“The Employer shall maintain, in the joint names of the Employer, the Construction Manager and others including, but not limited to, contractors, insurance of existing structures…against the risks covered by the Employer’s insurance policy referred to in Schedule 2 (i.e. the Specified Perils) subject to the terms, conditions, exclusions and excesses (uninsured amounts) of the said policy.”
“2. Contractor’s Obligations The Contractor shall: - … 2.3 indemnify the Employer against any damage, expense, or loss whatsoever suffered by the Employer or incurred to any third party to the extent that the same arises out of or in connection with any breach of this Contract or any negligence or breach of statutory duty on the part of the Contractor or any sub-contractor or supplier of his or any tier. The Contractor shall: - 2.3 indemnify the Employer against any damage, expense, or loss whatsoever suffered by the Employer or incurred to any third party to the extent that the same arises out of or in connection with any breach of this Contract or any negligence or breach of statutory duty on the part of the Contractor or any sub-contractor or supplier of his or any tier. 3. Construction Manager’s Instructions ... 3.3 Notwithstanding any other provision of this contract the Contractor shall no[t] be entitled to an increase in the Contract Price and/or to a change in the Completion Date to the extent that any Instruction for a Variation results from or is necessary in order to overcome the adverse effects of any lack of performance or error or omission or negligent act or default or breach of contract on the part of the Contractor or any supplier of his or any tier. 9. Early occupation of the Works. The Employer may upon written notice from the Construction Manager to the Contractor take occupation of any part of the Works or any area within such part prior to practical completion of the Project in which event the Employer shall assume responsibility for risk in relation to such part or area within such part of the Works (notwithstanding Clause 13.1) and (except to the extent otherwise instructed by the Construction Manager) protection of the Works (notwithstanding Clause 13.2 ) and may at his discretion ensure early release to the Contractor of any unpaid balance of the Contract Sum provided that the Contractor shall and hereby agrees to give its Employer a full indemnity for latent defects appearing in the Works arising at any time following such occupation being taken. 18. Liability The rights and liabilities conferred upon the Employer by this Deed are in addition to any other rights and remedies it may have against the Contractor including without prejudice to the generality of the foregoing any remedies in negligence.”
“65. Although your Lordships do not need to resolve the issue in this case, it seems to me that there is much force in the point that the rules about circuity of action do not provide the explanation. I would prefer to say that the true basis of the rule is to be found in the contract between the parties. In Hopewell Project Management Ltd v Ewbank Preece Ltd[1998] 1 Lloyd’s Rep 448 , 458 Mr Recorder Jackson QC said that in his view it would be nonsensical if those parties who were jointly insured under a contractors’ all risks policy could make claims against one another in respect of damage to the contract works, that such a result could not possibly have been intended by those parties and that had it been necessary for him to do so he would have held that there was an implied term to that effect. I would be content to accept that as a satisfactory basis for the rule on which, had it been necessary for them to do so, Wimpey and Hall would have been entitled to resist the claim.”
“7. Under the contract and Wimpey’s all risks insurance policy, CRS would be effectively indemnified by the insurers’ provision of a fund enabling it to pay Wimpey by repairing the fire damage. The insurers could not then make a subrogated claim against Wimpey because Wimpey was a party co-insured (with CRS) under the policy, and the insurers would be obliged to indemnify Wimpey against any liability which might be established, an obvious absurdity. The rationale of this rule may be a matter of some controversy (although I lean towards the explanation favoured by the Court of Appeal) but the rule itself is not in doubt.”
“Part 1: Contractor’s Insurances Minimum limit of indemnity for public liability cover: (Clause 13.3.2):£2,000,000 Professional indemnity is/is not required (Clause 13.3.3): £ Minimum limit of indemnity for professional indemnity cover:£15,000,000 … Part 2: Employer’s Insurance Details of the Employer’s policy of insurance for the Project are set out in the attachments annexed hereto and the policy is available for inspection at the Employer’s principal place of business. The conditions of the Employer’s policy require the Contractor: □ to give prompt notification to the Construction Manager of all incidents likely to give rise to a claim under the policy; □ to advise the Construction Manager of any loss or damage which may exceed the said policy excess of£2,000,000 … Notice to Contractors On Insurance Provisions 1. Contract Works Cover to Contractors is limited to the Specified Perils detailed below on the permanent and temporary works and materials for incorporation therein… The policy excess which is the responsibility of the Contractor is£1,500 each and every loss… 2. Third Party Liability Public liability cover is not provided under the Project Policy. All Contractors must maintain their own Insurances for a minimum limit of indemnity of£2,000,000 any one occurrence… Specified Perils: Fire, lightning, explosion, storm, tempest, flood, bursting or overflowing of water tanks, apparatus or pipes, earthquakes, aircraft and other aerial devices or articles dropped therefrom, riot and civil commotion, (but excluding any loss or damage caused by ionising radiations or contaminations by radioactivity from any nuclear fuel, radioactive toxic explosive or other hazardous properties of any explosive nuclear assembly or nuclear component thereof, pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds).”
