“3. It is intended that the form of the Contract will be based upon the document produced by Forsters LLP incorporating the JCT Standard Building Contract Without Quantities 2011 (DOC ID 3202342_6)… 5. Although the Contract has not yet been entered into, all the terms and conditions of the Contract will apply to any work carried out by you pursuant to the instructions contained in this letter. 6. We have appointed RLF 3PM LLP to act as the contract administrator ("the Contract Administrator") for the purposes of the Works and to act on our behalf as stated in the Contract. You must liaise with the Contract Administrator and comply with all instructions issued by him in relation to the Works as if the Contract had been entered into… 9. We will pay you in accordance with the terms of the proposed Contract for any activities properly undertaken by you pursuant to the instruction contained in this letter, provided that our total liability under this letter shall not exceed FIVE HUNDRED THOUSAND POUNDS (£500,000.00 ) plus Value Added Tax. For the avoidance of doubt, we are not bound to enter into any further contract with you and our commitment at this stage is strictly limited as set out in this letter. You must obtain our further authorisation and instruction before committing to any expenditure above the limit stated in this paragraph. 10. Within 7 days of the date of this letter and as a pre-condition of entry to the site of the Works in any event you must provide us with certificates of verification of insurance cover confirming that all insurances which you are (or will be) required to maintain under the terms of the proposed Contract are in place upon the required terms and at the required levels. In particular (to the extent that they have not been provided to us to date) we require evidence of your Contractor's All Risks, Professional Indemnity, Employer's Liability, Public Liability and (if applicable) JCT clause 6.5.1 (or similar) insurances… 21. This letter supersedes any previous instructions, correspondence or other discussions between us in relation to the Works and represents the entire agreement between us in relation to its subject-matter.”
“96. Mr Higgs pressed for there to be such an insurance policy for the Project. He believed that it had been agreed that insurance in such terms would be obtained. He said that Richard Knight, the RFU’s stadium director, had told him that comprehensive ground insurance was being obtained. Mr Knight had expressed the hope that this would lead to a reduction in the tender prices because the tenderers would not need to include the cost of insurance in their tenders.”
“100. In early July 2012 Mr Higgs began pressing for the project insurance to be put in place and a number of email exchanges followed between Mr Higgs and Marsh with Mr Knight, Mr Pettifer, and others being copied in. At one point reference was made to Delay Start Up insurance. This prompted Mr Higgs to explain in somewhat exasperated tones that the issue was nothing to do with Delay Start Up insurance. He asked that the insurance be put in place “immediately” because “otherwise I am going to have to ask [Conway] to provide their own insurance”
“101. In his answers to cross-examination Mr Higgs was clear that he believed that the insurance to be obtained by the RFU was going to be more extensive than that envisaged in the standard terms of the JCT Contract.”
“106. Mr Higgs and Mr Morris were patently honest and careful witnesses. It was apparent that at the time when they were giving evidence before me they both believed that the intention in 2012 had been for comprehensive insurance cover creating a fund recourse to which would be “the sole avenue for making good the relevant loss or damage” adopting the Gard Marine terms. I bear in mind the need for considerable caution in placing weight on the recollection of witnesses. Here Mr Higgs and Mr Morris were casting their minds back to 2012 in circumstances where they would have dealt with a considerable number of matters in the intervening period and where the question of the arrangements between Conway and the RFU will have been by no means at the forefront of their minds in that period. I find, however, that on the balance of probabilities the understanding and belief which those gentlemen expressed now was a reflection of the belief they had in 2012. In that regard the terms of Mr Higgs’s emails in July 2012 are significant and are consistent with what he says now was his understanding then.”
“(a) Rugby Football Union as the Principal and/or associated and/or subsidiary companies (b) The Contractor for each Project (c) All other contractors and/or sub-contractors of any tier and others engaged to provide goods or services in connection with the Project insured hereunder… Each for their respective rights and interests.”
“2 Clause 6.5.1 may be required, 3 Option C with 15% professional fees”
“(f) Insurers hereby agree to waive all rights of subrogation which they may have or acquire against any insured party except where the rights of subrogation or recourse are acquired in consequence of or otherwise a Vitiating Act in which circumstances Insurers may enforce such rights notwithstanding the continuing or former status of the vitiating party as an Insured.”
