“In determining what did happen in the past a court decides on the balance of probabilities. Anything that is more probable than not it treats as certain. But in assessing damages which depend upon its view as to what will happen in the future or would have happened in the future if something had not happened in the past, the court must make an estimate as to what are the chances that a particular thing will or would have happened and reflect those chances, whether they are more or less than even, in the amount of damages which it awards.”
“The rule of common law is that where a party sustains a loss by reason of a breach of contract he is, so far as money can do it, to be placed in the same situation with respect to damages as if the contract had been performed.”
“As a result of the activities carried out by ABB through their participation in the Cartel from1 April 2000 to17 October 2008 , BritNed: (a) paid a price under the Agreement that was unlawfully inflated above the price which would have prevailed had there been no Cartel.” 297. The Agreement in question is the contract between BritNed and ABB for the BritNed Works signed on21 May 2007 . 298. Both Mr Biro and Dr Jenkins, in considering the competitive price absent the Cartel, had used ABB’s data from before and after the Cartel: they have therefore proceeded on the basis that the competitive price is the price that ABB would have charged to BritNed absent the Cartel (the “ABB counterfactual price”). 299. Although its position is not clear, during the course of the trial BritNed may have posited a further counterfactual, based on the premise that a third party other than ABB would have won the project at a price lower than the ABB counterfactual price. 300. ABB submits that it is not open to BritNed to advance this argument for the first time during the course of the trial. It has not been considered by the experts and ABB has not had the opportunity to address it, by way of disclosure or factual or witness evidence.”
“To remedy the information asymmetry and some of the difficulties associated with quantifying harm in competition law cases, and to ensure the effectiveness of claims for damages, it is appropriate to presume that cartel infringements result in harm, in particular via an effect on prices. Depending on the facts of the case, cartels result in a rise in prices, or prevent a lowering of prices which would otherwise have occurred but for the cartel. This presumption should not cover the concrete amount of harm. Infringers should be allowed to rebut the presumption. It is appropriate to limit this rebuttable presumption to cartels, given their secret nature, which increases the information asymmetry and makes it more difficult for claimants to obtain the evidence necessary to prove the harm.”
“For the purposes of competition proceedings, it is to be presumed, unless the contrary is proved, that a cartel causes loss or damage.”
“In such a case [where witnesses were seeking to recall events and telephone conversations of five years earlier] memories may very well be unreliable; and it is of crucial importance for the judge to have regard to the contemporary documents and to the overall probabilities…”
“A decision shall be binding in its entirety. A decision which specifies those to whom it is addressed shall be binding only on them.”
“Article 1 The following undertakings infringed Article 101 of the Treaty and Article 53 of the EEA Agreement by participating, in a single and continuous infringement in the (extra) high voltage underground and/or submarine power cables sector:”
“This Decision shall be enforceable pursuant to Article 299 of the Treaty and Article 110 of the EEA Agreement. Done at Brussels…”
“(67) Adhering to the rules of the Cartel, from February 1999 onwards, the parties allocated projects according to their geographic region or customer. In addition, they exchanged information on prices and other commercially sensitive information in order to ensure that the designated power cable supplier or “allottee” would make the lowest price while the other companies would submit a higher offer or refrain from bidding or submit an offer that was unattractive to the customer. The parties installed reporting obligations to allow monitoring of the agreed allocations. Finally, the parties also implemented practices to reinforce the [Cartel] such as the collective refusal to supply accessories or technical assistance to certain competitors in order to ensure the agreed allocations.” (68) To ensure the implementation of the Cartel arrangements, the parties held periodical meetings and had contacts by email, telephone or fax. (69) Within the Cartel, and in line with [information pre-dating the infringement period], the European producers Nexans and Pirelli/Prysmian were normally referred to as “R” (“Regular”) members, the Japanese producers Sumitomo, Hitachi and JPS, Furukawa and VISCAS (and later also EXSYM) as “A” (“Associated”) members and the Korean companies LS Cable and Taihan as “K”
“Today, I had lunch with Dick Bos, project manager acquisition BritNed on TenneT side. Afterward, we had a short chat with Marco Kuijpers, the purchaser. They gave me the following feedback on our lost the order. Dick was very surprised that ABB gave a discount without a firm coupling of the package (cables + converters). The package was the trump card on which we should have won the order. In his perception (Dick has been a professional BtB salesman in aviation) this was our biggest mistake and really opened the door to go with Siemens!”
