“36. [I]n outline: (1) The procedure consists of two 'rounds'. First, after receipt of the Delivery Notice, Lotus had to give either an Acceptance Notice (as defined in paragraph 1.1.1 of Schedule 2 …), in which case the Film was accepted and completion and delivery of the Film was effected, or an Objection Notice (as defined in paragraph 1.1.2 of Schedule 2 …), specifying the ways in which the delivered materials were said to be defective. (2) In the event of an Objection Notice, EFB The Delivery Procedure permits steps to be taken by EFB or the Guarantor. For convenience, the Judge’s outline referred only to EFB. could then request additional information in relation to it and/or request return of the delivered materials, such return to be "at the requesting party's expense in order to allow … EFB … to cure the defects in such Lotus Delivery Materials" (paragraph 1.1.2 of Schedule 2 …). [I interpose that any request for the materials to be returned had to be made, if at all, within three days after receiving the Objection Notice or a Response and the materials were to be returned within five business days of receipt of the request.] (3) After Lotus had complied with these requests, EFB could either redeliver the materials (with defects cured as necessary) with a Cure Notice or serve an Arbitration Notice. This latter course would, in effect, constitute a challenge to the justification for the original Objection Notice. [I interpose that these steps were covered by paragraph 3 of Schedule 2] (4) In the former event (redelivery of materials with defects cured as necessary), the second 'round' commenced: Lotus could again either give an Acceptance Notice or it could give an Additional Objection Notice. In the latter event, EFB would have a further entitlement to request additional information in relation to the Additional Objection Notice and/or to request return of the re-delivered materials "physically delivered" to Lotus. [I interpose that it is at this stage that the material part of paragraph 5.2 may operate: as to which see below.] (5) Once these requests had been complied with, EFB could either again redeliver the materials (with defects cured as necessary) with an Additional Cure Notice or serve an Arbitration Notice. This latter course would, in effect, constitute a challenge to the justification for the Additional Objection Notice. (6) In the former event (second redelivery of materials with defects cured as necessary), Lotus could then either give an Acceptance Notice or it could give an Arbitration Notice. 37. Each of these steps was subject to a time limit. As a general proposition, the second 'round' was intended to be more compressed than the first 'round' for both Lotus and EFB. Thus: (1) On Lotus's side, in 'round' one, Lotus had 30 days from its receipt of the Delivery Notice in which to give an Objection Notice or an Acceptance Notice (paragraph 1.1 of Schedule 2 …). In 'round' two, Lotus had 15 Business Days from its receipt of the Cure Notice in which to give an Additional Objection Notice or an Acceptance Notice (paragraph 5 of Schedule 2 …). ("Business Days" were defined in clause 2.2 … as being "any day other than a Saturday, Sunday or a day on which banks in Germany or England are required to be closed".) (2) As for EFB, in 'round' one, if it received an Objection Notice, EFB had to redeliver the cured materials and give a Cure Notice within 30 days of the later of "(i) receiving the Objection Notice or the Response, as applicable, or (ii) the return of any Lotus Delivery Materials … " (paragraph 3.1 of Schedule 2 …). In 'round' two, if EFB received an Additional Objection Notice, the time for redelivery of the cured materials and the giving of an Additional Cure Notice was no later than within 15 Business Days of the later of "(i) receiving the Additional Objection Notice or the Second Response, as applicable, or (ii) the return of any Lotus Delivery Materials…" (paragraph 6.1 of Schedule 2 …). [I interpose that the periods of 30 days and 15 Business Days respectively were described as the “Cure Period”.] 38. A tight timetable was maintained in Schedule 2 … from the giving of the original Delivery Notice through to the end of any arbitral process. For example, paragraph 11 of Schedule 2 … provides that any arbitration was to be "expedited"; two arbitrators were to be appointed within five Business Days of any Arbitration Notice, with a third to be appointed three Business Days later; the arbitration was to commence within seven Business Days thereafter; the arbitrator was to issue an award not later than one day after the conclusion of the arbitration. 39. Schedule 2 … also spelt out the consequences of any failure to complete a step within the specified time: (1) In the event of a failure by Lotus to respond with either an Acceptance Notice or an Objection Notice within the time periods specified, it would be deemed to have given an Acceptance Notice (see paragraphs 2 and 9 of Schedule 2 …). It would no longer be possible for any objection to be made, an Acceptance Notice shall be conclusively presumed to have been given and "completion and delivery of the Film shall be conclusively presumed to have been effected". (2) In the event of a failure by EFB to deliver either a Cure Notice or Arbitration Notice with the time periods specified, an Arbitration Notice would be deemed to have been given (paragraphs 4 and 7 of Schedule 2 …). The provisions permitting the cure of defects would therefore come to an end. EFB would thus be deprived of the opportunity to cure any of the defects alleged and be compelled to arbitrate on the basis of the Film as it was.”
