“The court’s permission is required if a claimant seeks to rely on grounds other than those for which he has been given permission to proceed.”
“12.1 Where the claimant intends to apply for judicial review on grounds additional to those set out in the Claim Form, the claimant must make an application to the court for permission to amend the Claim Form. The application should be made in accordance with the requirements of Part 23. 12.2 The application must be made promptly and should include, or be accompanied by, a draft of the amended grounds and be supported by evidence explaining the need for the proposed amendment and any delay in making the application for permission to amend. 12.3 The application, the proposed additional grounds and any written evidence, must be served on the defendant and any interested party named in the Claim Form or Acknowledgement of Service.”
“An applicant must file an application notice unless- (a) a rule or practice direction states otherwise; or (b) the court dispenses with the requirement.” (a) a rule or practice direction states otherwise; or (b) the court dispenses with the requirement.”
“113. …is not an appropriate means of seeking to amend to rely on additional grounds of challenge. The claimant should have made an application to the court, accompanied by a draft of the proposed amendments to the claim form and supported by evidence, explaining the reason for the proposed amendment and any delay in making it: seeCPR 17.1 read with PD para 17.1 andCPR 23.6 read withPD23A para 9.1. See further,CPR 8 ,CPR 54.1 ,PD54A para 5.6 andCPR 2.3 . 114. We must emphasise that it cannot simply be assumed by those engaging in this type of litigation that permission will be given in the absence of compliance with the rules; and in the event, we refuse permission to amend the claim form to include this further ground of challenge for each of two separate reasons. First, the ground of challenge is unarguable. … Secondly, and separately, it would not be appropriate now to allow a challenge to events that occurred over a year or more ago, or to a decision taken in November 2018. The claim form, together with the grounds of claim, are required to be filed promptly and in any event within three months of the grounds of challenge first arising. The claimant did not include this ground in the claim form or in the first detailed set of grounds produced in March 2019 nor in the amended grounds set out in the document dated14 October 2019 . It is too late to raise this matter now.”
“The Member States shall in the first instance be responsible for investigating irregularities and for making the financial corrections required and pursuing recoveries.”
“For each Services element to be provided in this manner, the Tenderer shall identify in its response to question 2 of the Lot 2 Quality Questions a minimum of two Sub-Consultants, one of which must be a Cornish SME, which will be utilised to provide the Services. The identity of Sub-Consultants nominated shall be inserted into Schedule 27 of the Framework Agreement.”
“Applicants should note that procurements will be tested in detail in the lifetime of a project and by different independent bodies. In the event of non-compliance an irregularity will be declared, and a financial penalty will be imposed in line with EU guidance. This can be up to 100% of the irregular procurement expenditure. The managing authority therefore recommends that applicants seek appropriate legal and/or technical advice to ensure compliance.”
“This route will ultimately include a new Walking Cycling and Horse rider (WCH) bridge crossing the A30 at Chiverton. Due to the overlap with the main dual carriageway scheme the bridge would be implemented as a later phase, currently anticipated in late 2023, but both the Council and Highways England remain committed to its delivery.”
“CJP have been appointed as the main contractor for the A30 Chiverton to Carland improvements and are due to be on site from Autumn 2020 until December 2023 with the works fully open in 2023-2024. The A30 works in the Chiverton area include lowering the main carriageway by approx. 2m with significant earthworks and adjustment to the adjacent embankments in the area where the bridge would be located. This makes it exceedingly difficult for another contractor to be engaged to work in the same area, although not impossible and would be subject to agreement of HE. However the dualling works will have an impact on timings for the bridge construction and there is potential for the Council to incur a very large amount of risk/cost if we are to appoint another contractor and they caused any delay to the A30 works. There would be a need to work with [CJP] to align the projects, particularly with regard to the earthworks and traffic management regimes for potentially competing projects.” (Emphasis added.)
“a relatively quick way to appoint the contractor especially given they will be on site and working anyway. This approach has potential cost savings in economies of scale and construction activities such as traffic management and site compounds as well as protecting Cornwall Council from any of the risk associated in negatively impacting and delaying the site.”
