“The reasons for a decision must be intelligible and they must be adequate. They must enable the reader to understand why the matter was decided as it was and what conclusions were reached on the “principal important controversial issues”, disclosing how any issue of law or fact was resolved. Reasons can be briefly stated, the degree of particularity required depending entirely on the nature of the issues falling for decision. The reasoning must not give rise to a substantial doubt as to whether the decision-maker erred in law, for example by misunderstanding some relevant policy or some other important matter or by failing to reach a rational decision on relevant grounds. But such adverse inference will not readily be drawn. The reasons need refer only to the main issues in the dispute, not to every material consideration. They should enable disappointed developers to assess their prospects of obtaining some alternative development permission, or, as the case may be, their unsuccessful opponents to understand how the policy or approach underlying the grant of permission may impact upon future such applications. Decision letters must be read in a straightforward manner, recognising that they are addressed to parties well aware of the issues involved and the arguments advanced. A reasons challenge will only succeed if the party aggrieved can satisfy the court that he has genuinely been substantially prejudiced by the failure to provide an adequately reasoned decision.”
“(2) When making his decision the inspector may disregard any written representations or evidence or any other document received after the close of the inquiry. (3) If, after the close of an inquiry, an inspector proposes to take into consideration any new evidence or any new matter of fact (not being a matter of government policy) which was not raised at the inquiry and which he considers to be material to his decision, he shall not come to a decision without first (a) Notifying [in writing] the persons entitled to appear at the inquiry who appeared at the matter in question; and (b) affording them an opportunity of making written representations to him or of asking for the re-opening of the inquiry. And they shall ensure that such written representations or requests to re-open the inquiry are received by the Secretary of State within three weeks of the date of notification. (4) An inspector may, as he thinks fit, cause an inquiry to be re-opened and he shall do so if asked by the appellant or the local planning authority in the circumstances and within the period mentioned within paragraph (3): and where an inquiry is re-opened – (a) The inspector shall send to the persons entitled to appear at the inquiry who appeared at it a written statement of the matters with respect to which further evidence is invited;…”
“At any point before deciding the appeal the inspector may exercise his/her powers to seek further information from the parties if it is considered necessary to enable a properly informed, and reasoned, decision to be made.”
“The Secretary of State and Inspectors have discretion as to how to treat new materials submitted with or during the consideration of an appeal. They will apply their discretion on the basis of the relevance of the material to the appeal proposal, whether it simply repeats something that is already before the Inspector (for example, rebuttal evidence which adds nothing to what is already recovered in a proof of evidence) and whether it would be procedurally fair to all parties “including interested persons” if the material were taken into account…” “The Secretary of State and Inspectors have discretion as to how to treat new materials submitted with or during the consideration of an appeal. They will apply their discretion on the basis of the relevance of the material to the appeal proposal, whether it simply repeats something that is already before the Inspector (for example, rebuttal evidence which adds nothing to what is already recovered in a proof of evidence) and whether it would be procedurally fair to all parties “including interested persons” if the material were taken into account…”
“To boost significantly the supply of housing, local planning authorities should: • Use their evidence base to ensure that their local plan meets the full, objectively assessed needs for market and affordable housing in the housing market area as far as is consistent with the policies set out in this framework, including identifying key sites which are critical to the delivery of the housing strategy over the planed periods; • Identify and update annually a supply of specific deliverable sites sufficient to provide 5 years worth of housing against their housing requirements with an additional buffer of five per cent (moved forward from later in the planned period) to ensure choice and competition in the market for land…” • Use their evidence base to ensure that their local plan meets the full, objectively assessed needs for market and affordable housing in the housing market area as far as is consistent with the policies set out in this framework, including identifying key sites which are critical to the delivery of the housing strategy over the planed periods; • Identify and update annually a supply of specific deliverable sites sufficient to provide 5 years worth of housing against their housing requirements with an additional buffer of five per cent (moved forward from later in the planned period) to ensure choice and competition in the market for land…”
“To be considered deliverable, sites should be available now, offer a suitable location for development now, and be achievable with a realistic prospect that housing will be delivered on the site within five years and in particular that development of the site is viable. Sites with planning permission should be considered deliverable until permission expires, unless there is clear evidence that schemes will not be implemented within 5 years, for example they will not be viable, there is no longer a demand for the type of units or sites have long term phasing plans.”