“We do not understand why ABB gave away the discount€10m for the Lot 2.”
“ABB has no ship or strategic relationship for the provision of a ship. However, the cable manufacturing capacity is smaller than cable laying capacity. Has to be taken care of during the tender phase.”
“Consequently, I do not think it is credible, and nor do I believe, that ABB’s representatives, including Peter Leupp, Hans-Åke Jönsson and Magnus Larsson-Hoffstein would have harboured any belief that Nexans and/or Prysmian were competing with them for Lot 2 or for Lot 3.”
“I am concerned about the process. We are helping BritNed to develop the Contract with great efforts and costs and still we will be squeezed in the BAFO. It may well be that some of our competitors will be awarded the Contract in the end.”
“As we said on the phone yesterday, Staffan, it feels terrible that we will probably lose yet another HVDC project. We now need to do everything we can do to win BritNed, if this still is possible. My ambition for getting as competitive a price as possible from us is to convince the bosses in Zürich etc. that we have to come in with a reasonable margin and risk provision. However, to succeed, I need your help: Staffan: When you have any more information about the Great Belt straight, such as who the low bidder is and what the difference is in price or greater differences on the technical solution for the Tfo’s, then I will gladly receive this. Staffan/Bo: I’d be pleased to hear any news about BritNed as I will try to work on the bosses from a number of angles. It is highly unlikely that we will have time to change our business model on this. We then will have to ensure that we work closely together in terms of our updated quotes for BritNed. As soon as I have a technical quote from our estimators, we can talk about this.”
“There is a risk that the people who decided what margins there should be in the project, if they were aware of the Cartel, they could decide on different margins”
“There is evidence that cost reporting differed during and after the Cartel period…It might be the case that the Selling, General and Administrative divisions at ABB were less efficient as a result of the Cartel, leading to inflated costs and a higher SGA mark-up…”
“At our last HVDC meeting, Hans-Ake and I concluded it would be good that we both pay a visit to Mel Kroon (and possibly Lex Hartman). Each time I meet Mel Kroon he makes clear to me he is worried not to get competitive prices from ABB (factory full…). We believe we should create clarity around that issue now (in neutral time and proactively). I learned from Hans-Ake that it is anyhow to be expected that due to material price increases and a more sound cable market situation vs the days that NorNed was signed (nineties) the BritNed price could be some 20% higher versus the NorNed. The day Mel would hear from this, if we do not prepare that message upfront, he will definitely conclude: ABB are crooks! We want to avoid this.”
“TenneT experiences ABB as too arrogant with its pricing of the cable of • BritNed – 70% price increase in comparison with NorNed • NorNed 10km additional cable – 100% price increase in comparison with NorNed”
“81. Carrying out a regression analysis requires knowledge of various statistical techniques to measure the relationship between variables, to construct an appropriate regression equation and to calculate the precision of the parameters in this equation. In addition, it is necessary to have a good understanding of the industry concerned, in the first place, to formulate the right hypothesis when constructing the regression equation and to make the right choice as to the factors that are likely to have significantly influenced the variable of interest (and which should therefore be included in the analysis). Industry understanding is furthermore necessary to make informed choices about which statistical techniques to use in a given situation, for instance, to account for unusual observations (outliers) or other specific features in data sets. In particular, where the influencing variables were themselves affected by the infringement, biased results may occur if this aspect is not taken into account, e.g. through applying specific statistical techniques or through using data observations that lie outside the infringement period or market. 82. Without a sufficient number of data observations, statistical analysis cannot identify relationships between economic variables. To identify the effect of influencing variables on the variable of interest therefore requires that a sufficient range of data observations is available for all variables considered. Regression analysis therefore typically requires extensive data. However, statistical techniques may help to overcome some gaps in data or biases in their interpretation and there can be situations where also the analysis of a smaller number of data observations is meaningful. 