“NGESO operates the transmission system in GB 2.10 The TOs “TOs” are Transmission Owners. and the OFTOs “OFTOs” are Offshore Transmission Owners. own and maintain the physical transmission infrastructure but they do not operate it. The system as a whole is operated by a single system operator: the Transmission System Operator (TSO). The TSO functions for the whole of GB, including offshore transmission, are performed by a separate system operator entity, NGESO. 2.11 The TSO is also responsible for keeping the electricity system balanced in real-time by coordinating the output of generating stations and ensuring that supply and demand are exactly matched, and all equipment is being operated within safe physical limits at all times. The tools and actions that NGESO use to do this are known as ‘Balancing Services’, and include, for example, paying particular generators to reduce or increase their output. Balancing Services are essential to the safe operation of the GB transmission system. 2.12 The nature of Balancing Services is that one balancing action can be used to serve multiple purposes (for instance imbalance, network constraints, voltage issues). Where a constraint on the capacity of a piece of infrastructure is the initial driver of a balancing action, the costs of that action will be categorised as a system ‘constraint’ cost in NGESO’s reporting of charges for Balancing Services, even in instances where taking that action has also resolved multiple issues that are not constraint-related. 2.13 The characteristics of electricity mean that quantities of energy generated and consumed are very likely to differ from the quantities for which contracts have been struck in advance. Consequently, central arrangements are required to: (a) meter the quantities produced and consumed; (b) compare these with the quantities covered by bilateral contracts between generators, interconnectors and suppliers; and (c) provide financial settlement for the differences (known as ‘imbalances’).”
“3.11 The balancing mechanism provides a means by which NGESO can buy or sell additional energy close to real-time to maintain energy balance, and also to deal with other operational constraints of the transmission system. The energy balancing aspect of the BSC specifies how parties can make submissions to NGESO to either buy or sell electricity into/out of the market at close to real time through the balancing mechanism. 3.12 The settlement aspect of the BSC specifies how the actual positions of generators and suppliers (and interconnectors) against their contracted positions are monitored and metered and how imbalances are settled when actual delivery or offtake does not match contractual positions. 3.13 The BSC is administered by Elexon Limited (Elexon), a not-for-profit company which carries out this financial settlement process. Elexon’s administrative costs are recovered through BSC charges. The method of calculation of these is set out in Section D of the BSC.”
“3.15 The licence conditions include the following: Condition C4.1(a) requires NGESO to set a use of system charging methodology which will be approved by GEMA; and C4.1(b) requires NGESO to conform to the methodology (as modified in accordance with standard condition C5 (Use of system charging methodology) and standard condition C10 (Connection and Use of System Code)). Standard condition C4 paragraph 7 states that for these purposes ‘charges do not include references to: (a) connection charges’. 3.16 By way of standard condition C10.2(d), the charging methodology is to be set out in the CUSC which NGESO is required by standard condition C10 to establish (see paragraph 3.21 below). The methodology for calculating TNUoS and BSUoS charges is in section 14 of the CUSC.”
“CUSC MODIFICATION PROPOSALS 8.16.1 … (b) A proposal to modify the Charging Methodologies may be made: (i) by a CUSC Party, by the Citizens Advice, by the Citizens Advice Scotland or by a BSC Party; or (ii) under Paragraph 8.28.5, by the CUSC Modifications Panel; or (iii) by a Relevant Transmission Licensee in relation to Exhibit O Part IB, Exhibit O Part IIB, Exhibit O Part IC and Exhibit O Part IIC only; or (iv) by a Materially Affected Party, unless otherwise permitted by the Authority. (v) by the Authority, or by The Company under the direction of the Authority, pursuant to Paragraph 8.17A.1.” (i) by a CUSC Party, by the Citizens Advice, by the Citizens Advice Scotland or by a BSC Party; or (ii) under Paragraph 8.28.5, by the CUSC Modifications Panel; or (iii) by a Relevant Transmission Licensee in relation to Exhibit O Part IB, Exhibit O Part IIB, Exhibit O Part IC and Exhibit O Part IIC only; or (iv) by a Materially Affected Party, unless otherwise permitted by the Authority. (v) by the Authority, or by The Company under the direction of the Authority, pursuant to Paragraph 8.17A.1.”