"If [ ] gives an Additional Objection Notice and in such notice the Sales Agent contends that some or all of the Lotus Delivery Materials are not suitable for the making of commercially acceptable release prints or broadcast materials, to the extent that the Lotus Delivery Materials which the Sales Agent contends are not of technical quality suitable for the making of commercially acceptable release prints or broadcast material (as appropriate) have been physically delivered to the Sales Agent within three (3) days after the Sales Agent's receipt of … EFB's … written request (which request … EFB … shall make (if at all) within five (5) Business Days after receiving the Additional Objection Notice), the Sales Agent shall return those Lotus Delivery Materials requested by … EFB at the Guarantor's expense, in order to allow EFB… to cure the defects in "such Lotus Delivery Materials as appropriate." (Emphasis added to highlight the critical word – return)
"If (i) the Sales Agent fails to give any of the notices described in paragraphs 5.1, 5.2, 8.1 or 8.2 above or (ii) the Sales Agent fails to return to EFB… the Lotus Delivery Materials within the time period specified in paragraph 5.2 above, then completion and delivery of the Film shall be conclusively presumed to have been effected and the Sales Agent shall be conclusively presumed to have issued an Acceptance Notice. EFB … shall thereupon give notice to the Beneficiaries that completion and delivery of the Film shall be conclusively presumed to have been effected and that the Sales Agent shall be conclusively presumed to have issued an Acceptance Notice but failure to give such notice by EFB … to the Beneficiaries shall not affect the fact that completion and delivery of the Film shall be conclusively presumed to have been effected and that the Sales Agent shall be conclusively presumed to have issued an Acceptance Notice."
“40. Following EFB's delivery of the Lotus Delivery Materials and giving of the Delivery Notice on30 May 2018 , the subsequent steps of the Delivery Procedure were followed. In particular, pursuant to paragraph 1.1 of Schedule 2 to the CGA: (1) Lotus's response was required within "30 days from and after its receipt of … the Delivery Notice" (i.e. by29 June 2018 ). On27 June 2018 , Lotus gave an Objection Notice stating: "This notice constitutes an Objection Notice for the purposes of Schedule 2 of the [Completion Guarantee]". … The Objection Notice made various complaints, which included complaints that the Lotus Delivery Materials were not in accordance with the Approved Picture Specification, defined in paragraph 1.1.2 of Schedule 2 to the CGA and attached a quality control report alleging objections that the delivered materials were not if technical quality suitable for the making of commercially acceptable release prints. (2) Any request for additional information was required "within 3 Business Days … after receiving [the] Objection Notice" (i.e. by2 July 2018 ). On2 July 2018 , EFB made such a request for additional information. (3) Lotus had "3 Business Days after its receipt of [the] request" in which to respond in good faith thereto (i.e. by5 July 2018 ). On5 July 2018 , Lotus responded, stating "This is a response, prepared in good faith … for the purposes of Schedule 2 "Delivery Procedure" clause 1.1.2 of the [Completion Guarantee] … All of [Lotus's] rights in each and any jurisdiction are reserved." (4) Any request for return of the Lotus Delivery Materials had to be made "within 3 Business Days after receiving the Objection Notice or a Response, as applicable". On10 July 2018 , EFB requested return of the Lotus Delivery Materials to "EFB c/o Paul Dray at Lip Sync Productions LLP, 195 Wardour Street, London W1F 8ZG." (5) Lotus were required to return the Lotus Delivery Materials to EFB "within 5 Business Days after the Sales Agent's receipt of … EFB's … written request" (i.e. by17 July 2018 ). On16 July 2018 , the Lotus Delivery Materials were delivered to EFB (c/o Lip Sync as requested). They had been collected by FedEx from Lotus at 3.45pm (LA time) on13 July 2018 (a Friday) and had arrived at Stansted Airport the following day. Since it appears that Lotus had not elected for weekend delivery, they were not delivered until Monday16 July 2018 . 41. Pursuant to paragraph 3.1 of Schedule 2…, the cured Lotus Delivery Materials had to be delivered to Lotus, and a Cure Notice had to be given, "no later than 30 days after the later of (i) receiving the Objection Notice or the Response as applicable, or (ii) the return of any Lotus Delivery Materials as appropriate which … EFB … has requested in order to cure any claimed defects" (i.e. by15 August 2018 , "30 days after … the return of [the] Lotus Delivery Materials … which … EFB …. ha[d] requested"). On14 August 2018 the Lotus Delivery Materials were delivered to Lotus by EFB. They were collected by a courier, Team Air, at 6.00pm (London time) on13 August 2018 and delivered to Los Angeles the following day at 5.55pm (LA time). The Cure Notice was given on15 August 2018 . 