“12.2. Where the arbitrator directs or the parties agree to a hearing dealing with part of a dispute then whether or not there is any agreement between the parties as to such matters, the arbitrator may do any of the following: a) decide what are the issues or questions to be determined. b) decide whether or not to give an award on part of the claim submitted. c) make an order for provisional relief. …… 12.9. The arbitrator has the powers set out in section 57(3) to (6) (Correction of award or additional award) which are to be exercised subject to the time limits stated. 12.10. The arbitrator may notify an award or any part of an award to the parties as a draft or proposal. In such case unless the arbitrator otherwise directs no further evidence shall be admitted and the arbitrator shall consider only such comments of the parties as are notified to him within such time as he may specify and thereafter the arbitrator shall issue the award.”
“A party to arbitral proceedings may (upon notice to the other parties, to the arbitrator concerned and to any other arbitrator) apply to the court to remove an arbitrator on any of the following grounds-- (a) that circumstances exist that give rise to justifiable doubts as to his impartiality; (b) that he does not possess the qualifications required by the arbitration agreement; (c) that he is physically or mentally incapable of conducting the proceedings or there are justifiable doubts as to his capacity to do so; (d) that he has refused or failed-- (i) properly to conduct the proceedings, or (ii) to use all reasonable despatch in conducting the proceedings or making an award, and that substantial justice has been or will be caused to the applicant.”
“If a party to arbitral proceedings takes part, or continues to take part, in the proceedings without making either forthwith or within such time as is allowed by the arbitration agreement or the tribunal or by any provision of this Part, any objection-- (a) that the tribunal lacks substantive jurisdiction, (b) that the proceedings have been improperly conducted, (c) that there has been a failure to comply with the arbitration agreement or with any provision of this Part, or (d) that there has been any other irregularity affecting the tribunal or the proceedings, he may not raise that objection later, before the tribunal or the court, unless he shows that, at the time he took part or continued to take part in the proceedings, he did not know and could not with reasonable diligence have discovered the grounds for the objection.”
“It seems to me that section 57(3)(a) can be used to request further reasons from the arbitrator or reasons where none exist. The policy which underlies the Act is one of enabling the arbitral process to correct itself where possible without the intervention of the court. Torch contended that it was clear that the arbitrator had not decided the issue and that therefore there was no ambiguity in the award which required clarification, but the very existence of a genuine dispute on this question militates against that argument. If there was unarguably a clear failure to deal with an issue, it could be said that there was no ambiguity in the award, but as set out in the Al Hadha case, an award which contains an inadequate rationale or incomplete reasons for a decision is likely to be ambiguous or need clarification. There was therefore room for an application by Torch under s 57, as an exchange of letters with the owners in relation to this part of the award would have revealed, so that the time limit of 28 days … applied. In these circumstances Torch had available recourse under s 57, which had not been exhausted and s 70(2) therefore presents an insurmountable bar to Torch’s s 68 application. I none the less go on to determine the s 68 application, should I be wrong on the ambit of s 57.”
“Looking at the whole sorry history of the matter, it seems to me clear that the arbitrator has unquestionably pointed the finger at the Applicants and repeatedly accused them, in my judgment unfairly, of deliberate delay. Above all, he has not paid proper heed to their objections and has insisted that the hearing must start on the day he ordered, when they cannot be in a position to conduct their case properly. In my judgment he must be removed. I therefore grant the order asked in paragraph 1 of the notice of motion.”