“… in accordance with the Transmission Licence, the Authority may approve the CUSC Modification Proposal or a Workgroup Alternative CUSC Modification(s) contained in the CUSC Modification Report (which shall then be an "Approved CUSC Modification" until implemented). If the Authority believes that neither the CUSC Modification Proposal (nor any Workgroup Alternative CUSC Modification(s)) would better facilitate achievement of the Applicable CUSC Objectives, then there will be no approval. In such a case, the Code Administrator will notify CUSC Parties and will raise the issue at the next CUSC Modifications Panel meeting.”
“8.17A AUTHORITY RAISED OR DIRECTED MODIFICATION 8.17A.1 The Authority may: (a) itself; or (b) direct The Company to raise a CUSC Modification Proposal where the Authority reasonably considers that such CUSC Modification Proposal is necessary to comply with or implement the Electricity Regulation and/or any relevant Legally Binding Decisions of the European Commission and/or The Agency or in respect of Significant Code Review.”
“(1) The internal market in electricity, which has been progressively implemented since 1999, aims to deliver real choice for all consumers in the Community, be they citizens or businesses, new business opportunities and more cross border trade, so as to achieve efficiency gains, competitive prices and higher standards of service, and to contribute to security of supply and sustainability. (2) Directive 2003/54/EC of the European Parliament and of the Council of26 June 2003 concerning common rules for the internal market in electricity and Regulation (EC) No 1228/2003 of the European Parliament and of the Council of26 June 2003 on conditions for access to the network for cross-border exchanges in electricity have made significant contributions towards the creation of such an internal market in electricity. (3) However, at present, there are obstacles to the sale of electricity on equal terms, without discrimination or disadvantage in the Community. In particular, non-discriminatory network access and an equally effective level of regulatory supervision do not yet exist in each Member State, and isolated markets persist.”
“… the Commission should be empowered to establish or adopt the Guidelines necessary for providing the minimum degree of harmonisation required to achieve the aims of this Regulation.”
“…a situation in which an interconnection linking national transmission networks cannot accommodate all physical flows resulting from international trade requested by market participants, because of a lack of capacity of the interconnectors and/or the national transmission systems concerned.”
“1. General Provisions 1.1. Transmission system operators (TSOs) shall endeavour to accept all commercial transactions, including those involving cross-border-trade. 1.2. When there is no congestion, there shall be no restriction of access to the interconnection. Where this is usually the case, there need be no permanent general allocation procedure for access to a cross-border transmission service. … 2. Congestion-management methods 2.1. Congestion-management methods shall be market-based in order to facilitate efficient cross-border trade. For that purpose, capacity shall be allocated only by means of explicit (capacity) or implicit (capacity and energy) auctions. Both methods may coexist on the same interconnection. For intra-day trade continuous trading may be used.”
“17. ‘ancillary service’ means a service necessary for the operation of a transmission or distribution system…”
“Article 37 Duties and powers of the regulatory authority 1. The regulatory authority shall have the following duties: (a) fixing or approving, in accordance with transparent criteria, transmission or distribution tariffs or their methodologies; (b) ensuring compliance of transmission and distribution system operators and, where relevant, system owners, as well as of any electricity undertakings, with their obligations under this Directive and other relevant Community legislation, including as regards cross-border issues; … (d) complying with, and implementing, any relevant legally binding decisions of the Agency and of the Commission; … (l) respecting contractual freedom with regard to interruptible supply contracts and with regard to long-term contracts provided that they are compatible with Community law and consistent with Community policies; … (q) monitoring the implementation of rules relating to the roles and responsibilities of transmission system operators, distribution system operators, suppliers and customers and other market parties pursuant to Regulation (EC) No 714/2009…”
“Transmission system operators shall receive compensation for costs incurred as a result of hosting cross-border flows of electricity on their networks on the basis of the guidelines set out in Part A of the Annex.”
“Charges applied by network operators for access to the transmission system shall be in accordance with guidelines set out in Part B of the Annex.”
“(10) Variations in charges faced by producers of electricity for access to the transmission system should not undermine the internal market. For this reason average charges for access to the network in Member States should be kept within a range which helps to ensure that the benefits of harmonisation are realised.”
“a transmission line which crosses or spans a border between Member States and which connects the national transmission systems of the Member States” (ii) Article 2(4) defines “congestion” as: “… a situation in which all requests from market participants to trade between network areas cannot be accommodated because they would significantly affect the physical flows on network elements which cannot accommodate those flows”; (iii) Article 2(6) defines “structural congestion” as: “… congestion in the transmission system that is capable of being unambiguously defined, is predictable, is geographically stable over time, and frequently reoccurs under normal electricity system conditions.” (iv) Article 2(60) provides that: “‘ancillary service’ means ancillary service as defined in point (48) of Article 2 of Directive (EU) 2019/944.”