83. Data observations can, in principle, be gathered at different levels of aggregation. For example, where the relationship between price and input cost is to be analysed, data series either for the prices charged in individual transactions, for annual industry average prices or – in between – monthly data at firm level could be examined next to data series either for individual input costs per unit or for industry cost averages respectively. Using disaggregated data makes it possible to analyse a greater number of observations and therefore to obtain more precise estimates. Where such disaggregated data do not exist or are not accessible to the party carrying out the regression analysis, the analysis of aggregated data may still produce informative results, in particular if the aggregated data have a high frequency. 84. Having a sufficient range of data observations and the level of data aggregation are examples of the importance of data reliability and data relevance for economic analysis. However, most datasets are incomplete, and not all relevant facts may be observed or measured with high accuracy. It is therefore proper to explicitly acknowledge those imperfections. Deficiencies in the data should not prevent an economic analysis from being given proper weight, though conclusions should be drawn with caution. 85. Where used appropriately and on the basis of sufficient data observations, regression analysis can considerably refine the damages estimation through comparator-based methods. It should be stressed, however, that even very sophisticated regression equations rely on a range of assumptions and will (like any technique to predict a hypothetical situation) only be able to deliver estimates. It is good practice to consider the assumptions underlying a regression equation, because some assumptions may be more appropriate than others in a given situation and may lead to significantly different results. 86. One way to deal with the uncertainty of the estimate is to indicate the results not as a point estimate (“the price in the non-infringement scenario is 10€”), but as an interval (“the price in the non-infringement scenario is between 9€ and 11€”). The notion of “confidence interval” – which is standard in statistics – is used to describe how likely it is that the true value is contained in an interval. By convention in economics, a 95% likelihood that a specific interval does in fact contain the true value is regarded as a high degree of certainty. 87. A similar way of dealing with the uncertainty of estimates is to refer to the notion of “statistical significance”, which is a standard way of testing whether the results obtained in a regression analysis are due to a coincidence or whether they reflect in fact a genuine correlation. For this, a certain hypothesis is tested: in the field of damages actions, such a hypothesis could for instance be whether the cartel infringement did in fact have an actual effect on prices or not. The hypothesis that the infringement did not have an effect (and that therefore the non-infringement price does not differ from the price in the infringement scenario) is called the “null hypothesis”
“In my assessment, I included a similar number of projects, both submarine and underground, procured during and after the Cartel. This means that I rely on information on projects supplied by ABB during the Cartel period other than BritNed and that my approach gives an estimate of the average effect of the Cartel on the HV cable projects sold by ABB during the Cartel period. Within my statistical framework, I am able to test whether the Cartel effect relating to the BritNed project itself is significantly different from the average effect I estimate, and I find that it is not.”
“…[t]he very object and scope of the contract were to give the plaintiff the chance of being selected as a prize-winner”
“As a result of the activities carried out by [ABB] through [its] participation in the Cartel from1 April 2000 to17 October 2008 , [BritNed]: … (c) incurred a further loss of profit by virtue of the (cartelised) bid price affecting the ultimate decision on the level of transmission capacity. In particular, the inflated prices proposed by [ABB] in Phase One of the procurement process resulted in the premature and unnecessary elimination of consideration for procurement of a higher transmission capacity interconnector than the 1,000 megawatt capacity that was eventually procured. The 1,000 megawatt lower capacity option selected resulted in a loss of profits due to the lost opportunity to auction additional units of capacity.”
“As the size of the interconnector is increased, its impact on market prices also increases. At a certain size (above 1,320MW), the annual revenues start to fall, and theoretically, if the link is sufficiently large, there is complete price convergence between the Netherlands and Britain. Our analysis shows that the link would have to be very large for this to occur: using our price elasticity values, link revenues peak at a capacity of around 2GW, then decline gradually. At 4GW, annual revenues would be similar to those for the 1GW link. Even at a capacity of 10GW, there is some residual value (around€10m per annum) and utilisation.”