“10.1 General (a) The Grant Recipient must comply and secure compliance with the Structural and Investment Funds Regulations and the Grant Recipient hereby warrants that it shall not act or omit to act in any way that may cause the Grant Recipient, a Delivery Partner or the Secretary of State to breach the Structural and Investment Funds Regulations. (b) Further to clause 10.1(a) the Grant Recipient shall ensure that in accordance with Article 6 of Regulation 1303, the Project complies with applicable European Union law and the national law relating to its application.”
“Irregularity means any breach of European Union law, or of national law relating to its application resulting from an act or omission by a Grant Recipient or a Delivery Partner (and/or its agents and subcontractors), which has, or would have, the effect of prejudicing the budget of the European Union by charging an unjustified item of expenditure to the budget of the European Union.”
“There is only one supplier capable of providing the relevant goods, works or services due to technical, artistic or copyright reasons.”
“Chiverton Bridge Justification as to why a Direct Award to the Costains Jacobs Partnership (the Contractor appointed by National Highways to design and construct the A30 Carland Cross to Chiverton Widening Project) is the only feasible procurement option in view of funding constraints”
“Although the open tender or IDA option would provide absolute comfort that the procurement arrangement complies with the National Procurement Guidelines, such arrangements could not deliver the Chiverton Bridge in a safe manner and in the same working space as the ongoing A30 project, and in the same construction period as the A30 project to achieve the ESIF funding deadline date.” (Emphasis added.)
“the programme for Chiverton Bridge is already significantly behind the overall programme for the A30 widening, and in particular, the construction of the nearby bridges for that project. The optimum time that the bridge would be constructed is now, along with the currently ongoing construction of the other A30 bridges. This delayed delivery will make the integration of the Chiverton Bridge in to the A30 project a retro-fit, so therefore more difficult. Although the detailed design for the A30 works is almost complete, the scale and associated complexity of the A30 works will require design support throughout the construction period. Managing the late inclusion of Chiverton Bridge in to the A30 design and construction in a way that also enables the programme for Chiverton Bridge to still be embedded into the evolving construction of the main A30 scheme will be difficult. Utilising the pre-existing design team who already have familiarity of the A30 design, along with the A30 construction programming team would be key to achieving this. With CJP having control of the site within which the bridge is located, and potentially still undertaking works to the main carriageway and Chiverton Junction until December 2023, then it is not possible to provide access to another contractor until the A30 works are complete. As stated previously, the funding deadline of December 2023 does not allow for the bridge works to be undertaken later. Therefore, if the Council cannot gain access to the construction site for another contractor until a time that is too late to deliver the bridge and meet the ESIF deadline, the engagement of CJP is then the only practical delivery option that would complete the bridge construction before the funding expires.” (Emphasis added.)
“A single contractor delivering both the A30 and the Chiverton Bridge would provide the best assurance that this can be achieved to ensure the safety of construction operations during the works period while safely maintaining traffic flows on the strategically important A30 Trunk road. Using a separate contractor to construct the bridge would potentially jeopardise both road safety and the safety of construction operations. … If a separate bridge contractor was involved then an extremely high level of coordination between both parties would be required to achieve a safe traffic flow arrangement that would still enable both the A30 and bridge construction works to be achieved. … With CJP’s focus primarily being on the delivery of the c.300M A30 project, it is extremely unlikely that any diversion from this to participate in engagement with a separate contractor for the c.£3M bridge would enable the delivery of the bridge by the ESIF deadline date.”
“Due to the programme constraint set by the funding, the ongoing A30 works and the programme for these works, traffic management and construction working area requirements of the A30 dualling scheme, only a single contractor (the A30 contractor) could undertake the additional construction operations to deliver the Chiverton Bridge project in a safe manner and in the same working space, and in the same construction period to achieve the funding deadline date. Although a tender process could be completed, the coordination between two contractors to deliver the bridge in the same programme as the A30 scheme, especially with regard to construction safety, highway safety, liaison with regulatory bodies and coordination of statutory undertakers, to achieve the same31st December 2023 deadline date would not be possible as the site will be under the control of the A30 contractor. If the Council cannot gain access to the construction site for any other contractor until a time that is too late to deliver the bridge and meet the ESIF deadline, then the engagement of CJP is the only practical delivery option that would complete the bridge construction before the funding expires.”
“Therefore, there is a risk of ESIF funding clawback in the sum of£2,677,649 (100% of the ESIF Funding value for the bridge…) should an auditor later consider that there has been a non-compliance with European Commission requirements. Should the project be progressed then this risk will be allowed for within the management of the overall capital programme by way of a risk pot.”
