"The Drilling Unit shall be fully equipped as set out in Appendix 1 and shall be adequate to conduct the Well Operations at the locations specified by Amoco. The Drilling Unit and all other equipment, materials and supplies hereinafter specified as being supplied by the Contractor shall be certified and maintained in first class working condition, shall be suitable for their intended purpose, shall conform to all relevant laws and specifications and, together with the personnel, shall be furnished and maintained by Contractor at its sole cost ...."
"This Contract may not be terminated by CONTRACTOR except for non-payment by AMOCO ...."
"the BOP remains to be stripped down at least for partial inspection in order to ascertain whether any damage has been caused by fluid contamination. A more complete inspection may be necessary dependent upon initial results"
"CARs cover some of the major concerns listed above. Good progress has been made in progressing CARs since arrival at Rotterdam and there are now 12 out of 58 still in the 'not done' category. Copies are attached ...."
"In the morning of 19 January representatives of Amoco attended on board the rig and requested an extensive test to demonstrate the operability of the rig. Although such a test was not required by the Agreement BAO agreed to perform such a test"; and that "the alleged breakdowns are, on proper analysis, without substance. In any event it is absurd to suggest that BAO would not, and did not, seek to address each and every concern Amoco raised. To do otherwise would potentially jeopardise a contract under which BAO had spent over 2 years constructing a rig at a cost in excess of$200m , transporting it to the North Sea and arranging for it to operate for a period of at least 12 months. To assert further that BAO repudiated the Agreement in these circumstances is a nonsense." iii) It addressed and refuted the allegations about the BOP including stating that: "
"The jacking system, see comment, did cause concern during the team's early days at Sabine Pass, due to higher than expected failure rates of gears and pinions. The latest jacking operations have, however, been satisfactory. We have formally requested by memo to the Rig Manager (Mr Quinn) a copy of the report of Rowan's investigations into these failures." ii) Action: "
"Visually inspect storm locking mechanism. Function test at least once" with Rowan's comment "
“when I saw these dimensions quoted of 1.2 and 1.5mm my engineering judgment said ‘This cannot be true’”
“From a metallurgical viewpoint, I believe that the information regarding the properties and quality of the remaining pinions available at January 1999 meant that they could not be considered suitable for service without further evaluation….”
"... perform functions tests. Closing times satisfactory and ADC do not foresee problems with BOP Acceptance."
"Reservoir inspected and found large deposits of metal and other unidentifiable materials. Sample provided for further inspection"
"it did not contain rust. It contained the type of debris it is put there to catch"
"sure we had room to improve and we was going to improve"
"The Drilling Unit shall be fully equipped as set out in Appendix 1 and shall be adequate to conduct the Well Operations at the locations specified by Amoco. The Drilling Unit and all other equipment, materials and supplies hereinafter specified as being supplied by the Contractor shall be certified and maintained in first class working condition, shall be suitable for their intended purpose, shall conform to all relevant laws and specifications and, together with the personnel, shall be furnished and maintained by Contractor at its sole cost ...."
"This Contract may not be terminated by CONTRACTOR except for non-payment by AMOCO ...."
"the BOP remains to be stripped down at least for partial inspection in order to ascertain whether any damage has been caused by fluid contamination. A more complete inspection may be necessary dependent upon initial results"
"CARs cover some of the major concerns listed above. Good progress has been made in progressing CARs since arrival at Rotterdam and there are now 12 out of 58 still in the 'not done' category. Copies are attached ...."
"In the morning of 19 January representatives of Amoco attended on board the rig and requested an extensive test to demonstrate the operability of the rig. Although such a test was not required by the Agreement BAO agreed to perform such a test"; and that "the alleged breakdowns are, on proper analysis, without substance. In any event it is absurd to suggest that BAO would not, and did not, seek to address each and every concern Amoco raised. To do otherwise would potentially jeopardise a contract under which BAO had spent over 2 years constructing a rig at a cost in excess of$200m , transporting it to the North Sea and arranging for it to operate for a period of at least 12 months. To assert further that BAO repudiated the Agreement in these circumstances is a nonsense." iii) It addressed and refuted the allegations about the BOP including stating that: "
"The jacking system, see comment, did cause concern during the team's early days at Sabine Pass, due to higher than expected failure rates of gears and pinions. The latest jacking operations have, however, been satisfactory. We have formally requested by memo to the Rig Manager (Mr Quinn) a copy of the report of Rowan's investigations into these failures." ii) Action: "
"Visually inspect storm locking mechanism. Function test at least once" with Rowan's comment "
“when I saw these dimensions quoted of 1.2 and 1.5mm my engineering judgment said ‘This cannot be true’”
“From a metallurgical viewpoint, I believe that the information regarding the properties and quality of the remaining pinions available at January 1999 meant that they could not be considered suitable for service without further evaluation….”
"... perform functions tests. Closing times satisfactory and ADC do not foresee problems with BOP Acceptance."
"Reservoir inspected and found large deposits of metal and other unidentifiable materials. Sample provided for further inspection"
"it did not contain rust. It contained the type of debris it is put there to catch"
"sure we had room to improve and we was going to improve"