is now possible and clump weight solution for installation is no longer required. This will reduce the weather window from 50 hours at under 2M Hs to 18 hours at under 2M Hs."
"window start Thursday 48 hrs 2M Hs"
"Head assembly in water. Weather increasing, winds gusting 35 knots, seas 3-4 metres"
"I could have put there 5 metres and everything should be fine"
"this does not mean that the limit is lower than 3 metres"
"discussed the 25th September agreement which was a duress situation as we saw it at the time"
"the cavalier attitude displayed by DSND with respect to its obligations under the terms of the Memorandum of Understanding entered into on25 September 1998 , and in particular to the Schedule attached to, and forming an integral part of that Agreement."
"A transaction entered into as the result of undue influence is voidable and not void. The right to rescind on the ground of undue influence may be lost either by express affirmation of the transaction by the victim, by estoppel or by delay amounting to proof of acquiescence. Although there can normally be no affirmation until the party knows he has the right to rescind, it has been doubted whether this is a hard and fast rule: "the whole of the circumstances must be looked at to see whether it is just that the complaining beneficiary should succeed."
"By a Memorandum of Understanding dated25 September 1998 ("the MOU") you undertook to provide a DSV for the period 10 November to5 December 1998 .....In breach of the above obligation, and in spite of our numerous requests from early November onwards for urgent action on our part to supply a DSV on a continuous basis in accordance with your obligations you completely failed to provide an in-house DSV or a third party DSV for the agreed period......In any event, your failure to procure a DSV from 10 November and thereafter is itself an irremediable breach, which entitled us to terminate the contract."
"(I) Contractor persistently fails to perform the Work diligently in an efficient, workmanlike, skilful and careful manner, or (ii) Contractor fails to comply with any term of this Contract... then in any such event Owner having given Contractor reasonable opportunity to remedy the situation shall have the right to terminate this Contract by giving written notice thereof to Contractor."
"The CONTRACTOR shall commence performance of the WORK, continue and complete the WORK in an expeditious and timely manner and in accordance with the PROGRAMME cited in Exhibit C together with the Key Dates and Milestones. CONTRACTOR acknowledges that the timely performance of its obligations hereunder are vital, fundamental and essential for the exploitation of the Field. Consequently time is of the essence of this CONTRACT, as delays in the performance of the WORK would cause most substantial prejudice to OWNER. CONTRACTOR shall be entitled to schedule the performance of the WORK so as to maximise efficiency, providing always that the key dates and milestones are not delayed."
"As a result of variations to the contract workscope and methodology used to install their riser systems and contract schedule , PGS and DSND agree to the below mentioned mechanism for compensation and revised schedule attached hereto "
"Because of the uncertainty in providing the DSV(s) created by the many versions of DSV availability, none of which have materialised, PGS has no confidence in the current proposal, being the 5th contradiction since10th November 1998 "