“Existing structures and contents - Joint Names Policy for Specified Perils C.1 The Employer shall take out and maintain a Joint Names Policy in respect of the existing structures (which from the Relevant Date shall include any Relevant Part to which clause 2-33 refers) together with the contents thereof owned by him or for which he is responsible, for the full cost of reinstatement, repair or replacement of loss or damage due to any of the Specified Perils up to and including the date of issue of the Practical Completion Certificate or last Section Completion Certificate, or (if earlier) the date of termination of the Contractor's employment (whether or not the validity of that termination is contested). The Contractor shall authorise the insurers to pay all monies from such insurance to the Employer. The Works - Joint Names Policy for All Risks C.2 The Employer shall take out end maintain a Joint Names Policy for All Risks Insurance with cover no less than that specified in clause 6.8 for the full reinstatement value of the Works or (where applicable) Sections (plus the percentage, if any, stated in the Contract Particulars to cover professional fees) and (subject to clause 2-36) shall maintain such Joint Names Policy up to and including the date of issue of the Practical Completion Certificate or, if earlier, the date of termination of the Contractors employment (whether or not the validity of that termination is contested). The obligation to maintain the Joint Names Policy under this paragraph C.2 shall not apply in relation to any Section after the date of issue of the Section Completion Certificate for that Section.”
“1. Whether the insured losses said by the RFU and the RSA to be in the sum of£3,334,405.26 are irrecoverable because RSA cannot exercise subrogation rights and/or because on a proper interpretation of the project policy and/or the project policy and the JCT contract the RFU and/or the RSA are not entitled to claim the insured losses; 2 If the answer to question 1 is that the RFU cannot recover its insured losses from Conway, does this prevent CSP from claiming a contribution from Conway under theCivil Liability (Contribution) Act 1978 in respect of any liability CSP may have to the RFU in respect of the insured losses?”
“107. However, the question of whether the understanding which Mr Higgs and Mr Morris had accurately reflected either the terms of the agreement between the RFU and Conway and or the basis on which the Policy was taken out is a different matter. I have to consider whether the understanding which Mr Higgs had of the effect of the Policy was correct. In that regard I remind myself that the terms of the contract between the RFU and Conway are the key to ascertaining the effect of the insurance which was obtained pursuant to that contract. In addressing the terms of the contract between the parties the following are relevant. 108. The parties were substantial entities dealing at arm’s length. The Project was a major exercise which involved the RFU in engaging several sub-contractors and in relation to which it was acting through a number of professionals including solicitors and insurance brokers. RLF3PM were not the only professionals acting for the RFU and it is of note that Mr Higgs accepted that responsibility for the insurance arrangements on behalf of the RFU was in the hands of Jon Pettifer of Mace. For its part Conway was a substantial civil engineering business with an in-house legal department and an internal insurance manager. This is not a case where the contractually effective dealings were conducted solely, or indeed principally, through Mr Higgs and Mr Morris. Rather the terms were agreed between teams of a number of professionals on each side… 110. The Letter of Intent stated expressly that it was envisaged that the contract which would be entered between the RFU and Conway would be in the terms of the JCT contract and that if such a contract was entered it would apply retrospectively and supersede the Letter of Intent. The Contract when entered was in the form of the JCT contract. I have already said that the terms of the Contract, the Letter of Intent, and the Policy standing alone are consistent with the RFU’s position and not with that of Conway. If the parties had been contracting on the footing that recourse to the insurance would be the sole avenue for redress for damage of the kind which occurred then further amendments to the standard JCT contract could have been made so as to provide for that in clear and express terms. That was not done and, moreover, was not done even though the Contract was entered 3 months after the Policy had been taken out. This is particularly significant given that the JCT contract sets out a detailed structure for allocating risks and responsibilities. Different options were available in respect of the insurance arrangements. The parties chose Option C but did so without any express modification or expansion of its effect… 122. It is significant that the Letter of Intent with its reference to the intention to adopt the JCT contract was sent after the RFU had accepted the recommendation to go down the OCIP route and while the RFU’s agents were negotiating with the insurance brokers and seeking a suitable policy. This supports the view that all concerned were proceeding on the footing that when an insurance policy was obtained its effect would be compatible with the arrangements envisaged in the JCT contract. It is also evident that the decision to take out insurance for the Project as a whole was not a new development after the sending of the Letter of Intent nor one which in some way superseded or modified the arrangements envisaged in that letter… 124. It is important to keep in mind the nature of the loss under consideration here. The claim is for loss allegedly suffered by the RFU as a consequence of damage to the cabling caused by deficiencies on the part of Conway in respect of the ductwork. Was the RFU intending to take out insurance covering Conway in respect of the liability for such loss with the consequence that the RFU’s recourse should be limited to a claim under the Policy?”