“an OTSV is not an external audit and does not constitute a definitive determination of compliance for the purposes of the programme as a whole. The MA’s verification activity does not replace the independent audit functions required under the EU regulatory framework, which are carried out by the GIAA.”
“The [Council’s] justification to use a STA [i.e. Single Tender Action] is ‘There is only one supplier capable of providing the relevant goods, works or services due to genuine technical, artistic or copyright reasons’. The [Council] obtained legal advice and completed a technical document explaining the justification for procuring through a Single Tender Action. There is also the Tender Evaluation & Whole Scheme Analysis. However, the supporting documentation does not fully justify there is only [one] supplier, as follows: Cornwall Council technical document – • ‘the engagement of CJP is then the only practical delivery option that would complete the bridge construction before the funding expires’. • Two contractors working on the same footprint is ‘extremely difficult or almost impossible’, however this is given the ‘tight deadline for the completion of both projects’. • ‘a tender process could be completed … [however] to achieve the same31st December 2023 deadline date would not be possible as the site will be under the control of the A30 contractor’. Tender Evaluation & Whole Scheme Analysis – • This report explains that to install the bridge ‘there are no specific restrictions to using CJP for this project. … CJP are the preferred supplier given their involvement in the overall design of the A30 dualling project’. Therefore, the reason for using CJP is the ESIF funding deadline and their involvement in the A30 dualling project, which are not STA justifications.”
“The terms of the Invitation to Tender (ITT) for The Cornwall Council Built Environment Professional Services Framework19th June 2018 requires where a tenderer intends to provide any service through sub-consultants to identify a minimum of two and ‘one of which must be a Cornish SME’ (para 3.7.2 ITT). The framework does not permit to ‘enter into Supply Chain frameworks with Sub-Consultants that were not submitted as part of the Consultant’s tender for this Framework’ (para 16.22). There were two bids for the framework, which included lists of sub-contractors respectively for the winning bidder MWJV and the other bidder KCCJV. Interestingly the winning bidder MWJV doesn’t list a Cornish sub consultant for the Building Surveying sub-consultant service, yet still won without fulfilling the selection criteria. Recommendation The AA will raise an irregularity under ERDF procurement irregularity type 10, use of restrictive criteria including regional or local preferences, rate of correction 25%.”
“The MA [i.e. Managing Authority] does not have discretion to ignore a substantial irregularity identified by the GIAA, that it then concludes was irregular. Ultimately, the MA has to reach its own view but – as is unsurprising – it takes seriously the conclusions of the GIAA, which is the expert body in this field. When the MA concludes that there is an irregularity, it has no discretion not to claw back: its obligation is to protect EU funds and ensure that only regular expenditure is declared.”
“The MA issued its payment recovery request on the same date as the final audit report was issued because it had formed its own assessment of the findings, following receipt of the GIAA’s draft report. The Article 127 audit process had also occurred right at the end of the ERDF programme’s life, with a result that there was something of a time premium in processing the results of the audit.”
“As a consequence of my experience, over a 15 year period involved in ERDF funding, I have considerable experience in reviewing and scrutinising project plans, proposals and designs for major infrastructure projects. I have reviewed and assessed many dozens of projects of this kind. This has included detailed discussion of project coordination and programme management including, on occasion, disputes in relation to those matters. I would estimate that I have had detailed insight into at least 20 substantial infrastructure projects and at least half a dozen major road projects in the last 15 years, as well as hundreds of projects of other kinds. I brought that experience to bear when assessing the issues set out below. The other aspect of my experience that is relevant to this case is my experience of the approach that the European Commission and European Court of Auditors (‘ECA’) takes when assessing ERDF funding irregularities. I knew from a number of disputes with the Commission and ECA that they take an exacting approach to these matters. … I came to the case fresh. … I independently reviewed the material submitted together with the documentation previously provided during the audit process and the information available to MHCLG in relation to the project. This included project documentation, internal reports produced by [the Council], correspondence relating to the procurement approach adopted, and the explanations provided by [the Council] in response to the Article 127 audit finding. … I was personally responsible for preparing and issuing the MA’s final decision letter dated14 May 2025 . I carefully reviewed, from scratch, the relevant background documents, and the Council’s representations and supporting evidence.”