“Question…knowing what we now know from ILEX would it be advisable to drop the 1,320MW option and allow the contractors time to concentrate on their 1,000MW bid? BritNed Board asked this question yesterday – my view is that we seem to be coming into a focus somewhere near 1,000MW plus a short-term overload capacity. The only reason I can see for continuing with prices for the 1,320MW option is for the sake of information for modelling/regulator purposes. We need the answer today, if possible, for the Board to consider – I suspect every day saved will help the contractors.”
“This presentation is intended to provide an update on the first stage of the Tender process for the BritNed Interconnector and present to the joint venture board members the recommendations from the Project Team, to approve these recommendations and therefore progress to Stage 2.”
“This Regulation aims at setting fair rules for cross-border exchanges in electricity, thus enhancing competition within the internal electricity market, taking into account the specificities of national and regional markets. This will involve the establishment of a compensation mechanism for cross-border flows of electricity and the setting of harmonised principles on cross-border transmission charges and the allocation of available capacities of interconnections between national transmission systems.” 513. Article 6(6) of Regulation 1228/2003 provides: “Any revenues resulting from the allocation of interconnection shall be used for one or more of the following purposes: (a) guaranteeing the actual availability of the allocated capacity; (b) network investments maintaining or increasing interconnection capacities; (c) as an income to be taken into account by regulatory authorities when approving the methodology for calculating network tariffs, and/or in assessing wither tariffs should be modified.”
“(1) New direct current interconnectors may, upon request, be exempted from the provisions of Article 6(6) of this Regulation and Articles 20 and 23(2), (3) and (4) of Directive 2003/54/EC The provisions of which are considered further below. under the following conditions: (a) the investment must enhance competition in electricity supply; (b) the level of risk attached to the investment is such that the investment would not take place unless an exemption is granted; (c) the interconnector must be owned by a natural or legal person which is separate at least in terms of its legal form from the system operators in whose systems that interconnector will be built; (d) charges are levied on users of that interconnector; (e) since the partial market opening referred to in Article 19 of Directive 96/92/EC, no part of the capital or operating costs of the interconnector has been recovered from any component of charges made for the use of transmission or distribution systems linked by the interconnector; (f) the exemption is not to the detriment of competition or the effective functioning of the internal electricity market, or the efficient functioning of the regulated system to which the interconnector is linked. … (4) (a) The regulatory authority may, on a case by case basis, decide on the exemption referred to in paragraphs (1) and (2). However, Member States may provide that the regulatory authorities shall submit, for formal decision, to the relevant body in the Member State its opinion on the request for an exemption. This opinion shall be published together with the decision. … (5) The exemption decision shall be notified, without delay, by the competent authority to the Commission, together with all the information relevant to the decision. This information may be submitted to the Commission in aggregate form, enabling the Commission to reach a well-founded decision. … Within two months after receiving a notification, the Commission may request that the regulatory authority or the Member State concerned amend or withdraw the decision to grant an exemption. The two months period may be extended by one additional month where additional information is sought by the Commission. If the regulatory authority or Member State concerned does not comply with the request within a period of four weeks, a final decision shall be taken in accordance with the procedure referred to in Article 13(3).” (a) the investment must enhance competition in electricity supply; (b) the level of risk attached to the investment is such that the investment would not take place unless an exemption is granted; (c) the interconnector must be owned by a natural or legal person which is separate at least in terms of its legal form from the system operators in whose systems that interconnector will be built; (d) charges are levied on users of that interconnector; (e) since the partial market opening referred to in Article 19 of Directive 96/92/EC, no part of the capital or operating costs of the interconnector has been recovered from any component of charges made for the use of transmission or distribution systems linked by the interconnector; (f) the exemption is not to the detriment of competition or the effective functioning of the internal electricity market, or the efficient functioning of the regulated system to which the interconnector is linked. (a) The regulatory authority may, on a case by case basis, decide on the exemption referred to in paragraphs (1) and (2). However, Member States may provide that the regulatory authorities shall submit, for formal decision, to the relevant body in the Member State its opinion on the request for an exemption. This opinion shall be published together with the decision. … Within two months after receiving a notification, the Commission may request that the regulatory authority or the Member State concerned amend or withdraw the decision to grant an exemption. The two months period may be extended by one additional month where additional information is sought by the Commission. If the regulatory authority or Member State concerned does not comply with the request within a period of four weeks, a final decision shall be taken in accordance with the procedure referred to in Article 13(3).”