“125. I am satisfied that the agreement between the RFU and Conway did not provide that by taking out the Policy the RFU was creating a fund recourse to which would be the sole remedy for loss suffered by the RFU as a consequence of breach or other default by Conway. The terms of the Letter of Intent and the Contract make no reference to such an arrangement and are indicative of a very different arrangement. For me to find that the Policy was taken out on the basis alleged by Conway and with the intention and authority it now asserts there would need to be compelling evidence to counter the inferences from the natural reading of the Letter of Intent and the Contract. There is no such evidence. I am satisfied that the Policy was effected on the basis that it was providing the cover contemplated by Option C in the JCT contract. It was doing so in respect of the Project as a whole but it was not going beyond that. In particular it did not provide a common fund recourse to which was to be the RFU’s sole redress for loss flowing from breaches by Conway or any other contractor. I am satisfied that the understanding which Mr Higgs had of the effect of the Policy did not accurately reflect the terms on which the RFU and Conway were dealing nor the basis on which the Policy was taken out. 126. It follows that the Letter of Intent, the Policy, and the Contract are to be read according to their terms. The Policy insured both the RFU and Conway but they were not insured to the same extent in respect of the same risk. In particular they were not co-insured in respect of the losses which the RFU is said to have suffered by reason of damage to the cables resulting from defects in the ductwork and for which the RFU has been indemnified by RSA.”
“130. I reject Mr Ghaly’s argument in this regard and conclude that the waiver of subrogation in Memorandum 1(f) only extends to matters in respect of which Conway is insured under the Policy. In the light of my finding that Conway is not co-insured with the RFU to the extent of the losses currently in issue that means this waiver of subrogation does not assist it in these proceedings. There is considerable force in the points made by Mr Reed and Mr Wheater but I reach the same conclusion by a different route which has regard to both the wording of the memorandum and the terms of the Contract between the RFU and Conway. 131. As between RSA and Conway Memorandum 1(f) is addressing rights which the former has against the latter as the latter’s insurer. It is those rights which are rights of subrogation against Conway. Such a right can only arise to the extent that Conway is an insured party and in respect of matters where Conway is insured by RSA. If and to the extent that the RFU and Conway are co-insured of the same insurer in respect of the same loss to the same extent then a claim in respect of the insured loss against Conway would be a claim made by RSA as insurer against its insured and would be caught by the waiver of subrogation. Alternatively it would be a claim which could not be brought by the RFU and matters could not be improved by RSA exercising rights flowing from its indemnification of the RFU. However, if, as is the position here, the RFU and Conway are not co-insured in that way then the waiver does not operate to protect Conway. The waiver cannot operate to protect Conway against claims arising out of matters in respect of which it is not insured. The point can be put very shortly. If RSA were Conway’s insurer in respect of these losses then the right being exercised would be one of subrogation against Conway. However, that is not the position and the rights which RSA is exercising against Conway are not rights of subrogation against Conway. Instead the right which RSA is exercising against Conway is the RFU’s right to compensation for the loss caused to the RFU by Conway. RSA has acquired by virtue of its right of subrogation against the RFU the right to bring proceedings for that loss against Conway in the name of the RFU but the claim being made in that way is not a claim arising out of RSA’s right of subrogation against Conway and so is unaffected by the waiver of such rights.”
“The result of these authorities is, in my judgment, as follows: (1) Where at the time when the contract of insurance was made the principal assured or other contracting party had express or implied actual authority to enter into that contract so as to bind some other party as co-assured and intended so to bind that party, the latter may sue on the policy as the undisclosed principal and co-assured regardless of whether the policy described a class of co-assured of which he was or became a member. (2) Where at the time when the contract of insurance was made the principal assured or other contracting party had no actual authority to bind the other party to the contract of insurance, but the policy is expressed to insure not only the principal assured but also a class of others who are not identified in that policy, a party who at the time when the policy was effected could have been ascertained to qualify as a member of that class can ratify and sue on the policy as co-assured if at that time it was intended by the principal assured or other contracting party to create privity of contract with the insurers on behalf of that particular party. (3) Evidence as to whether in any particular case the principal assured or other contracting party did have the requisite intention may be provided by the terms of the policy itself, by the terms of any contract between the principal assured or other contracting party and the alleged co-assured or by any other admissible material showing what was subjectively intended by the principal assured.”
“As a matter of construction, there must be a strong inference that DOL’s authority to insure was co-extensive with its obligation to do so”
“48 The position therefore is that there is no liability to pay compensation on either side. The employer has no claim for compensation against the contractor. All he can do is insist that the contractor must proceed with due diligence to carry out the reinstatement work and must authorise the release to him of the insurance moneys. The contractor has no claim for compensation against the employer. All he can do is insist that the employer must use the insurance moneys for payment of the cost of carrying out the reinstatement work. It makes no difference whether the fire was caused by the negligence of the contractor or one of his sub-contractors or of the employer or of some third party for whose acts or omissions neither of the parties to the contract is responsible. The ordinary rules for the payment of compensation for negligence and for breach of contract have been eliminated.”
