“27.1 Neither COMPANY nor CONTRACTOR shall be responsible for any failure to fulfil any term or condition of the Contract if and to the extent that fulfilment has been delayed or temporarily prevented by an occurrence, as hereunder defined as FORCE MAJEURE, which has been notified in accordance with this Clause 27 and which is beyond the control and without the fault or negligence of the party affected and which, by the exercise of reasonable diligence, the said party is unable to prevent or provide against. Both parties shall use their reasonable endeavours to mitigate, avoid, circumvent, or overcome the circumstances of FORCE MAJEURE.” 27.2 For the purpose of the Contract, Force majeure shall be limited to the following: ………… (h) Drilling moratorium imposed by the government …….. 27.5 In the event of force majeure occurrence, the party that is or may be delayed in performing the Contract shall notify the other party without delay giving the full particulars thereof and shall use all reasonable endeavours to remedy the situation without delay. ……… 27.8 In the event that a FORCE MAJEURE condition prevails for a period of sixty (60) consecutive days then COMPANY may terminate the CONTRACT forthwith by giving notice, or may elect keeping CONTRCATOR under CONTRCT and keep paying the DAILY FORCE MAJEURE RATE.”
“Given, however, the rejection of the Jubilee Development Plan, drilling must de facto cease within the Jubilee field area. As things currently stand, therefore, it is no longer possible to conduct Jubilee field work under the Drilling Contract. It is [Tullow’s] position that the above both individually and cumulatively may result in Force Majeure ………which may prevent Work from being performed in Ghana. Based upon our current estimates, if unresolved, the Force majeure occurrences will mean that drilling activity will cease around3 October 2016 .”
“if and to the extent that fulfilment has been delayed or temporarily prevented by an occurrence, as hereunder defined as Force Majeure”
“Where there is no option in the business sense, the consequence of damning one channel is simply that the flow of duty is diverted into the others and the freedom of choice is restricted. If then a shipper cannot ship wheat, he must ship either barley or flour. The width of the alternatives is in the contract for the benefit of both parties and it can be a liability as well as a benefit for the shipper.”
“Where under the terms of a contract an amount due to a subcontractor in respect of work or services for or in connection with a petroleum agreement the person liable under that contract to make payment to the subcontractor shall withhold from the aggregate amount due to the subcontractor the percentage of the aggregate amount that may be specified in the petroleum agreement ……….”
“A person who enters into a contract with a contractor for the provision of work or services ……., in the Republic for or in connection with the petroleum agreement to which the contractor is a party……..”