“28. I do not accept the proposition that simply because the award contains an error which is unfair to a party there must have been a failure to comply with s 33 of the 1996 Act on the part of the tribunal and thus a serious irregularity for the purposes of s 68(2)(a). First, there is nothing in the 1996 Act to suggest that it is intended to allow the court to intervene to put right mistakes of fact or of law which could not have been put right under earlier legislation. The 1996 Act was intended to ‘restate and improve the law in relation to arbitration’, and in view of the well-established policy of the courts to intervene only in cases where there had been some unfair treatment or result which warranted intervention, the grounds must remain limited. Secondly, such a proposition, if correct, would enable a dissatisfied party to challenge an award on the grounds of an error of fact or of law under s 68(2) and thereby to open up the whole course of the arbitral proceedings so as to invite the court to conclude that there was some unfairness, whereas it is in my view plain from the Act that the only method of appealing against a decision, as such, is provided by s 69 of the 1996 Act (appeal on point of law). Whilst there will be occasions when there is an overlap between an appeal under s 69 and a challenge under s 68 of that Act the latter should not be used as an indirect method of appealing against a decision of fact, other than in an exceptional case. Thirdly, s 33 is primarily concerned with the tribunal’s failure to conduct the proceedings fairly and impartially, and although a failure to comply with s 33 is placed first in s 68(2), it is in reality more in the nature of a general provision of which section 68(2) contains further examples … 29. Similarly, s 68(2)(d) of the 1996 Act is not to be used as a means of launching a detailed inquiry into the manner in which the tribunal considered the various issues. It is concerned with a failure, that is to say where the arbitral tribunal has not dealt at all with the case of a party so that substantial injustice has resulted, eg where a claim has been overlooked or where the decision cannot be justified as a particular key issue has not been decided which is crucial to the result. It is not concerned with a failure on the part of the tribunal to arrive at the right answer to an issue. In the former instance the tribunal has not done what it was asked to do, namely to give the parties a decision on all the issues necessary to resolve a dispute or disputes (which does not of course mean decisions on all the issues that were ventilated but only those required for the award). In the latter instance the tribunal will have done what it was asked to do (or will have purported to do so) but its decision or reasoning may be wrong or flawed. The arbitral tribunal may therefore have failed to deal properly with issues but it will not have failed to deal with them.” b) The most recent authority under section 68 is the decision of the House of Lords in Lesotho Highlands Development Authority v. Impregilo SPA and Ors[2005] UKHL 43 . The proper operation of section 68 is summarised by Lord Steyn at paragraph 28 of his speech: “First, unlike the position under the old law, intervention under s 68 is only permissible after an award has been made. Secondly, the requirement is a serious irregularity. It is a new concept in English arbitration law. Plainly a high threshold must be satisfied. Thirdly, it must be established that the irregularity caused or will cause substantial injustice to the applicant. This is designed to eliminate technical and unmeritorious challenges. It is also a new requirement in English arbitration law.
“The pleadings that were actually produced were prolix and diffuse and the schedules, which were not Scott Schedules, failed to consolidate and reduce into a composite pleading all aspects of each disputed work item. No agreed lists of items about which they agreed and disagreed were produced and they failed to agree any figures as figures. The result of these failures was a significant increase in the costs of each party and a failure to produce a coherent list of issues for resolution by the arbitrator in a form that would have enabled an award to be drafted which dealt with all remaining disputes without mistake, error or omission.”
“The meaning of ‘failure to deal with all the issues’ must therefore refer to a failure to deal with a claim or a distinct defence to a claim advanced before the tribunal and not merely to an omission to give reasons for the tribunal’s conclusion in respect of such claim or defence. It is in those cases in which the award expresses no conclusion as to a specific claim or a specific defence that the award can be said to have failed to deal with an issue.”
“Counsel observed that it must have been assumed that there was a substantial injustice. This is not good enough. The burden is squarely on the application who invokes the exceptional remedy under section 68 to secure if he can findings of fact which establish the precondition of substantial injustice. The employer did not satisfy this requirement. In these circumstances I would rule that the precondition of substantial injustice has not been established and that on this ground alone the challenge to pre-award interest should fail.”
“Accordingly, although each case turns on its own facts, the following considerations are in my judgment likely to be material: (1) the length of the delay; (2) whether in permitting the time limit to expire and the subsequent delay to occur the party was acting reasonably in all the circumstances; (3) whether the respondent to the application or the arbitrator caused or contributed to the delay; (4) whether the respondent to the application would by reason of the delay suffer irredeemable prejudice in addition to the mere loss of time if the application were permitted to proceed; (5) whether the arbitration is continued during the period of delay and, if so, what impact on the progress of the arbitration or the costs incurred the determination of the application by the court might now have; (6) the strength of the application; and (7) whether in the broadest sense it would be unfair to the applicant for him to be denied the opportunity of having the application determined.”
