“If you are unable to access transcripts directly, 3 additional cases have also been provided that may assist you as detailed below. The Council is not seeking to introduce new evidence at this stage but assist you in providing access to case transcripts which you are likely to identify as warranting consideration. A copy of the case transcript referred to in the Planning Encyclopaedia at para P106A.06 (set out below) has been included (as it was envisaged that with no access to transcripts you may need to consider this as part of your deliberations), An application to discharge an obligation will only be successful where the obligation no longer serves a useful purpose. This is not a high test. In Batchelor Enterprises (above) it was common ground between the parties, and Sullivan J. appears to have accepted, that a useful purpose in this context meant a useful planning purpose. In R (on the application of Renaissance Habitat Ltd) v West Berkshire DC [2011] J.P.L. 1209 Ouseley J. cast some doubt on this and expressed a reluctance to narrow the range of public interest purposes that an obligation may serve to purely planning purpose, and was reluctant to enable debate as to whether a purpose served was indeed a planning purpose. However, in practice it seems unlikely that this debate will arise given the obligations within an obligation will ordinarily relate at least to a planning purpose. The Renaissance Habitat case was the key case cited in R (The Garden & Leisure Group Ltd) v N Somerset Council[2003] EWHC 1605 (Admin) where is was accepted (para 28) that the correct approach to considering an application under section 106A of the 1990 Act was to ask four essential questions (highlighted in the transcript). A copy of this transcript has also been provided and if it assists the Council’s response to those questions is outlined below for information (this simply summarises the Council’s case). i) The current obligation is to pay the balance of the sum of£459,346.85 , which fell due on3rd August 2016 . ii) The purpose of the obligation is to reimburse the Council for part of the expenditure it incurred for the benefit of the applicant in the construction of the new road. It gives effect to the “historic financial arrangement” between the Council and the applicant. iii) That is a useful purpose. Local Authorities are short of money. iv) The proposed modification would destroy that purpose. It would leave the Council without the money.”
“9. However, part 1 of the Second Schedule of the S106 agreement requires the payment of a highway contribution of£459,346.85 within a specified timescale only partly related to the provision of the houses granted permission on the site. The sum of£100,000 was due to be paid on the date falling in one year after the date of the agreement. The appellant confirms that this amount has been paid to the Council, together with a further£60,000 at the time of the completion of a health centre on part of the site. The balance of£299,346.85 is due to be paid on the earliest of the three alternative dates. These are firstly, 14 days after the completion of a sale of the whole or of two or more acres of the site, secondly, the date of completion of 50% by number of the dwellings authorised to be constructed by the planning permission and thirdly, the date of expiry of the period of five years and six months from the date of the S106 agreement. 10. As development has not started on site, and the land has not been sold, the balance of the highway contribution fell due for payment on3 August 2016 . 11. The main issue is therefore whether the planning obligation regarding the contribution to the highway costs still serves a useful purpose. Reasons The Council refer me to a judgment(Tesco Stores Ltd v SSE and others) which it considers demonstrates that once an obligation becomes binding it cannot be challenged on the grounds that it lacks sufficient relationship with the proposed development. However the quoted passage relates to the granting of planning permission, and once permission has been granted whether this decision may be challenged on the basis that the s106 obligation is not sufficiently connected with the proposed development. This is somewhat different to the case before me to discharge a planning obligation… 17. In this instance though, the Secretary of State did consider the obligation at appeal and found that the obligation in respect of the highway contribution was not necessary. I concur with this view. The payment related to a historic financial agreement between the parties at the time the road was constructed. It is therefore not necessary for the road to be constructed to make the residential development acceptable… 19. At the time, the appeal site could not have been developed had the road not been constructed. However, the road has now been in place for a significant number of years. Therefore, a payment required towards the highway costs of constructing the road, in any subsequent S106 obligation, would not in my opinion be directly related to the development proposed at the time. This, together with the road not being necessary to make the residential development acceptable means that the obligation does not continue to serve a useful purpose in this respect.”
“(1) The Secretary of State may proceed to a decision on an appeal taking into account only such written representations as have been sent within the relevant time limits… (3) In this regulation “relevant time limits” means the time limits prescribed by these Regulations, or where the Secretary of State has exercised the power under regulation 17, any later time limit.”
“The Secretary of State may in a particular case give directions setting later time limits than those prescribed by these Regulations.”
“The department considers that the expression ‘no longer serves any useful purpose’ should be understood, in land-use planning terms. Thus, if an obligations only remaining purpose is to meet some non-planning objective it will generally be reasonable to discharge it.”
“It is accepted that the question to be considered by the local planning authority in each case is the same: does the obligation still serve a useful planning purpose? Since the court in judicial review proceedings may not substitute its own answer to that question for that of the local planning authority, the question in relation to an application for judicial review in respect of a local authority's decision under section 106A(1)(a) is whether a reasonable local planning authority could have concluded that the obligation still served a useful planning purpose.”
“A planning obligation, which required as a pre-condition for commencing development that a developer pay a financial contribution for a purpose which did not relate to the burdened land, could be said to restrict the development of the site, but it would also be unlawful. Were such a restriction lawful, a planning authority could use a planning obligation in the context of an application for planning permission to extract from a developer benefits for the community which were wholly unconnected with the proposed development, thereby undermining the obligation on the planning authority to determine the application on its merits. Similarly, a developer could seek to obtain a planning permission by unilaterally undertaking a planning obligation not to develop its site until it had funded extraneous infrastructure or other community facilities unconnected with its development. This could amount to the buying and selling of a planning permission. Section 75 , when interpreted in its statutory context, contains an implicit limitation on the purposes of a negative suspensive planning obligation, namely that the restriction must serve a purpose in relation to the development or use of the burdened site. An ulterior purpose, even if it could be categorised as a planning purpose in a broad sense, will not suffice. It is that implicit restriction which makes it both ultra vires and also unreasonable in the Wednesbury sense for a planning authority to use planning obligations for such an ulterior purpose.”
“of course it is normal for a planning obligation to be undertaken or offered in connection with an application for planning permission and to be expressed as conditional upon the grant of permission. But once the condition has been satisfied, the planning obligation becomes binding and cannot be challenged by the developer or his successor in title, on the ground that, it lacked a sufficient nexus with the proposed development.”