“65 …I would prefer to say that the true basis of the rule is to be found in the contract between the parties. In Hopewell Project Management Ltd v Ewbank Preece Ltd[1998] 1 Lloyd's Rep 448 , 458 Mr Recorder Jackson QC said that in his view it would be nonsensical if those parties who were jointly insured under a contractors' all risks policy could make claims against one another in respect of damage to the contract works, that such a result could not possibly have been intended by those parties and that had it been necessary for him to do so he would have held that there was an implied term to that effect”
“75. …It appears, however, that the following doctrines have at times been put forward to explain the impermissibility for an insurer to sue by way of subrogation in the name of one co-assured to recoup himself from another co-assured on the basis of the latter’s negligence or default: the doctrine of circuity of action and the doctrine of an implied term in the insurance contract. It also appears that the doctrine of circuity of action is no longer favoured (see Brooke LJ at para 69 and Lord Hope at para 64), and that the doctrine of an implied term in the insurance contract has now been replaced by a doctrine of the true construction of the underlying contract for the provision of joint names insurance (Brooke LJ at para 73 and Lord Hope at para 65): and that this last doctrine may operate with the assistance of an implied term to the effect that co-insureds cannot sue one another in respect of damage in respect of which they are jointly insured (Lord Hope at para 65)… 77... Moreover, if the underlying contract envisages that one co-assured may be liable to another for negligence even within the sphere of the cover provided by the policy, I am inclined to think that there is nothing in the doctrine of subrogation to prevent the insurer suing in the name of the employer to recover the insurance proceeds which the insurer has paid in the absence of any express ouster of the right of subrogation, either generally or at least in cases where the joint names insurance is really a bundle of composite insurance policies which insure each insured for his respective interest. Most co-insurances are of such a composite kind: see the discussion in McGillivray on Insurance Law, 10th Edition, 2003, at paras 1-194 and at paras 22-99 to 22-102. It is unusual for an insurer to sue his own insured to recover insurance proceeds due under his own policy, but it must be recalled that he does so in the name of and under the right of another party, viz the employer. In similar or analogous fashion, an insurer may find that one co-insured’s fault cannot be held against another co-insured so as to save the insurer from liability: see Samuel & Co Ltd v Dumas[1924] AC 431 at pages 444 to 446, General Accident Fire and Life Insurance Corporation Ltd v Midland Bank Ltd[1940] 2 KB 388 at page 405 and 406, and State of the Netherlands v Youell[1997] 2 Lloyd’s Rep 440 at pages 447 and 448.”
“139. The critical question is whether the contractual scheme between the owners and the demise charterer precluded any claim by the former against the latter for the insured loss of the vessel. This is a matter of construction. It has become a common practice in various industries for the parties to provide for specified loss or damage to be covered by insurance for their mutual benefit, whether caused by one party’s fault or not, thus avoiding potential litigation between them. The question in each case is whether the parties are to be taken to have intended to create an insurance fund which would be the sole avenue for making good the relevant loss or damage, or whether the existence of the fund co-exists with an independent right of action for breach of a term of the contract which has caused that loss. Like all questions of construction, it depends on the provisions of the particular contract: see, for example, Co-operative Retail Services Ltd v Taylor Young Partnership Ltd[2002] 1 WLR 1419 .”
“In view of the fact that NOW was not specifically identified as a co-assured on the face of the policy, the question arises by what means it could become bound to the insurers as co-assured on any of the terms of that contract. Since the first half of the 19th centurv there has been continuing discussion in the authorities and the textbooks as to the circumstances in which, where a contract of insurance is expressed to insure a named assured together with a class of others unnamed for their respective rights and interests, someone who qualifies as a member of that class can sue on the policy. Although, by the decision of the House of Lords in Keighley, Maxsted & Co. v. Durant, [1901] A.C. 240, it was made clear that an undisclosed principal could not ratify a contract made by someone acting at the relevant time without authority, the position of an unidentified member of a class of assured referred to in the policy has been left in some doubt.”
“However, if, as is the position here, the RFU and Conway are not co-insured in that way then the waiver does not operate to protect Conway. The waiver cannot operate to protect Conway against claims arising out of matters in respect of which it is not insured”
“It follows that if the effect of the waiver clause would be to preclude DOL's insurers from pursuing by subrogation post-delivery claims which but for the waiver clause would not arise out of losses insured for the benefit of NOW under the policy, this would place NOW in exactly the same position vis-a-vis insurers as regards such claims as if those losses had been fully insured under the policy. In effect the waiver clause would extend the scope of the insurance to cover losses which were never actually insured for the benefit of NOW. This gives rise to the question whether, as a matter of construction of the policy, if the provisions to the contrary clause limit the cover available to a sub-contractor to a scope less than the full scope provided by the policy to DOL, the waiver clause has the effect of protecting the sub-contractor against subrogated claims for losses which, so far as that sub-contractor is concerned, were uninsured by that policy. Such a consequence would indeed be remarkable. The policy would limit the cover with one hand and indirectly by waiver of subrogation remove the limit by another hand.”