“(1) Paragraph (2) applies if – a. the Court is satisfied that a decision or action taken by a utility was in breach of the duty owed in accordance with Regulations 45A or 45B; and b. the contract has already been entered into. (2) In those circumstances, the Court – (a) must, if it is satisfied that any of the grounds for ineffectiveness applies, make a declaration of ineffectiveness in respect of the contract unless Regulation 45L requires the Court not to do so…”
“45K – grounds for ineffectiveness (1) There are three grounds for ineffectiveness. The first ground (2) Subject to paragraph (3), the first ground applies where the contract has been awarded without prior publication of a notice in the Official Journal in any case in which these Regulations require the prior publication of such a notice. … The second ground (5) The second ground applies where all the following apply – (a) the contract has been entered into in breach of any requirement imposed by - (i) Regulation 33A (the standstill period) … (b) there has also been a breach of the duty owed to the economic operator in accordance with regulation 45A or 45B in respect of obligations other than those imposed by regulation 33A (the standstill period) and this Part; (c) the breach mentioned in sub-paragraph (a) has deprived the economic operator of the possibility of starting proceedings in respect of the breach mentioned in sub-paragraph (b) or, pursuing them to a proper conclusion, before the contract was entered into; (d) the breach mentioned in sub-paragraph (b) has affected the chances of the economic operator obtaining the contract.”
“33A - Standstill period”
“45E - Special time limits for seeking a declaration of ineffectiveness. (1) This regulation limits the time within which proceedings may be started where the proceedings seek a declaration of ineffectiveness. (2) Such proceedings must be started - (a) where paragraph (3) or (5) applies, within 30 days beginning with the relevant date mentioned in that paragraph; (b) in any other case, within 6 months beginning with the day after the date on which the contract was entered into.”
“(5) This paragraph applies where the utility has informed the economic operator of - (a) the conclusion of the contract; and (b) a summary of the relevant reasons in which case the relevant date is the day after the date on which the economic operator was informed of the conclusion or, if later, was informed of a summary of the relevant reasons. (6) In paragraph (5), ‘the relevant reasons’ means the reasons which the economic operator would have been entitled to receive in response to a request under regulation 33(9).”
“16 - Call for competition (1) Subject to regulation 17, for the purposes of seeking offers in relation to a proposed contract a utility shall make a call for competition. (2) The requirement under paragraph (1) to make a call for competition is satisfied - (a) In the case of a contract to be awarded using the restricted procedure or the negotiated procedure: … (ii) if a notice indicating the existence of a qualification system for economic operators has been sent to the Official Journal in accordance with regulation 25(17) and the requirement referred to in paragraph (5) is satisfied; or (b) in any case by sending to the Official Journal a contract in [a prescribed form] containing the information specified in respect of the contract. (5) The requirement referred to in paragraph (2)(a)(ii) is that the economic operators selected to tender for or to negotiate the contract are selected from the candidates which qualify in accordance with the system.”
“21. It should be noted that this particular ground has wider implications beyond the classic situation of a deliberately illegal direct award involving no transparency at all. For example: … (c) Where there has been an OJEU advertisement but the subsequent contract is outside the scope of the initial contract notice. (d) Where an existing contract is subjected to a variation, in the erroneous belief that the scope and scale of the change does not need a new OJEU advertisement.”
“(13) In order to combat the illegal direct award of contracts, which the Court of Justice has called the most serious breach of Community law in the field of public procurement on the part of a contracting authority or contracting entity, there should be provision for effective, proportionate and dissuasive sanctions. Therefore a contract resulting from an illegal direct award should in principle be considered ineffective …” (14) Ineffectiveness is the most effective way to restore competition and to create new business opportunities for those economic operators which have been deprived illegally of their opportunity to compete. Direct awards within the meaning of this Directive should include all contract awards made without prior publication of a contract notice in the Official Journal of the European Union within the meaning of Directive 2004/18/EC. This corresponds to a procedure without prior call for competition within the meaning of Directive 2004/17/EC.”
“ … alternatively, [Alstom relies] on the second ground in Regulation 45K (the First Defendant having failed to provide a standstill period as required by Regulation 33A in respect of the materially varied contract and having breached the Amended Regulations, by failing to hold a tender process in accordance therewith in relation to that contract).”
“By reason of the above breaches, the Claimant has been deprived of the opportunity to tender for the materially varied Contract; to tender for a contract with a clear baseline in relation to IGC requirements (present and future) and/or without the need for unqualified compliance with the fifth Mandatory Requirement; and/or to bid on the basis of the material amendments identified above.”
“For your information, I would add that your tender was also ranked highly for the qualitative evaluation criteria but was unsuccessful because of its price.”
“Have Siemens altered their bid (technical or price) since their appointment as Preferred Bidder: If so, when and how; has it affected their scores?”
“We do not consider that any material changes have been made to Siemens’ bid since its appointment as preferred bidder. We have provided you with detailed explanations and responses to your queries about the difference between Alstom’s and Siemens’ bids. Eurostar owes duties of confidentiality to Siemens in respect of its bid which it is not prepared to breach. You are not entitled to further information in this respect.”
“Is Siemens’ contract conditional upon the new rules: If so, how is that conditionality expressed.”
“The contract when signed will not be conditional on the introduction of new Tunnel Safety Rules concerning DP [distributed power]. It does however provide a mechanism for managing the risk of the relevant rule not changing. The issue is discussed in detail in the body of this letter. We are not prepared to disclose the detail of the relevant contract clauses as this is commercially sensitive and confidential. It is not necessary for Alstom to understand the award of the contract.”