“… the Council has not discharged the burden of proving that technical reasons made it absolutely necessary for the contract to be awarded to CJP and to none other. The reasons given are potential delay, existing contractual obligations, but the Council’s own documents show that other contractors could have possibly undertaken the works. Furthermore, the justification based solely on ESIF funding deadlines and CJP’s involvement in the A30 project does not meet the requirements for a single tender award under EU procurement rules. The single supplier route (Regulation 32) can only be justified where there is a genuine technical or operational requirement that limits the availability of other suppliers, which has not been adequately demonstrated in this case.”
“The Public Services (Social Value) Act 2012 does not override procurement rules. Instead it requires contracting authorities to consider how their procurement could improve the economic, social and environmental well-being of the area pre-procurement. The Act works in conjunction with procurement legislation, not in opposition to it. It does not affect the requirement for public bodies to comply with public procurement legislation and treat all contract bidders equally. The requirement for at least one Cornish SME as a sub-contractor in the procurement process could be considered to violate the principles of non-discrimination and equal treatment. While the rule does not explicitly exclude non-Cornish companies, it places them at a disadvantage, particularly those without local networks in Cornwall. This indirectly discriminates against businesses outside the region and could have deterred them from bidding.”
“constitutes an irregularity under EU law, irrespective of whether the winning bidder, MWJV, complied with the criterion or not. The mere existence of such criteria could have deterred potential bidders without Cornish sub-contractors, thus restricting competition.”
“Operations supported by the ESI Funds shall comply with applicable Union law and the national law relating to its application (‘applicable law’).”
“The negotiated procedure without prior publication may be used for public works contracts, public supply contracts and public service contracts in any of the following cases: (a) where no tenders or no suitable tenders or no requests to participate or no suitable requests to participate have been submitted in respect to an open procedure or a restricted procedure, provided that the initial conditions of the contract are not substantially altered and that a report is sent to the Commission where it so requests. … (b) where the works, supplies or services can be supplied only by a particular economic operator for any of the following reasons: (i) the aim of the procurement is the creation or acquisition of a unique work of art or artistic performance; (ii) competition is absent for technical reasons; (iii) the protection of exclusive rights, including intellectual property rights; The exceptions set out in points (ii) and (iii) shall only apply when no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters of the procurement. (c) in so far as is strictly necessary where, for reasons of extreme urgency brought about by events unforeseeable by the contracting authority, the time limits for the open or restricted procedure or competitive procedures with negotiation cannot be complied with. The circumstances invoked to justify extreme urgency shall not in any event be attributable to the contracting authority.” (Emphasis added.)
“Where the situation of exclusivity is due to technical reasons, they should be rigorously defined and justified on a case-by-case basis. They could include, for instance, near technical impossibility for another economic operator to achieve the required performance or the necessity to use specific know-how, tools or means which only one economic operator has at its disposal. Technical reasons may also derive from specific interoperability requirements which must be fulfilled in order to ensure the functioning of the works, supplies or services to be procured.”
“The European Structural and Investment Found (ESIF) procurement requirements clearly set out that the selection process must adhere to i) Public Procurement Law, ii) Treaty principles, or iii) National Rules, as appropriate. Specifically, the Public Sector Procurement Directive 2014/24 and thePublic Contracts Regulations 2015 (PCR 2015) provide a harmonised set of procurement rules aimed at ensuring equal opportunities for businesses across Europe. The PCR 2015, under Part 2, is applicable to contracts above the EU threshold, which is the case here. For contracts below threshold, the Treaty Principles of non-discrimination, equal treatment and transparency still apply by virtue of Chapter 6 of the ESIF National Procurement Requirements and Regulation 110 of the PCR 2015. Therefore, the procurement process followed by the Council is subject to these principles, regardless of the contract’s value.” (Emphasis added.)