“I do have reservations about several issues which require, but lacked, a factual input. I feel that it is probably in both parties’ interests that I issue this particular award as a draft rather than as a formal award which confers finality to the issues. The fact that I am proposing to decline to determine the issues set out under paragraphs 79, 85, 92, 93, 94, 96, 101, 102, 115, 125, 135 and 144 of my draft award is not as serious as it may appear. Many of the issues I am unable to determine relate to the date when an alleged defect was notified to the Respondent by the Claimant. I simply do not have that information and in the scheme of things it probably does not matter too much.”
“The Respondent shall provide the Claimant with a list of documents in their possession relating to: 1. The design of the swimming pool works; 2. The defect liability period; 3. Correspondence relating to the contract by not later than13th August 2004 .”
“It was at this stage I drew to the arbitrator’s attention that I would be looking to deal with a number of the pleaded matters by way of preliminary issues. I summarised these as follows: a) Whether or not the alleged defects were patent or latent; b) Whether the alleged defects arose from design or simply bad workmanship. c) Whether one of the matters complained of was within the contract. After discussion it was agreed that there should be a hearing to try and decide these issues.”
“1. Design 2. Defects Liability 3. In or out of the Contract.”
“D.O. One of my applications today will be to fix hearing in September/October to deal with preliminary issues One of which whether allegations fall within design defect or building defects. Another, one of defects discoverable within a six month period and therefore down to the architect. A.R. [Mr. Ring] Probably won’t be resisted. D.O. Two areas where we say the issues will probably have to go to arbitration, about 8-9 areas where one or other applies. One item does not fall within contract at all: ozonator. We close pleadings and try and knock out issues at short hearing in autumn. Then, if you are with me, it will reduce the issues. If not, will go to full hearing. R.H.[Arbitrator] Do you agree? A.R. Similar. This document insurers of architect will want to see. Agreed to the appointment of arbitrator. In terms of timing don’t see why what your suggestion won’t work. Majority of things will be one thing or the other. Only caveat is for something to fall between two stools. R.H. Design liability could be subcontracted. A.R. Still Woods. D.O. Still an issue to be dealt with at preliminary issue.”
“15. The parties have instructed me via some protracted correspondence relating to the skeleton arguments and by clarification at the hearing to determine the following preliminary issues in an attempt to shorten proceedings as well as to reduce costs. 16. The agreed questions that I am required to decide upon are those set out in the Respondent’s solicitor’s letter to the Claimants’ solicitor dated30th November 2004 , acknowledged on6th January 2005 . 17. The preliminary issues to be determined are as follows: Statement of Claim, item 6, sets out the claim as breach of contract by the Respondent. I have subdivided question 2 into parts (a) and (b) for the purpose of answer. Question 1. That the alleged defect is a design defect which the Respondent has no liability for. Question 2. That the alleged defect is: (a) latent, not patent, and (b) was not notified until after the expiry of the contractual defects liability period. Question 3. That the alleged defect relates to work which was not within the scope of the contract works.”
“36. I find that, under the FAS Building Contract there is a basic principle that, where defective construction occurs, the contractor is prima facie responsible for those defects up to the statutory time limit set out by theLimitation Act 1980 as amended by theLatent Damages Act 1986 . 37. The contractor is responsible for instituting mechanisms which ensure the building is completed according to contract and failure to do so is the principal recourse for a client complaining of a defect. 38. Prima facie, contractors should be, and remain, liable for their own breaches of contract and should not have a general release from liability in respect of all breaches which the architect should have reasonably detected but failed to detect. It is unreasonable and too favourable to contractors to let them shelter behind the architect’s failure to detect faults in the course of his visits during the progress of the works: See clauses 2.21, 2.22 and 6.36 of the FAS Building Contract, advising the contractor that the architect has no liability to the contractor for supervision.”