“ The word ‘condition’ may refer either to an event, or to a term of a contract….Where ‘condition’ refers to an event, that event may be either an occurrence which neither party undertakes to bring about or the performance by one party of his undertaking. The first possibility is illustrated by a contract by which A is to work for B and B is to pay A£50 , ‘if it rains tomorrow’. Here the obligations of both parties are contingent on the happening of the specified event which may therefore be described as a contingent condition. The second possibility is illustrated by the ordinary case in which A agrees to work for B at a weekly wage payable at the end of the week. Here the contract is immediately binding on both parties, but B is not liable to pay until A has performed his promise to work. Such performance is a condition of B’s liability and, as A has promised to render it , the condition may be described as promissory…..”
“If the bank can send us today the letter of credit, the contract is accepted”
“…made no comment or inference that due to the inconsistencies in the offered Letter of Credit that there was no contractual obligation between the parties. ….[URP] only pointed out the mistakes that they wanted to be rectified….”
“6.18 We believe that neither of these two potential conditions precedent to a binding contract would make commercial sense. 6.19 If there was an agreed commodity, price, volume, shipment period and origin (as is the case here) and the opening of the Letter of Credit were to be a condition precedent to the Contract being binding, then Buyers would simply not open the Letter of Credit if the market moved down and Sellers would have no recourse. 6.20 If there was an agreed commodity, price, volume, shipment period and origin (as is the case here) and the delivery of the POP Certificate were to be a condition precedent to the Contract being binding, then Seller would simply not deliver the POP if the market moved up and Buyers would have no recourse. 6.21 Neither scenario, in the Board’s view, would have been contemplated at the time of negotiations. WE THEREFORE FIND THAT neither the opening of the Letter of Credit nor the delivery of the POP Certificate was a condition precedent to the contract being binding. ”
“…a condition precedent to the opening of the Letter of Credit. In other words, Sellers were under the contractual obligation to deliver the POP Certificate….and only then were Buyers under the contractual obligation to open the Letter of Credit.”
“ s.31 (1) An objection that the arbitral tribunal lacks substantive jurisdiction at the outset of the proceedings must be raised by a party not later than the time he takes the first step in the proceedings to contest the merits of any matter in relation to which he challenges the tribunal’s jurisdiction…. s.73 (1) If a party to arbitral proceedings takes part, or continues to take part, in the proceedings without making, either forthwith or within such time as is allowed by the arbitration agreement or the tribunal or by any provision of this Part, any objection – (a) that the tribunal lacks substantive jurisdiction…. he may not raise that objection later, before the tribunal or the court…..” (Italicisation added.) s.73 he may not raise that objection later, before the tribunal or the court…..”
“s.31 (4) Where an objection is duly taken to the tribunal’s substantive jurisdiction and the tribunal has power to rule on its own jurisdiction, it may – (a) rule on the matter in an award as to jurisdiction, or (b) deal with the objection in its award on the merits. s.73 (2) Where the arbitral tribunal rules that it has substantive jurisdiction and a party to arbitral proceedings who could have questioned that ruling - (a) by any available arbitral process of appeal or review, or (b) by challenging the award, does not do so, or does not do so within the time allowed by the arbitration agreement or any provision of this Part, he may not object later to the tribunal’s substantive jurisdiction on any ground which was the subject of that ruling. ”
“…an objection later than the time specified in subsection (1) or (2) if it considers the delay justified.”
“ Unless otherwise agreed by the parties, an arbitration agreement which forms or was intended to form part of another agreement …..shall not be regarded as invalid, non-existent or ineffective because that other agreement is invalid, or did not come into existence or has become ineffective, and it shall for that purpose be treated as a distinct agreement.”