“a service necessary for the operation of a transmission or distribution system, including balancing and non-frequency ancillary services, but not including congestion management”
“Set the Transmission Generation Residual to zero, subject to maintaining compliance with [Annex B].... The ESO is developing a modification which would enact the post CMP261 definition of the [Permitted Range], and would allow us to direct that our policy position of no residuals charged to generation is met.”
“45. The Proposal(s) must set out proposals to modify the Use of System Charging Methodology, Section 14 CUSC to set the TGR to£0 , subject to ensuring ongoing compliance with EU Regulation No 838/2010 (in particular, the requirement that average transmission charges paid by producers in each Member State must be within prescribed ranges – which for Ireland, Great Britain and Northern Ireland is 0 to 2.50 EUR/MWh). This should be achieved by charging generators all applicable charges (having factored in the correct interpretation of the connection exclusion as set out in EU Regulation 838/2010) and adjusted if needed to ensure compliance with the 0 to 2.50 EUR/MWh range. 46. …the Proposal(s) must set out proposals for an appropriate adjustment charge to ensure compliance with the EU Regulation 838/2010, if NGESO considers it necessary…”
“What the Code requires … is compliance with the legal standard. Something that amounts to a nearer miss than the pre-existing state of affairs is not good enough” ([2022] EWHC 987 at paragraph [16]). In the judgment under appeal at paragraph [45] the Judge said: “ … I accept the factual premises of the proposition. The modification proposal that GEMA approved made things better insofar as the amendment made to the CUSC prevented transmission charges outside the specified range. It was, in that regard, an improvement on the unamended provisions of paragraph 14.14.5 of the CUSC. I also accept that the criterion at paragraph 8.23.7 of the CUSC, for approval of a modification, is whether GEMA is satisfied that what is proposed "would better facilitate achievement of the Applicable CUSC Objectives". In many circumstances that criterion will bring with it a practical margin of judgement for GEMA as expert regulator. This may be particularly significant when assessment of a modification proposal requires a balance to be struck between overlapping or competing practical considerations. But that was not this case. The relevant objective was compliance with a legal standard and in that context a miss is as good as a mile. In the circumstances of this case, it is immaterial that the amendment to the CUSC improved the situation, making for a situation that better complied with Regulation 838/2010. Actual compliance with Regulation 838/2010 was what was required to permit GEMA to approve this aspect of modification proposal CMP 317/327.”
“In circumstances where this was an explicitly short term solution, with NGESO expected to bring forward a further CUSC modification proposal to align the correct methodology with GEMA’s own (in the CMA’s view correct) interpretation of the Connection Exclusion, the CMA’s view was that GEMA had not fallen into legal error in approving CMP 317/327”
“GEMA is wrong to suggest that some constructions are more erroneous than others. A construction of a legal provision is either right or wrong…”
“GEMA is wrong … to suggest that if any of the proposed amendments was assessed to be better than the status quo, it could lawfully be chosen as a “stop gap” measure. That would suggest that an unlawful construction of legislation could be adopted and applied if it represented the “least bad” option. That is not a lawfully relevant consideration. The Court does not permit a public body to maintain an error of law for the sake of expediency, until it can be redressed in a more lasting fashion: R v. Paddington Valuation Officer ex p Peachey[1966] 1 QB 380 , CA, per Danckwerts LJ at p. 418 and Salmon LJ at p. 419. To do so would subvert the rule of law.”
“Historical compliance with the Limiting Regulation In addition to bringing forward future modification(s) as set out above, NGESO should evaluate whether there has been non-compliance with the Limiting Regulation in 2020-21 and/or previous charging years as a result of the i) the inclusion in the CUSC Calculation of Distributed Generator volumes and charges; and/or ii) the fact that the CUSC Calculation is based on an erroneous interpretation of the Connection Exclusion. We understand that NGESO’s initial assessments indicate that it is unlikely that there has been any non-compliance in respect of previous charging years. The position in respect of this current charging year is less clear and requires further investigation. If and insofar as any non-compliance is identified, we expect NGESO to bring forward additional modifications to address such issues. We will work together with NGESO to understand the compliance position in respect of previous years.”
