"areas designated for the protection of habitats or species where the maintenance or improvement of the status of water is an important factor in their protection, including relevant Natura 2000 sites designated under Directive 92/43/EEC(1) [the Habitats Directive] and Directive 79/409/EEC(2) [the Wild Birds Directive] ."
"Measures taken pursuant to this Directive shall be designed to maintain or restore, at favourable conservation status, natural habitats and species of wild fauna and flora of Community interest."
"(h) for diffuse sources liable to cause pollution, measures to prevent or control the input of pollutants…."
"4. When this case was opened I had a discussion with Mr Wolfe as to what could be achieved by this litigation. I am glad to say that it was agreed, at my suggestion, that the defendants should put in, effectively, a one-page document identifying precisely the basis upon which they said they would be acting so that Mr Wolfe could attack that to the extent that he considered it necessary to do so. There has been an adjournment and the parties have, in the end, reached agreement as to what the defendant should declare they propose to do. On that basis, which will form part of the order of the court, the claim has been withdrawn."
" CONSENT ORDER UPON the Defendants having set out their position in the attached Schedule IT IS ORDERED BY CONSENT: 1. The claim is withdrawn other than for the purposes of enforcing the Schedule. 2. Liberty to the parties to apply in relation to the enforcement of the Schedule. SCHEDULE DEFRA/Environment Agency Position Statement It is not true that the Secretary of State and Environment Agency do not intend to apply WPZs. As the draft RBMP (30 October 2015 ) states in the "
"26. …. the particular challenges of diffuse water pollution ("
"We have been working together with Natural England to look at how we can comply with the Consent Order. We have decided that the DWPPs are the best vehicle to publish the results of the analysis (SIPs are very high level and it would be difficult to capture the options/evidence within them). Over the next 3-4 years the following will need to be completed for all N2K DWPPs: A. Complete any investigations needed to fill essential gaps in evidence to understand the problem and the sources. B. Complete options appraisal of all mechanisms needed to achieve protected area objectives, including assessing their effectiveness and costs. C. Update DWPPs to include the above assessment and actions to take forwards the identified mechanisms." ii) An internal Environment Agency paper headed "
"….In November 2015, a Consent Order was agreed that requires the Environment Agency, working with Natural England (NE) to evaluate and identify the measures necessary to achieve protected area objectives in each N2K site that is unfavourable due to diffuse water pollution. This includes: An assessment of how far the existing measures and mechanisms to tackle diffuse water pollution will lead to the necessary improvements in water quality to meet the conservation objectives of these sites. If these are adjudged to be insufficient, the appraisal of alternative measures and mechanisms, including WPZs. The publication of the results as an appendix to the Diffuse Water Pollution Plans (DWPP), jointly owned by NE and Environment Agency …."
"Looking at the matter first without reference to the authorities, I should have thought that the meaning of the expression concerned, in the context in which it is used, was fairly clear. The performance of an act, in this case the presentation of a complaint, is not reasonably practicable if there is some impediment which reasonably prevents, or interferes with, or inhibits, such performance. The impediment may be physical, for instance the illness of the complainant or a postal strike; or the impediment may be mental, namely, the state of mind of the complainant in the form of ignorance of, or mistaken belief with regard to, essential matters. Such states of mind can, however, only be regarded as impediments making it not reasonably practicable to present a complaint within the period of three months, if the ignorance on the one hand, or the mistaken belief on the other, is itself reasonable. Either state of mind will, further, not be reasonable if it arises from the fault of the complainant in not making such inquiries as he should reasonably in all the circumstances have made, or from the fault of his solicitors or other professional advisers in not giving him such information as they should reasonably in all the circumstances have given him."
"It is open to the Government to have regard to its overall budget and the other calls upon its resources in deciding what steps to take in implementation of the strategy, including its requirement that efforts should be made to achieve the 2010 and 2016 targets as far as reasonably practicable."
"57 … the courts recognise that they are not well placed to question the judgement made by either the executive or the legislature in relation to matters of public expenditure. This is both on the ground of relative institutional competence and on the ground of democratic legitimacy. The allocation of scarce or finite public resources is inherently a matter which calls for political judgement. This does not mean that the courts have no role to play but it does mean that they must tread with caution, affording appropriate weight and respect to the judgement formed by the executive or the legislature. …… 80. ….this is an area in which the Respondent had to make difficult choices, in straitened financial circumstances, as to its priorities for public expenditure. It is better placed than the Court can ever be to know the needs of its local area and its residents. If cuts cannot be made to the budget in one context, they are likely to be necessary in some other context and will affect other people, who are not before the Court. Even if no cuts had to be made elsewhere, the gap in public finances would have to be filled in some other way, typically by raising taxes or borrowing, even assuming that those options are available. These methods all have consequences for other people. Sometimes this is called a "polycentric" issue, to use the word made famous by Prof. Lon Fuller, 'The Forms and Limits of Adjudication' (1978) 92 Harv. LR 353. This point goes to the relative institutional competence of the Respondent as compared with the Court…"
"In my view the phrase "so far as reasonably practicable" in paragraph 8 is sufficiently general for it to embrace matters additional to the physical feasibility of planting replacement trees of the same maturity. In this area there is very little nowadays which is not physically feasible if enough money is spent. Hence in this context the phrase is apt to include financial considerations."