“This includes a number of sites which are proposed as housing allocations in the Preferred Options versions of the TTP and the RAP. However, these Plans have not been subject to independent testing through an examination and several of the sites do not appear to have planning permission or to be allocated for housing in the Local Plan. In addition, some sites appear to have constraints which could impede deliverability. Consequently I have not been given sufficient evidence to indicate that these sites can be regarded as being available, suitable and achievable as required by PPS3. Therefore, it has not been demonstrated that a five year supply exists. ”; ii). The decision of Inspector Graham relating to land at Moat House Farm, Marston Green, in the area of Solihull MBC dated21 February 2012 . At [11] of her decision she addressed the question of Draft Local Plan sites, which the Council had brought into account in its calculation of the housing land supply. The inspector said: “The draft Local Plan identifies proposed sites for 1,445 net additional dwellings, and the Council maintains that these should be taken into account when calculating the 5 years supply position. However, it is important to bear in my mind that this emerging Local Plan is still only a draft, which has yet to be the subject of further consultation, representations, and Examination in Public. Paragraph 54 of PPS3 explains that to be considered deliverable, sites should be available, suitable and achievable at the point of adoption of the relevant Local Development Document. There can be no guarantee that sites included in the current draft will remain in the finished version of the Local Plan, which in any event will not be adopted before 2013. As the situation stands at present, I consider that these sites should not be included when calculating the current five year land supply position” iii). The later decision of Inspector Graham relating to land at Park Road, Malmesbury, Wiltshire dated15 March 2012 . At [18] of her decision she accepted that “the Council’s 2010/2011 Annual Monitoring Report (AMR) provides the logical starting point for assessing the supply of deliverable housing sites.”
“It is fair to note that all three sites have physical, environmental and infrastructure constraints that will need to be addressed. However, the council has liaised with the developers of each, and obtained delivery trajectories which update the information provided in AMR. I see no convincing reason to doubt these revised figures, which indicate that within the five year period an additional 420 dwellings will be provided at the north Chippenham site, and a further 110 at the East Chippenham site. ”
“17. Of the large permitted areas, there does appear to be doubt over the delivery of the former Bath and Portland Stoneworks site given its past history, not being in the 2009/10 Annual Monitoring Report, and little evidence that matters have moved on substantially since. Similarly with the Blue Hills Site, this appears to have been subject to persistent delays and to being put back in time in the successive Annual Monitoring Reports. The delivery timescale for land adjacent to the scrap yard at Trowbridge also appears to be receding and reduction here is appropriate. 18. Other sites with permissions that had been previously dismissed have been brought back into the list, but it is apparent that even with the acceptance of these sites in total, a shortfall is possible. The Council has added 183 units in this category where none were previously included. Footnote 11 of the framework does provide for live permissions to be counted unless there is clear evidence that the schemes will not be implemented within 5 years, for example, they will not be viable, there is no longer a demand for the type of units or sites or sites have long term phasing plans. Clearly those where the permission has expired should not be included and where land was bought at or near the height of the market, doubts over viability would be legitimate. The prospect of new permissions on new land being required to replace such stalled schemes was discussed. Windfalls have also been significantly increased and that is provided for in paragraph 48 of the framework subject to certain requirements on historic evidence. There appears to be good reason to reduce the figure on that basis as suggested, Vision and strategic sites are disputed in their entirety, and given the process to be gone through and the doubts over delivery, a degree of caution is appropriate. The requirement is to identify a supply of specific deliverable sites and to be considered deliverable, sites should be available now. These sites cannot truly be described as being available now.” [Emphasis added]
“Thank you for your email below. Unfortunately it was received too late to be considered by the Inspector.”
“available now” connotes that, if the site had planning permission now, there would be no other legal or physical impediment integral to the site that would prevent immediate development; iii). Questions as to the viability of the proposed development or, for example, whether a developer had been identified or was in a position immediately to start work, would go to the question whether there was a realistic prospect of delivery within five years, but not to the question whether the site was available now. For the same reason, the fact that a site does not “offer a suitable location” does not affect whether or not it is “available now”, suitability of the location being a separate requirement; iv). Where sites without planning permission are subject to objection, the nature and substance of the objections may go to the question whether the site offers a suitable location; and they may also determine whether the development is achievable with a realistic prospect that housing will be delivered on the site within five years. Even if detailed information is available about the site and the objections, prediction of the planning outcome is necessarily uncertain. All that probably need be said in most cases is that where sites do not have planning permission and are known to be subject to objections, the outcome cannot be guaranteed. Accordingly, where there is a body of sites which are known to be subject to objections, significant site specific evidence is likely to be required in order to justify a conclusion that 100% of all those sites offer suitable locations and are achievable with a realistic prospect that they will be delivered within five years; v). For similar reasons, where sites are in contemplation because of being included in an emerging policy document such as the eWCS, and the document is still subject to public examination, that must increase the lack of certainty as to outcome. That is implicitly recognised by [216] of NPPF which requires decision-takers to “give weight to relevant policies in emerging plans according to: the stage of preparation of the emerging plan (the more advanced the preparation, the greater the weight that may be given)” and to “the extent to which there are unresolved objections to relevant policies (the less significant the unresolved objections, the greater the weight that may be given)… .”
“Thank you for your email below. Unfortunately it was received too late to be considered by the Inspector.”
“In order for strategic plans to be put in place to address the housing supply, I consider that allocated sites can be included, including those within emerging plans, subject to the weight that can be given to that plan and its evidence base and the submission of information indicating a reasonable likelihood of them progressing within the five year period.”
“While full weight cannot be given to the precise numbers put forward by the Council, I consider it reasonable to include these sites in absence of specific evidence that they cannot be delivered.”