42. That led to 'round' two. Lotus had "15 Business Days from and after receipt of [the Cure Notice] and the relevant Lotus Delivery Materials" in which to give an Additional Objection Notice or an Acceptance Notice: paragraph 5 of Schedule 2 to the CGA (i.e. by6 September 2018 ). (1) On17 August 2018 , Lotus wrote confirming that, under paragraph 5 of Schedule 2 …, and in the light of the intervening August bank holiday in England on27 August 2018 , the date required for a response was6 September 2018 . On5 September 2018 , Lotus gave an Additional Objection Notice (again including a quality control report). On that occasion reference was made only to "clause 5.2 of Schedule 2 …". … . (2) Any second request for additional information was required "within 3 Business Days … after receiving [the] Additional Objection Notice ": paragraph 5.2 of Schedule 2 (i.e. by10 September 2018 ). On10 September 2018 , EFB made a request for additional information. (3) Lotus had "3 Business Days after its receipt of [the] request" in which to respond: paragraph 5.2 of Schedule 2 … (i.e. by13 September 2018 ). On13 September 2018 , Lotus responded. The letter stated: "This is a response, prepared in good faith … for the purposes of Schedule 2 "Delivery Procedure" clause 5.2 of the [Completion Guarantee] … All of [Lotus's] rights in each and any jurisdiction are reserved". (4) Any request for the return of the Lotus Delivery Materials "physically delivered" to Lotus had to be made "within 5 Business Days after receiving the Additional Objection Notice": paragraph 5.2 of Schedule 2 (i.e. by12 September 2018 ). In contrast to 'round' one, the time for the request for the return of materials was fixed by reference to the date of receipt of the Additional Objection Notice alone. EFB could not wait until after the receipt of the second response to the request for additional information. On12 September 2018 , EFB requested the return of the Lotus Delivery Materials. Once again, the request specified that the return should be made to "EFB c/o Paul Dray at Lip Sync Productions LLP, 195 Wardour Street, London W1F 8ZG." Given the 8 hour time difference between the UK and Los Angeles, the request would have to be received early in the morning by Lotus. (5) Lotus were required to return the Lotus Delivery Materials to EFB "within 3 days after the Sales Agent's receipt of … EFB's … written request": paragraph 5 of Schedule 2 … (i.e. by15 September 2018 ). It is common ground that the Lotus Delivery Materials were not delivered to EFB by that date. Part of the Lotus Delivery Materials were delivered on17 September 2018 and part were delivered on18 September 2018 .” (1) Lotus's response was required within "30 days from and after its receipt of … the Delivery Notice" (i.e. by29 June 2018 ). On27 June 2018 , Lotus gave an Objection Notice stating: "This notice constitutes an Objection Notice for the purposes of Schedule 2 of the [Completion Guarantee]". … The Objection Notice made various complaints, which included complaints that the Lotus Delivery Materials were not in accordance with the Approved Picture Specification, defined in paragraph 1.1.2 of Schedule 2 to the CGA and attached a quality control report alleging objections that the delivered materials were not if technical quality suitable for the making of commercially acceptable release prints. (2) Any request for additional information was required "within 3 Business Days … after receiving [the] Objection Notice" (i.e. by2 July 2018 ). On2 July 2018 , EFB made such a request for additional information. (3) Lotus had "3 Business Days after its receipt of [the] request" in which to respond in good faith thereto (i.e. by5 July 2018 ). On5 July 2018 , Lotus responded, stating "This is a response, prepared in good faith … for the purposes of Schedule 2 "Delivery Procedure" clause 1.1.2 of the [Completion Guarantee] … All of [Lotus's] rights in each and any jurisdiction are reserved." (4) Any request for return of the Lotus Delivery Materials had to be made "within 3 Business Days after receiving the Objection Notice or a Response, as applicable". On10 July 2018 , EFB requested return of the Lotus Delivery Materials to "EFB c/o Paul Dray at Lip Sync Productions LLP, 195 Wardour Street, London W1F 8ZG." (5) Lotus were required to return the Lotus Delivery Materials to EFB "within 5 Business Days after the Sales Agent's receipt of … EFB's … written request" (i.e. by17 July 2018 ). On16 July 2018 , the Lotus Delivery Materials were delivered to EFB (c/o Lip Sync as requested). They had been collected by FedEx from Lotus at 3.45pm (LA time) on13 July 2018 (a Friday) and had arrived at Stansted Airport the following day. Since it appears that Lotus had not elected for weekend delivery, they were not