“ 19. Prior to the coming into force of the 1996 Act the English courts had worked out a doctrine of separability, as expressed in Harbour Assurance Co. (UK) Ltd. v Kansa General Insurance Co. Ltd. …, the substance of which was that, if the scope of an arbitration clause were sufficiently wide to cover the dispute, an arbitrator would, because of the separability of the agreement to arbitrate, have jurisdiction conclusively to determine whether the matrix contract was void ab initio, for example on the grounds of fraud or illegality, or was voidable, for example for misrepresentation or repudiatory breach. This jurisdiction was held to exist provided always that there was a binding agreement to arbitrate. The essence of the separability doctrine was that of insulation of the agreement to arbitrate from the matrix contract to the effect that the agreement to arbitrate would not be rendered void or invalid or avoided solely because the matrix contract was void or invalid or had been avoided. Unless the agreement to arbitrate was independently void or invalid, that agreement would remain in effect and the arbitrator could determine conclusively whether the matrix contract was enforceable. Thus, for example,…..if the matrix contract were illegal and void, that matter of illegality could be conclusively determined by the arbitrator unless the agreement to arbitrate was also independently rendered illegal and void by the legislation in question. However, where one of the parties to the arbitration had not agreed to become a party to the matrix contract it could invariably be said that the party in question was not bound by the arbitration agreement. That, however, is quite different from a case of statutory illegality, which renders the matrix contract void. 20. Section 7 of the 1996 Act reflects this concept of separability. Its effect in substance is to confirm that arbitrators have jurisdiction conclusively to determine issues on the voidness or voidability of the matrix contract to the effect that they do not lose jurisdiction by reason only that the matrix contract may be void or voidable. However, s.7 leaves intact the requirement that the arbitration agreement should be valid and binding. If it is not valid and binding for reasons other than the bare fact that the matrix contract is not valid and binding, then s.7 does not enable arbitrators to exercise conclusive jurisdiction in respect of any issue relating to the matrix contract…… ”
“17. The principle of separability enacted in section 7 means that the invalidity or rescission of the main contract does not necessarily entail the invalidity or rescission of the arbitration agreement. The arbitration agreement must be treated as a ‘distinct agreement’ and can be void or voidable only on grounds which relate directly to the arbitration agreement…. 18. …..Even if the allegation is that there was no concluded agreement (for example, that terms of the main agreement remained to be agreed) that is not necessarily an attack on the arbitration agreement. If the arbitration clause has been agreed, the parties will be presumed to have intended the question of whether there was a concluded main agreement to be decided by arbitration. 19. ….Mr Butcher QC, who appeared for the owners, said that but for the bribery, the owners would not have entered into any charter with the charterers and therefore would not have entered into an arbitration agreement. But that is ….exactly the kind of argument which section 7 was intended to prevent. It amounts to saying that because the main agreement and the arbitration agreement were bound up with each other, the invalidity of the main agreement should result in the invalidity of the arbitration agreement….. ”
“ (1) A party to arbitral proceedings may ….apply to the court challenging an award in the proceedings on the ground of serious irregularity affecting the tribunal, the proceedings or the award….. (2) Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant – (a) Failure by the tribunal to comply with section 33 (general duty of tribunal);”
“ (1) The tribunal shall – (a) act fairly and impartially as between the parties, giving each party a reasonable opportunity of putting his case and dealing with that of his opponent….. (2) The tribunal shall comply with that general duty in conducting the arbitral proceedings, in its decisions on matters of procedure and evidence and in the exercise of all other powers conferred on it.”
“There are no reasons for the Board to consider any issues after this date.”
“Attempts by Sellers to anyhow further try to execute the Contract and the fact that Buyers would most probably have accepted such an execution to replace the invoices for default damages (in a sharply rising market) do not alter the fact that the Contract was terminated on20 December 2006 and that the only remaining contractual right of Buyers was to receive payment of these default damages. ”
“ ….one cannot have it both ways: on the one hand declare the contract at an end on20 December 2006 and invoice default damages in the total amount of US$1,439,432.00 (and keep sending reminders of this invoice) and on the other stimulate a seller to execute a no longer existing contract (at a low contract price compared to a sharply rising market); i.e., never officially reopen the contract but then still declare the seller in default when it becomes clear that he cannot execute this tonnage; and then ‘replace’ the old default damage invoice with a new one that is about US$2,000,000 higher.”
“ Any application or appeal must be brought within 28 days of the date of the award or, if there has been any arbitral process of appeal or review, of the date when the applicant or appellant was notified of the result of that process.”
“….It is possible that the time limit in Clause 70(3) will have expired by the time an award is released. However, the DAC is of the view that the date of the award is the only incontrovertible date from which the time period should run. Any other starting point would result in great uncertainty (e.g. as to the exact point at which an award is ‘released’ or ‘delivered’). Further, any difficulties arising from specific circumstances can be easily remedied by way of an extension of time …..”