"21. In the summer of 2016, the Agency provided a prioritisation of sites based on a set of categories which would determine the phasing of the work necessary to comply with the WFD obligations. The Claimants expected, at the very least, that measures including WPZs (where appropriate) would be applied promptly for the 'category 1 sites' – where the Agency said it already had the evidence available to make decisions about effective measures. Five pilot sites were included in this category. 22. A progress report published by the Agency in September 2016 … indicated that all steps for the category 1 sites would be completed by March 2017. That report also stated that " [o]ver the next 4 years (until March 2020) the following actions will need to be completed by Area for all 36 N2K DWPP/NMP (note that some Areas have already completed some steps): Step A: Complete any investigations needed to fill gaps in evidence to understand the problem and the sources. Step B: Complete options appraisal of measures and mechanisms which could achieve protected area objectives. Step C: Update DWPP (or NMP) to include above assessment and agreed actions to take forward the preferred option. " …. 23. However, a year later, in a further document published by the Agency in August 2017 ("
"30. The six-monthly 'DWPP site progress updates' provided by the Department to the Claimants categorise each site as follows: Green (denoting that work is on track or completed), Amber (denoting slowed progress), Red (denoting that activity has 'stopped' or 'slowed' or the completion date is yet to be confirmed). 31. Three of the most recent progress updates (January 2019, August 2019 and May 2020) demonstrate the continuing sliding or rolling back of deadlines for completing the Consent Order work ….. For example, in the January 2019 update, 15 of the sites were expected to be completed by the end of 2019. In the August 2019 update, that figure had reduced to 9. By the May 2020 update, 17 of the sites had no expected completion date at all (many of which simply said 'on hold') and the other sites either had lines drawn through the expected completion date or had 2020+, 2021 or beyond. 32. The May 2020 update showed that, of the 37 sites, 20 sites were in the red category, 9 were in the amber category, and only 8 were in the green category. The main reason cited for this 'stopped' or 'slowed' progress was resource constraints (following the theme picked up in correspondence and meetings between the parties over the many years since the Consent Order was made). 33. This culminated in a pre-action letter from the Claimants to the Defendants on21 August 2020 setting out the basis on which the Defendants had failed to carry out the Consent Order work 'as soon as reasonably practicable' …. 34. The Defendants responded on11 September 2020 …. At paragraph 12 of this letter, the Secretary of State accepted that " all of the obligations under the Consent Order are to be carried out 'as soon as reasonably practicable' "
"38. The November 2020 updated shows a very slight improvement in progress, following the pre-action letter sent to the Defendants in August. However, the state of play remains significantly behind previous commitments made by the Defendants during the five years since the Consent Order was made and the Claimants cannot accept the new completion dates provided because the Defendants have repeatedly reneged on these dates in the past ….. and because 2021 sees the end of one six-year RBMP cycle and design/establishment of the next and final cycle… 39. We are now told that the work for four of the sites has been completed and that final published versions should be available shortly. Thirteen sites have expected completion dates in 2021 and 4 have dates in 2022 and beyond. However the remaining 16 sites are in the 'red' category with no expected completion date and are either 'on hold' or 'under review'. Given the length of time the Defendants have had to carry out this work, this extremely poor progress represents all but a wholesale failure by the Defendants to comply with the terms of the Consent Order."
"Defra were aware of how the range of pressures risked hampering progress on our priorities and resourcing decisions were made taking into consideration a wide range of factors and priorities needing to be delivered with limited public funds. Ultimately, DWPPs and related work must be carried out within budgetary constraints and it is not open to Defra, the Environment Agency or Natural England to apply to unlimited funding to these workstreams. Whilst no additional resource was made available for the express purpose of accelerating progress on DWPPs, Defra, the Environment Agency and Natural England worked hard to make progress alongside other operational priorities funded from their non-ring fenced budget lines. …"
"Despite significant investment in these sites over the years to gather evidence, more still needs to be done to understand sources and pathways of pollution at these N2K sites. To carry out option appraisals, as set out in the Consent Order, requires considerably more work for Area teams than can currently be resourced without impacting significantly on the business. To date, there has been no separate funding associated with this work … and Areas are having to make decisions to either not carry out this work or drop other essential priorities."
"44. In summary therefore it is certainly true that progress in the preparation of DWPPs has been slower than was initially anticipated in 2015/2016. That in large part has arisen due to no additional financial resource being allocated to the EA for delivery of this work at a time when our core allocation from government was continuing to decline, whilst our ongoing regulatory obligations were increasing. As outlined this was in the context of the unforeseeable development of EU Exit which meant public funding settlements have been extremely challenging and our resources have been focused towards achieving the more strategic outcomes available for the water environment during this rather unique period. In managing these demands and opportunities I am confident both that we have applied, and will continue to apply, a best endeavours approach to progressing the preparation of the DWPPs; whilst also maximising the opportunities arising from the investigations to make a real difference to the water environment."
"A range of factors have affected delivery of the programme of work on diffuse water pollution affecting European sites. The main challenges are: scientific understanding/capability; resourcing to manage and undertake the necessary analysis and stakeholder work; and a change in approach during the course of the programme towards an adaptive management approach. This led to a focus on action on the ground alongside a business-as-usual approach to evidence gathering and development of plans."