“Under the status quo, there is a serious and imminent risk of a breach of the lower limit of the Permitted Range. We understand from the ESO that the estimated value of offshore Local Charges in Charging Year 2021-2022 is c.£423m and estimated generator output is 223 TWh (or 223 million MWh). We expect that the vast majority, if not all, of these charges would fall within the Connection Exclusion, but the current CUSC Calculation assumes that they do not, and therefore takes them into account. The effect of including these charges in the CUSC Calculation is to increase calculated average charges by£1.90 /MWh above what would otherwise be the case (and thus to produce a matching increase in the negative adjustment made by the TGR). On the basis of currently-forecast GBP/EUR exchange rates of around 1.1, this is equivalent to€2.09 /MWh. Taking into account a c.20% ex ante error margin, there is therefore a serious risk under the status quo that annual average transmission charges (calculated in accordance with the Limiting Regulation) will fall below the lower limit of the Permitted Range. This would constitute non-compliance with the Limiting Regulation. Since the Baseline presents an immediate risk of non-compliance with the Limiting Regulation, we consider that a proposal which would secure compliance (or reduce the risk of such non-compliance) would represent an improvement on the status quo. Approval of such an option would be preferable to allowing the status quo to remain (whether by rejecting all proposals or exercising our send back powers).”
“The Authority therefore needs to choose between the imperfect status quo and a series of imperfect alternatives. It is open to the Authority to approve a modification proposal which is based on an incorrect interpretation of the Connection Exclusion, if that proposal is better than the (imperfect) Baseline and the other (imperfect) proposals at facilitating the achievement of the ACOs.”
“Our decision We have considered the issues raised by the modification proposals and the FMR dated13 August 2020 , including taking into account the responses to the Workgroup Consultation and Code Administrator Consultation. We have also considered and taken into account the votes of the Workgroup and the CUSC Panel on CMP317/327. We do not consider that any of the proposals incorporate the correct interpretation of the Connection Exclusion. Notwithstanding this, we have concluded that the Original Proposal would be likely to avoid the imminent risk of a breach of the Limiting Regulation that is posed by the status quo, and better facilitate achievement of the ACOs than either the status quo or any of the WACMs. We also consider that approval of the Original Proposal would be consistent with our principal objective and statutory duties. Accordingly, our decision is to approve the Original Proposal and direct that it be implemented. Our approval of the Original Proposal is on the express basis that it is a ‘stop-gap’ measure which should avert an imminent risk of breach of the Limiting Regulation, and allow time for the formulation of a longer-term solution that properly reflects the correct interpretation of the Connection Exclusion. We expect NGESO to bring forward a further CUSC Modification Proposal that will fully give effect to the correct interpretation of the Connection Exclusion. We also expect NGESO to bring forward a CUSC Modification Proposal to remove from the CUSC Calculation the TNUoS Charges payable by Large Distributed Generators and their associated volumes (MWh). The need for this further modification is explained in more detail in the ‘Future Modifications’ section below.”
“In this section we address Ground 3 of the Appellants’ NoA, namely that GEMA erred in law in its construction of the Ancillary Services Exclusion (ASE) and its corresponding treatment of (i) the relevant BSUoS charges; and (ii) the relevant BSC charges. It was wrong, the Appellants said, to treat those charges as falling within the ASE and accordingly not limited by the Permitted Range for the average annual transmission charges Generators pay.”
“71. … I consider the reasoning in the CMA's decision is correct. As with most arguments of statutory instruction there are points that can be made for both sides of the argument. SSEGL places reliance on several linguistic points for example, that in some other provisions in the 2019 Regulation specific reference is made to congestion arising from use of interconnectors (see article 19), and that in other provisions congestion must include reference to congestion within a transmission network. SSEGL also submits that it is not possible to divorce congestion that affects the use of interconnectors from congestion within a network. However, I consider there are two matters within the CMA reasoning that clearly tip the balance in favour of the conclusion it reached. The first is that the notion of congestion charging is defined as congestion arising from requests to trade between network areas. I accept the point made at paragraph 8.56 of the CMA's decision that this is synonymous with a request to trade across an interconnector. The second is the point at paragraph 8.59 of the CMA's decision, the distinction drawn between congestion management services and balancing and non-frequency allocation services. I am satisfied that the CMA's conclusion was correct, and for this reason, the second part of SSEGL's Ground 3 also fails.”
“…a situation in which an interconnection linking national transmission networks cannot accommodate all physical flows resulting from international trade requested by market participants, because of a lack of capacity of the interconnectors and/or the national transmission systems concerned.”
“…a service necessary for the operation of a transmission or distribution system, including balancing and non-frequency ancillary services, but not including congestion management.”