delivered until Monday16 July 2018 . (1) On17 August 2018 , Lotus wrote confirming that, under paragraph 5 of Schedule 2 …, and in the light of the intervening August bank holiday in England on27 August 2018 , the date required for a response was6 September 2018 . On5 September 2018 , Lotus gave an Additional Objection Notice (again including a quality control report). On that occasion reference was made only to "clause 5.2 of Schedule 2 …". … . (2) Any second request for additional information was required "within 3 Business Days … after receiving [the] Additional Objection Notice ": paragraph 5.2 of Schedule 2 (i.e. by10 September 2018 ). On10 September 2018 , EFB made a request for additional information. (3) Lotus had "3 Business Days after its receipt of [the] request" in which to respond: paragraph 5.2 of Schedule 2 … (i.e. by13 September 2018 ). On13 September 2018 , Lotus responded. The letter stated: "This is a response, prepared in good faith … for the purposes of Schedule 2 "Delivery Procedure" clause 5.2 of the [Completion Guarantee] … All of [Lotus's] rights in each and any jurisdiction are reserved". (4) Any request for the return of the Lotus Delivery Materials "physically delivered" to Lotus had to be made "within 5 Business Days after receiving the Additional Objection Notice": paragraph 5.2 of Schedule 2 (i.e. by12 September 2018 ). In contrast to 'round' one, the time for the request for the return of materials was fixed by reference to the date of receipt of the Additional Objection Notice alone. EFB could not wait until after the receipt of the second response to the request for additional information. On12 September 2018 , EFB requested the return of the Lotus Delivery Materials. Once again, the request specified that the return should be made to "EFB c/o Paul Dray at Lip Sync Productions LLP, 195 Wardour Street, London W1F 8ZG." Given the 8 hour time difference between the UK and Los Angeles, the request would have to be received early in the morning by Lotus. (5) Lotus were required to return the Lotus Delivery Materials to EFB "within 3 days after the Sales Agent's receipt of … EFB's … written request": paragraph 5 of Schedule 2 … (i.e. by15 September 2018 ). It is common ground that the Lotus Delivery Materials were not delivered to EFB by that date. Part of the Lotus Delivery Materials were delivered on17 September 2018 and part were delivered on18 September 2018 .”
“(1) The court's task is to ascertain the objective meaning of the language which the parties have chosen to express their agreement. It has long been accepted that this is not a literalist exercise focused solely on a parsing of the wording of the particular clause, but that the court must consider the contract as a whole and, depending on the nature, formality and quality of drafting of the contract, give more or less weight to elements of the wider context in reaching its view as to that objective meaning. (2) Interpretation is a unitary exercise; where there are rival meanings, the court can give weight to the implications of rival constructions by reaching a view as to which construction is more consistent with business common sense. But, in striking a balance between the indications, given by the language and the implications of the competing constructions, the court must consider the quality of drafting of the clause. (3) The court must also be alive to the possibility that one side may have agreed to something which with hindsight did not serve his interest. This exercise involves checking each suggested interpretation against the provisions of the contract and investigating its commercial consequences. Similarly, the court must not lose sight of the possibility that a provision may be a negotiated compromise or that the negotiators were not able to agree more precise terms. (4) Textualism and contextualism are not conflicting paradigms in a battle for exclusive occupation of the field of contractual interpretation. Rather, the lawyer and the judge, when interpreting any contract, can use them as tools to ascertain the objective meaning of the language which the parties have chosen to express their agreement. The extent to which each tool will assist the court in its task will vary according to the circumstances of the particular agreement or agreements. (5) Account should be taken of the fact that negotiators of complex formal contracts may often not achieve a logical and coherent text because of, for example, the conflicting aims of the parties, failures of communication, differing drafting practices, or deadlines which require the parties to compromise in order to reach agreement. There may often therefore be provisions in a detailed professionally drawn contract which lack clarity and the lawyer or judge in interpreting such provisions may be particularly helped by considering the factual matrix and the purpose of similar provisions in contracts of the same type.”