“The mere presence within the decision of an immaterial error of law does not make the decision itself one which is to any extent unlawful…”
“How to apply the Treaty Principles 16. Contracts within the scope of the interpretative communication are required to apply ‘a degree of advertising sufficient to enable the … market to be opened up to competition and the impartiality of procedures to be reviewed’. In practical terms this means that the offer must be advertised on a forum allowing interested operators from other Member States to consider bidding and that the information in the advertisement must be sufficient to be reviewed, i.e. the advertisement sets out the specifications and the process that will be used to evaluate the bid. It is recognised that in rare cases an advertisement is not possible due to extreme urgency due to unforeseeable events or technical, artistic or exclusive rights issues. In such circumstances, the ESIF grant recipient should complete the form at Annex 2. 17. The Interpretative Communication does not set out how the opportunity is to be advertised, except that the scope of the advertising needs to be appropriate. As a guide, the department expects the following requirements to be followed for all contracts subject to the Treaty Principles: Value of contract Minimum Procedure Advertising Required£0 -£2,499 Direct award None£2,500 -£24,999 3 written quotes or prices sought from relevant suppliers of goods, works and services None£25,000 – Relevant public Contracts Regulations threshold Formal tender process in line with the Interpretative Communication and the relevant guidance set out below 1) Advertised on Contracts Finder, and 2) the opportunity is advertised on the ESIF grant recipient’s website for a reasonable time period.”
“A procurement shall not be subdivided with the effect of preventing it from falling within the scope of [Part 2], unless justified by objective reasons.”
“The reasons for a decision must be intelligible and they must be adequate. They must enable the reader to understand why the matter was decided as it was and what conclusions were reached on the ‘principal important controversial issues’, disclosing how any issue of law or fact was resolved. Reasons can be briefly stated, the degree of particularity required depending entirely on the nature of the issues falling for decision. The reasoning must not give rise to a substantial doubt as to whether the decision- maker erred in law, for example by misunderstanding some relevant policy or some other important matter or by failing to reach a rational decision on relevant grounds. But such adverse inference will not readily be drawn. The reasons need refer only to the main issues in the dispute, not to every material consideration. They should enable disappointed developers to assess their prospects of obtaining some alternative development permission, or, as the case may be, their unsuccessful opponents to understand how the policy or approach underlying the grant of permission may impact upon future such applications. Decision letters must be read in a straightforward manner, recognising that they are addressed to parties well aware of the issues involved and the arguments advanced. A reasons challenge will only succeed if the party aggrieved can satisfy the court that he has genuinely been substantially prejudiced by the failure to provide an adequately reasoned decision.”
“…the central issue in this case is whether the decision of the Secretary of State leaves room for genuine as opposed to forensic doubt as to what he has decided and why. This is an issue to be resolved as the parties agree on a straightforward down-to-earth reading of his decision letter without excessive legalism or exegetical sophistication.”
“CJP would have had (1) an entitlement to unimpeded access to the site on which it was due to carry out the construction works, and (2) an obligation to carry out the construction works in accordance with the contract programme (failing which it would have been subject to delay liquidated damages).”
“In Commission audits, the burden of proof lies on the Commission to demonstrate that there would have been cross border interest.”
“Existence of a certain cross border interest For the purpose of assessing the existence of a certain cross border interest in contracts not subject to the Directives, the Commission carries the burden of proof, taking into account the jurisprudence of the European Court of Justice. In this context, it is first necessary to determine whether there are factual elements that would in conjunction substantiate cross border interest, including the following: (i) the subject-matter of the contract, (ii) its estimated value, (iii) the technical requirements of the contract, (iv) the geographic location of the place of performance, (v) evidence of tenders from other Member States or expressed interest by economic operators from a different Member State.”
“See judgment C-507/03 Commission v Ireland, 2007 ECR I-1977, paras 32 and 34. See also cases C-412/04 Commission v Italy[2008] ECR I-619 ; joined cases C-147/06 and C-148/06, SECAP SpA and Santorso Soc v Commune di Torino[2008] ECR I-3565 .”
“13. ESIF grant recipients are strongly encouraged to investigate whether their contract will be of cross border interest at the start of any procurement process. Those wishing to make the argument should complete the form at Annex 3, prior to letting the contract, and submit this to the relevant Department. 14. The evaluation as to whether a contract may generate cross border interest must be made by the ESIF grant recipient, taking into account the individual circumstances of the case, such as the subject matter of the contract, its estimated value, the specifics of the sector concerned (size and structure of the market, commercial practices), the geographic location of the place of performance and relevant market information. 15. The assessment of the existence of cross border interest must be taken prior to letting the contract and therefore to be valid, the form must be signed and dated. The reasons why the ESIF grant recipient believes there is no cross border interest should be set out alongside relevant supporting evidence.”