“It is the intention of the parties that the Activities will be performed by [Richmond] on a “cost plus” basis and that therefore, [Richmond] will not charge [Vinergy] anything more than the cost it incurs for the Activities plus the amount due to it pursuant to clause 2.3 ……and [Richmond] will furnish to [Vinergy] invoices and other documents in support of such costs it incurs for the Activities. In the event it is discovered that [Richmond] has breached the provisions of this clause, (1) [Richmond] shall within 3 days of demand from [Vinergy], reimburse the excess to [Vinergy] and (2) without prejudice to the foregoing or to any other right or remedy available to [Vinergy] under this Agreement or at law, [Vinergy] shall, notwithstanding clause 17 of this Agreement, be entitled to forthwith terminate this Agreement.”
“17.1 Either party may terminate this Agreement immediately upon: 17.1.1 failure of the other party to observe any of the terms herein and to remedy the same where it is capable of being remedied within the period specified in the notice given by the aggrieved party to the party in default, calling for remedy, being a period not less than twenty (20) days; …. 17.1.2 the other party suffering an Insolvency Event …….”
“18.2 Termination of this Agreement, including but not limited to Termination in accordance with Clause 17, will not prejudice the rights of action or remedy of [Vinergy] or [Richmond] in respect of any antecedent breach by the other party of any of such party’s obligations under this Agreement.”
“Richmond pleaded termination under Clause 17 as well as at common law but in their arguments before the Tribunal they placed the emphasis of their argument on the latter. It was clear that some of the claims, such as those for non-payment, were capable of remedy and the notice of termination on20th July 2012 was premature given that the initial notice to remedy was served on 2nd July and Clause 17.1.1 requires the parties to give notice of not less than 20 days to remedy before termination. This is, however, of limited relevance since Richmond also have common law rights to terminate on the ground of a repudiatory breach and these rights (and rights in respect of antecedent breaches generally) are expressly preserved by Clause 18.2 of the MSA.”
“Whether Richmond was able to rely on an unhindered common law right to terminate the MSA by reason of a repudiatory breach so as to completely bypass the notice and remedy requirements in the termination clause.”
“Those provisions themselves must in my judgment form part of an appreciation of the benefit the parties were intended to derive from the contract. Thus circumstances otherwise within the scope of the termination provisions but falling short of the precise terms would in my judgment not give rise to the right to terminate at common law for the very reason that the parties agreed when and how such circumstances should have that consequence: see Lockwood Builders v Rickwood.”
“……in deciding whether by its conduct a party evinces an intention not to be bound by the terms of the contract, the way in which parties agreed to treat breaches within the terms of their contract must be a factor to take into account. In particular, if a breach of a term had to reach a degree of seriousness before a contractual termination clause could be applied, it is unlikely that a breach which was less serious would, by itself, amount to a repudiatory breach.”
“In my view it is wrong to treat the right to terminate in accordance with the terms of the contract as different in substance from the right to treat the contract as discharged by reason of repudiation at common law. In those cases where the contract gives a right of termination they are in effect one and the same.”
“Equally, the fact that for a particular breach the contract provided that there should be a period of notice to remedy the breach would indicate that the breach without the notice would not, in itself, amount to a repudiatory breach.”
"My own view -- returning to the facts of the instant case -- is that cl 2 and the common law right to accept a repudiatory breach can exist side by side, but only in circumstances where the contractor displays a clear intention not to be bound by his contract, for example, by walking off the site long before completion (as suggested during the course of argument by Hirst LJ) or, by way of further illustration, failing to comply with plans in a very fundamental way, for example, by not building a third storey when contractually bound to do so. But such cases are far removed from the instant one. On the facts of this case, I, for my part, would be prepared to hold that cl 2 created the only effective way in which Mr Rickwood could determine this agreement. It is difficult to understand why the clause should be there at all if that were not the true position."
"In my judgment, this cl 2 did impliedly preclude Mr Rickwood from terminating the contract on the facts of the present case otherwise than by the exercise of his rights under cl 2 since the complaints made fell squarely within the scope of cl 2, ie complaints as to the quality of materials and workmanship. However, cl 2 would not have done so in relation to breaches outside the ambit of cl 2, eg. by Mr Ryan walking off the site when the works were still substantially incomplete."
“While the Tribunal has upheld the Respondent’s case that it is entitled to discretionary rebates, that item was the subject of a without prejudice agreement subject to which the Claimant provided an agreed fixed discount of US$5 per metric ton to the Respondent pending a decision in arbitration. The purpose of that agreement was to retain the status quo between the parties pending that decision. Although the tribunal has now determined that issue in favour of the Respondent and made a finding that an additional sum is due to the Respondent as a result, the Claimant is not thereby in breach of its obligation to perform the MSA.”
“At an early stage the parties were in dispute on the issue of rebates. They had intended to put the matter to an arbitrator for early determination, pending which they agreed on a without prejudice basis that Richmond would provide a discount of US$5 pmt but that this would be adjusted later in accordance with the arbitrator’s determination. In the event this process was not progressed at that early stage and neither party took the dispute to arbitration at that time. Hence it was that Richmond provided a discount of US$5 pmt to Vinergy from shipment 21 in January 2010 forwards, irrespective of the level of rebate earned or received by Richmond from Pasargad. That discount resulted in a total credit of US$153,238.47 to Vinergy.”