“This Directive establishes common rules for the generation, transmission, distribution and supply of electricity. It lays down the rules relating to the organisation and functioning of the electricity sector, access to the market, the criteria and procedures applicable to calls for tenders and the granting of authorisations and the operation of systems.”
“Member States shall ensure the implementation of a system of third party access to the transmission and distribution systems based on published tariffs, applicable to all eligible customers and applied objectively and without discrimination between system users. Member States shall ensure that these tariffs, or the methodologies underlying their calculation, are approved prior to their entry into force in accordance with Article 23 and that these tariffs, and the methodologies – where only methodologies are approved – are published prior to their entry into force.”
“(a) BritNed has to present to the national regulators within ten years after start of operations (as defined in the exemption decisions) a report that contains all the details necessary to scrutinise the total costs and revenues of the project and the rate of return on the investment with 2007 as the base year allowing for comparison with data provided for the exemption request. (b) If, calculated on the basis of the first 10 years, the estimated internal rate of return for the entire project is more than one percentage point above the internal rate of return estimated when filing the exemption request, BritNed shall have two options: (i) It shall either increase the interconnector capacity to such an extent that the initially estimated rate of return is met. The additional capacity would not automatically be covered by the scope of the present exemption; or (ii) Alternatively, BritNed shall accept the profits (discounted to 2007) figures exceeding the initially estimated rate of return by more than one percentage point are capped and used, at equal parts, to finance the regulated asset base in the UK and in the Netherlands.” (i) It shall either increase the interconnector capacity to such an extent that the initially estimated rate of return is met. The additional capacity would not automatically be covered by the scope of the present exemption; or (ii) Alternatively, BritNed shall accept the profits (discounted to 2007) figures exceeding the initially estimated rate of return by more than one percentage point are capped and used, at equal parts, to finance the regulated asset base in the UK and in the Netherlands.”
“509. The submissions which have been set out above address the first question, namely whether BritNed has suffered any loss for which it should be compensated by an award of damages. For the reasons set out above, it is submitted that the effect of the IRR Cap is that BritNed would be no worse off absent the overcharge and consequently has not suffered any loss. 510. To be clear, it is not a necessary part of ABB’s argument that an award of damages would not be subject to the IRR Cap. It is not suggested that overcompensation arises by reason of the fact that the IRR Cap applies to BritNed’s revenues but not to any recovery by way of damages. Rather, overcompensation would arise if BritNed receives an award of damages in circumstances in which it is no worse off by reason of any overcharge. The effect of any overcharge is simply to permit BritNed to retain correspondingly greater revenues before being obliged to take steps to reduce its IRR. This means that BritNed has suffered no loss and no award of compensatory damages is necessary. This is the case irrespective of the regulatory treatment of any award of damages.”
“…given that the principal capital cost on [BritNed’s] balance sheet is the cost it incurred in commissioning the BritNed Interconnector Project, the inflated price it had to pay to [ABB] for the Works, by virtue of the unlawful actions of [ABB] and its fellow cartelists, led [BritNed] to incur higher capital costs than it would have incurred under competitive conditions.”
“319. Pleaded claim …BritNed’s pleaded claim for compound interest is that it bore higher capital costs than would have been the case absent the overcharge. 320. However, it is evident from BritNed’s financial accounts that it did not incur any higher capital costs, as it had not raised any debt funding since the start of the project in 2007…BritNed was in fact fully funded by its shareholders. BritNed has therefore not incurred any capital funding costs at all, let alone increased costs as a result of any overcharge. … 322. Shareholders’ losses At [Joint Statement/Issue 58], Dr Jenkins explains the basis of her analysis as follows: “To see this more clearly, without the overcharge, the equity investors would have invested a smaller amount in BritNed (as the required investment would have been smaller). As a result, the equity investors would have been able to invest the savings (which equals to the overcharge amount) in other projects to earn returns from them. As a result, the overcharge reduced the profits of the equity investors (or shareholders).”