“congestion” means a situation in which all requests from market participants to trade between network areas cannot be accommodated because they would significantly affect the physical flows on network elements which cannot accommodate those flows;”
“Network congestion problems shall be addressed with non-discriminatory market-based solutions which give efficient economic signals to the market participants and transmission system operators involved. Network congestion problems shall be solved by means of non-transaction-based methods, namely methods that do not involve a selection between the contracts of individual market participants. When taking operational measures to ensure that its transmission system remains in the normal state, the transmission system operator shall take into account the effect of those measures on neighbouring control areas and coordinate such measures with other affected transmission system operators as provided for in Regulation (EU) 2015/1222.”
“‘congestion’ means a situation in which an interconnection linking the Great Britain transmission network with the transmission network of another country or territory cannot accommodate all physical flows resulting from international trade required by market participants, because of a lack of capacity of the interconnectors or the transmission systems concerned.”
“… a transmission line which crosses or spans a border between Great Britain and another country or territory and which connects the national transmission system of Great Britain with the transmission system of that other country or territory.”
“i) When construing an enactment, including the exercise of power under an enactment, it is relevant to identify the intention or purpose of the measure, i.e. the mischief to which it is directed. ii) In all cases (save with regard to consolidating enactments) the purpose or mischief may be identified by the posing of questions (cf Lord Bingham in Quintavalle) such as: If the legislation has changed, what has changed? If there is a problem which had to be resolved, what was the problem? If there was a blemish in the legislation, what was that blemish? If there was an improvement which was sought to be achieved, what was that improvement?”
“It is presumed that the legislator intends the court to apply a construction which rectifies any error in the drafting of the enactment, where required in order to give effect to the legislative intention”
“This power is confined to plain cases of drafting mistakes. The courts are ever mindful that their constitutional role in this field is interpretative. They must abstain from any course which might have the appearance of judicial legislation. A statute is expressed in language approved and enacted by the legislature. So the courts exercise considerable caution before adding or omitting or substituting words. Before interpreting a statute in this way the court must be abundantly sure of three matters: (1) the intended purpose of the statute or provision in question; (2) that by inadvertence the draftsman and Parliament failed to give effect to that purpose in the provision in question; and (3) the substance of the provision Parliament would have made, although not necessarily the precise words Parliament would have used, had the error in the Bill been noticed. The third of these conditions is of crucial importance. Otherwise any attempt to determine the meaning of the enactment would cross the boundary between construction and legislation: see Lord Diplock in Jones v. Wrotham Park Settled Estates [1980] A.C. 74, 105. In the present case these three conditions are fulfilled. Sometimes, even when these conditions are met, the court may find itself inhibited from interpreting the statutory provision in accordance with what it is satisfied was the underlying intention of Parliament. The alteration in language may be too far-reaching. In Western Bank Ltd v. Schindler[1977] Ch 1 , 18, Scarman L.J. observed that the insertion must not be too big, or too much at variance with the language used by the legislature. Or the subject matter may call for a strict interpretation of the statutory language, as in penal legislation. None of these considerations apply in the present case. Here, the court is able to give effect to a construction of the statute which accords with the intention of the legislature.”
“iii) To identify the purpose or mischief and to answer these questions it is permissible to examine Explanatory Notes, White and Green Papers, Ministerial statements (Bradley) and Law Commission Reports, all of which may be admissible forms of evidence. iv) However, not all such admissible sources are of equal weight. Those sources (such as Explanatory Notes) whose "shape" was closely connected to the "shape of the proposed legislation" may be more informative as guides (Westminster City Council) than other sources which are more remote from the final language selected by Parliament. v) In addition, a court may draw inferences from the statutory words actually used in the scheme of the legislation as a whole and from any case law on the underlying subject matter and a court might ask whether it may be inferred that Parliament intended to act consistently with the standard set out in case law (Chetnik). vi) Material that is admissible will reflect the views of their authors. And the views of authors, including the Government of the day, do not necessarily reflect the will of Parliament (Westminster City Council). If there is an inconsistency between the statutory language and the pre-legislative, admissible, material it cannot, without more, therefore be assumed that the statutory purpose must reflect the purpose set out in pre-existing admissible material. vii) However, if there is a collision between a literal interpretation of an enactment and the contextual material with the consequence that the literal interpretation "is manifestly contrary to the intention which one may readily impute to Parliament, when having regard to the historical context and the mischief…", then the enactment should be construed in the light of the purpose as evident from the historical context and mischief (R v Z per Lord Carswell).”