“There is also no dispute that although it was the obligation of [Rolls-Royce] under Clause 13.5 of the Contract to maintain joint names insurance of both the existing structures and of the Works (meaning thereby [Tyco’s] Works) [Rolls-Royce] failed to do so and at the time of the escape no such insurances were in force. That was a clear breach by [Rolls-Royce] of its obligations and may entitle [Tyco] to damages if it has suffered loss as a result of such breach. However, again, that is not in issue in this action. This action is concerned with the different question, namely whether the provisions in clause 13.5 of the Contract have the effect of relieving [Tyco] from liability in respect of the risks covered by the insurance which should have been in place under clause 13.5.”
“Rolls-Royce is demanding an indemnity from Tyco in the very circumstances against which it told Tyco that it need not take out liability insurance”
“As [Brooke LJ] pointed out [in the court of appeal in CRS], in the Surrey Heath case the court was concerned with the JCT Standard Form of Building Contract with Contractor’s Design, 1981 Edition. Clause 20.2 of that contract did not (unlike clause 20.3 in the present case) expressly exclude the works from the property in relation to which the contractor provided the employer with an indemnity if it was damaged through his negligence”
“The effect of the contractual agreement must always be a matter of construction. People are free to contract as they like. It may be the true construction that a provision for insurance is to be taken as satisfying or curtailing a contractual obligation, or it may be the true construction that a contractual obligation is to be backed by insurance with the result that the contractual obligation stands or is enforceable even if for some reason the insurance fails or proves inadequate.”
“First, condition 6.2 is primarily concerned with liability, that of the contractor, and requires it to insure in support of it. Condition 6.3B is concerned only with insurance, which it does not expressly relate to the existence or non-existence of any liability. It says nothing about liability. Neither condition refers to the other…” (at 30). Most of the specified perils for which insurance is required under condition 6.3B are of a type resulting only from natural phenomena – “Acts of God” – or are not normally the responsibility of either contracting party. That is how Slade LJ interpreted it in Dorset County Council v Southern Felt Roofing Company Ltd(1989) 48 BLR 96 , at page 106, when considering a comparable brace of provisions, the latter clearly imposing on the employer the risk of a number of similar natural hazards, including fire: “Now fire, no less than the impact of lightning, can occur without the negligence or fault of any human agency. If the draftsman chose to refer to a number of possible other causes of damage which involve no fault on the part of anyone, I do not see why, in referring to fire, he should not be taken to have similarly had in mind damage by fire occurring without negligence on the part of the Contractor.”
“Lord Hope concluded that where two parties entered into a contract which stipulated that one party had to obtain an insurance in the joint names for both, then one joint insured could not sue another joint insured for damages where the loss was covered by the insurance because there was an implied term in the contract preventing such action. That is the position in the present case. Mr Taverner was unable to provide a reason why the same result would not apply in this case, particularly given the addition of the “no right of recourse” provision in the contract.”
“58…in these cases there was no express link between the exclusion of the contractor’s liability for liability for fire and the employer’s obligation to insure. It was thus an open question whether it was the parties’ intention to exclude liability for a fire caused by the negligence of the contractor or those for whom he was responsible. No one could quarrel with a decision that that was not the intention of the parties. In that context the courts observed that the obligation of the employer to insure against fire did not extend to an obligation to insure against fire negligently caused by the contractor…These observations must, however, be read in their context and cannot apply to cases where it is expressly agreed that the insurance policy is to be in joint names and without recourse to rights of subrogation as between the co-insured. In such cases it would be absurd to exclude, from the ambit of the obligation to insure, fire negligently caused by one of the co-insured since that is the very instance in which subrogation would normally arise. [emphasis added] 59. Other things being equal, I would, like Aikens J (see paragraph 39), prefer to say that any building contract, which imposes an obligation on one of the parties to insure against the risk of fire, intends to require that party to insure against both fires caused by negligence of one of the parties and fires not so caused. That is what insuring against fire means, see eg Harris v Poland[1941] 1 KB 462 , 464-5 per Atkinson J. It does not mean that the party carrying out the insurance obligation must insure against some fires but need not insure against other fires. 60. But whatever the position in general might be, if a building contract exempts one of the parties from liability for loss or damage caused by specified perils which it then requires should be insured by a joint policy without right of subrogation between co-insurers, it makes no sense for the contract to be construed to permit loss or damage caused by the specified perils to be recoverable by one of the parties in cases where the peril occurs as a result of the negligence of the other party or those for whom he is responsible.”
“It is difficult to think of a wider scope of persons intended to be covered”
“Whatever might have been the position if there had been an express provision that [Tyco] had to insure against his own and his sub-contractor’s negligence that is not the present case…”
“There is in my judgment no justification for cutting down the clear meaning of those words which are perfectly apt to provide for insurance in respect of both negligent and non-negligent fires or water damage.”
“Having considered the terms of the Contract, although it is differently worded from the contract in CRS (and in other reported cases) nevertheless the Contract does in my judgment show a clear intention that damage caused by the Specified Perils whether to the Works or to the existing structures was to be treated differently from damage not involving the occurrence of a Specified Peril. In my judgment the indemnities given in clauses 2.3 and 9 should be read as subject to a special regime laid down in clause 13.5 in relation to damage caused by Specified Perils. Such reading of the Contract will give a sensible commercial effect to all the provisions of the Contract. The issue is not it seems to me one of excluding liability for negligence but rather of ascertaining how the parties have agreed that the risks and liabilities in relation to the Specified Perils are to be borne.”