“(1) Unless otherwise agreed by the parties, the court may on the application of a party to arbitral proceedings (upon notice to the other parties) determine any question of law arising in the course of the proceedings which the court is satisfied substantially affects the rights of one or more of the parties. … (2) An application under this section shall not be considered unless – (a) it is made with the agreement of all the other parties to the proceedings, or (b) it is made with the permission of the tribunal and the court is satisfied – (i) that the determination of the question is likely to produce substantial saving in costs, and (ii) that the application was made without delay.” (a) it is made with the agreement of all the other parties to the proceedings, or (b) it is made with the permission of the tribunal and the court is satisfied – (i) that the determination of the question is likely to produce substantial saving in costs, and (ii) that the application was made without delay.”
“Whether or not the Purchaser’s response contained in either: (a) Bargate Murray’s letter dated11 October 2017 , or (b) alternatively, Bargate Murray’s letter dated24 October 2017 , to the Builder’s settlement offer contained in Reed Smith’s letter dated9 October 2017 , in light of the legally relevant exchanges between 9 October and30 November 2017 , created a binding and enforceable Settlement Agreement between the Purchaser and the Builder.”
“This sets out the Builder’s offer to settle all and any claims of whatever nature, whether known or unknown arising out of the aforementioned SBC [shipbuilding contract] (including those pending in the present arbitration) by way of the payment of a liquidated sum. … Replacement Works The Builder remains of the view that no further works are required to implement a full and complete repair to the Vessel’s paint system, than the works offered in the Builder’s part 36 offer of9 July 2014 . However, in the interests of arriving at a commercial settlement of this claim (which is, in any case, a claim for specific performance of the warranty works), the Builder is prepared to perform the repair works which the Purchaser has stated in its [sc. letter] of8 September 2017 are necessary, and according to which the Purchaser’s offer of8 September 2017 was calculated. That is to say, the Builder is prepared to remove the paint system, and replace it with the same or an equivalent paint system, including any with widely-available commercial superyacht fairing compound, and the same topcoat colour scheme as presently applied, in the following areas of the Vessel (‘the Replacement Works’): … In all other respects, the Builder is prepared to conduct the Replacement Works in the same manner, and on the same terms, as set out in the Builder’s part 36 offer of9 July 2014 , Schedule 1 to that letter, and the Builder’s clarification letter of29 July 2014 . Costs … in order to reach a commercial settlement of this dispute, the Builder is prepared to offer the Purchaser the sum of €… in respect of the Purchaser’s costs. … Offer in Full and Final Settlement In view of the foregoing, the Builder’s offer is as follows: 1. The Replacement Works; and 2. Costs – €… Accordingly, the total net payment to be made by the Builder, in addition to performing the Replacement Works at its own cost will be €… Additional Settlement Terms The conclusion of a final settlement will remain subject to the following terms: 1. A full release of any existing or future (known or unknown) claims arising out of or in connection with the SBC, whether against the Builder, B+V, or any other sub-contractor, and to include the Straub-coupling warranty claim. 2. The Purchaser formally to withdraw its deceit allegation(s) against the Builder and/or B+V and/or against any individual employed during the material time by the Builder and/or B+V (as a term of settlement). 3. Return and cancellation of all outstanding guarantees. 4. Conclusion of a formal settlement agreement to include, prior to signature, formal approval of the settlement by the competent corporate body of the Builder. Duration and implications of this Further Offer If this offer is accepted by the Purchaser, payment will be made by the Builder to a bank account nominated by the Purchaser within 14 days from the conclusion of the formal settlement agreement referred to above. Details of the Purchaser’s nominated bank account are to be provided to the Builder within 7 days from the conclusion of the formal settlement agreement. Given the proximity of the hearing date, this offer will remain open for acceptance until 17:00 on Wednesday11 October 2017 and, if not accepted, will expire and be withdrawn and will no longer be open for acceptance. In the event this offer is not accepted, the Builder reserves the right to bring this letter to the attention of the Tribunal in the context of any submissions as to how the Tribunal should exercise its broad discretion on the question of costs. In particular, in the event (as the Builder anticipates) the Tribunal orders the Builder to carry [sc. out] repair works which are equal to or less than the works specified in the Purchaser’s Offer of8 September 2017 , the Builder will invite the Tribunal to order that the Purchaser pays all of the Builder’s costs from11 October 2017 in any event on an indemnity basis. …”
“… the Further Offer is accepted by the Purchaser, subject only to the following points of clarification that are needed for logistical reasons: 1. The Further Offer does not say at which yard the work will be carried out. Can you please state which yard the Builder proposes to use? For the avoidance of doubt, the Purchaser would be prepared for that to be Blohm + Voss, or its new owner, Lurssen, or another European yard of comparable standing and quality. 2. The Further Offer is unclear about a start date for the work. For your information, the Purchaser’s preferred start date is about October 2018, after the next summer cruising season. We suggest, therefore, that the parties liaise about an exact date convenient to both parties. 3. Whilst the Purchaser is content for the work to be overseen by Wrede, the Purchaser must have the right to send its own consultants to assist Wrede, and receive reports and updates from Wrede, as it is in the interests of both the Purchaser and the Builder that any further dispute be avoided. 4. We understand that the settlement requires approval from the Builder’s board. Whilst that is understood by the Purchaser, your and Mr Bracker’s recommendation ought, we assume, [sc. to] ensure it is forthcoming. Regarding the arbitration hearing, our view is that it should be adjourned sine die pending formal board approval. 5. The Further Offer, taking account of the foregoing points, should be set out in a formal short settlement agreement to be executed by both the Purchaser and the Builder (once board consent is obtained) and that settlement agreement must expressly provide it is in full and final settlement of all disputes and differences arising out of or in connection with the subject matter of the Arbitration, and all the further matters that you mention in your Further Offer. It must be common ground that neither party is ‘buying litigation’ in order to end this long running paint dispute.”
“This Deed is subject to the approval of the Board of the Builder, and it will only become valid and binding on the Builder when executed on its behalf by an authorised signatory(ies).”
“… The meaning of that phrase is well-known. What it means is that (a) neither party intends to be bound either in law or in equity unless and until a formal contract is made; and (b) each party reserves the right to withdraw until such time as a binding contract is made. It follows, therefore, that in negotiating on that basis [both parties] took the commercial risk that one or other of them might back out of the proposed transaction … In short a ‘subject to contract’ agreement is no agreement at all. …”
“The conclusion of a final settlement will remain subject to the following terms: … (4) Conclusion of a formal settlement agreement to include, prior to signature, formal approval of the settlement by the competent corporate body of the Builder”
“on the true construction of the settlement agreement, while the Builder was not obliged to perform the terms of the settlement before the formality of approval and execution of the contract had been dealt with, the Builder was bound in the meantime, to seek formal approval for those terms and not to do anything which would prevent approval of them from being granted.”