“Our Environmental Health team has objected to these applications on noise grounds. In view of their objections, I am currently writing both applications up for refusal. As a Prior Approval application and with the applicant having no available control over noise from nearby commercial premises, I can see no way in which the applications could be amended to address these concerns. I hope we will be able to issue a decision in the next day or two.”
“Thanks Tony, I have arranged a meeting with our acoustic surveyor and Brian Cox the acoustic office[r] in Crawley Council for Thursday the 4th to meet on site at 12 pm. Can you pls call Hamish and have him push off the decision till after the meeting”
“Tony, I have spoken now to Hamish as I can not get through to you and he has agreed that you should send him an email that we are meeting on Thursday at 12pm with Brian Cox and thus you allow the decision to be extended (otherwise the decision is on the 5th of May which is Saturday and Hamish is not in on the Friday so it will be determined on Thursday so there is no point meeting..) So please send Hamish a[n] email asap that you are allowing the decision to be extended. He is waiting for your email”
“Good afternoon and I hope that all is well with you and I refer to the two prior notification applications on the above sites. As set out in my client’s email below I understand that the meeting is to occur in terms of the potential issue around noise disturbance and on the basis of Part W of the Order I set out that my client would be willing to agree a new determination date for both applications until12 May 2018 and if any further extensions are required in order to resolve this matter then I would be happy to agree these with you in advance.”
“Thanks for your email. I will certainly discuss this with my manager although, as I explained to Mr Gluck earlier, I cannot see any way in which a Prior Approval application could be amended to address the noise concerns that have been raised.”
“We are aware that our client’s agent offered by email … to extend the determination deadline for the Applications until12 May 2018 , and that a meeting was held to discuss the Applications on3 May 2018 . However, there is no record of the Council agreeing in writing to extend the time limits, as expressly required by Article 7 of the Order. Indeed, the case officer responded to the above email stating that ‘I will certainly discuss this with my manager although, as I explained to Mr Gluck earlier, I cannot see any way in which a Prior Approval application could be amended to address the noise concerns that have been raised’. This is quite clearly not in any way an expression of agreement to an extension of time by the Council (though in any event it is not clear that an implied agreement would suffice), but instead is an affirmation that the Council was intending to determine the Applications in accordance with its own (albeit erroneous) calculation of the 56-day timescales. There was therefore no written agreement to extend time, and the 56-day timescales to determine the Applications remained.”
“9. On27 April 2018 the Council received an email from the appellant’s agent, stating that, ‘my client would be willing to agree a new determination date for both applications until12 May 2018 …’. The Council argue that, in accordance with Article 7 (c) of the GPDO, it had the appropriate written notice from the appellant that a longer period to the 56 day determination period had been agreed and both decisions were made before that period expired. 10. The appellant contends that he did not give written notice for a longer period to the 56 days and that the Council have implied an extension by context. This is unacceptable as the GPDO only allows deadlines to be extended ‘through express and unequivocal written agreement’. Furthermore, the email of27 April 2018 from his agent to the Council stated that the appellant would be ‘willing’ to extend the deadline which is an offer and not a formal agreement. 11. I have carefully considered the appellant’s arguments regarding whether he agreed to a longer period to determine the applications and based on all the information before me, which includes other emails, I am satisfied that such an agreement was entered into by both parties. Moreover, I have not been provided with any substantive evidence that an email cannot be considered ‘in writing’ for the purposes of agreeing the longer period. Furthermore, there is no requirement under Article 7 of the GPDO that both parties have to agree the longer period independently, only that there is an agreement ‘by the applicant and the authority in writing’, and the email from the appellant’s agent is that written agreement. Consequently, permission was not deemed to have been granted.”
“5. The email from the agent to the Council follows an email from the applicant which confirms that he had spoken to officers regarding the need for a further meeting to discuss matters at the sites and that an email is expedited ‘allowing the decision to be extended’. I do not find the phrase, ‘would be willing’ ambiguous as it is clear that the agent is following his client’s instruction and confirms the acceptance of a longer period to determine the applications. Moreover, the email concludes by stating that if further extensions are required to resolve matters, ‘I would be happy to agree these with you in advance’. 6. Furthermore, the email from the Council does not state that the agreement to the extension to the determination date is rejected, rather that it expresses a concern that the matter relating to noise is unlikely to be overcome, which the author will discuss with his manager. In addition, I have not been provided with any substantive evidence that an email cannot be considered ‘in writing’ for the purposes of agreeing the longer period. Moreover, there is no requirement under Article 7 of the GPDO that both parties have to agree the longer period independently, only that there is an agreement ‘by the applicant and the authority in writing’, and the email from the appellant’s agent is that written agreement.”
“if it consists of or includes— (a) the erection, construction, alteration or extension of any building, bridge, aqueduct, pier or dam; or (b) the formation, laying out or alteration of a means of access to any highway used by vehicular traffic, unless the prior approval of the appropriate authority to the detailed plans and specifications is first obtained”
“Development consisting of a change of use of a building and any land within its curtilage from a use falling within Class B1(a)(offices) of the Schedule to the Use Classes Order, to a use falling within Class C3 (dwellinghouses) of that Schedule”
“Development under Class O is permitted subject to the condition that before beginning the development, the developer must apply to the local planning authority for a determination as to whether the prior approval of the authority will be required as to— (a) transport and highways impacts of the development, (b) contamination risks on the site, (c) flooding risks on the site, (d) impacts of noise from commercial premises on the intended occupiers of the development, and (e) the provision of adequate natural light in all habitable rooms of the dwellinghouses, and the provisions of paragraph W (prior approval) apply in relation to that application.” use falling within Class C3 (dwellinghouses) of that Schedule”
“(1) The following provisions apply where under this Part a developer is required to make an application to a local planning authority for a determination as to whether the prior approval of the authority will be required. … (3) The local planning authority may refuse an application where, in the opinion of the authority— (a) the proposed development does not comply with, or (b) the developer has provided insufficient information to enable the authority to establish whether the proposed development complies with, any conditions, limitations or restrictions specified in this Part as being applicable to the development in question. … (9) The local planning authority may require the developer to submit such information as the authority may reasonably require in order to determine the application, which may include— (a) assessments of impacts or risks; (b) statements setting out how impacts or risks are to be mitigated; or (c) details of proposed building or other operations. … (11) The development must not begin before the occurrence of one of the following— (a) the receipt by the applicant from the local planning authority of a written notice of their determination that such prior approval is not required; (b) the receipt by the applicant from the local planning authority of a written notice giving their prior approval; or (c) the expiry of 56 days following the date on which the application under sub-paragraph (2) was received by the local planning authority without the authority notifying the applicant as to whether prior approval is given or refused. … (13) The local planning authority may grant prior approval unconditionally or subject to conditions reasonably related to the subject matter of the prior approval….”
“Where, in relation to development permitted by any Class in Schedule 2 which is expressed to be subject to prior approval, an application has been made to a local planning authority for such approval or a determination as to whether such approval is required, the decision in relation to the application must be made by the authority— (a) within the period specified in the relevant provision of Schedule 2, (b) where no period is specified, within a period of 8 weeks beginning with the day immediately following that on which the application is received by the authority, or (c) within such longer period as may be agreed by the applicant and the authority in writing.”
“Where the Secretary of State makes a call-in direction in relation to a prior approval application any deemed prior approval provision shall have no effect in relation to such an application.”
“In my judgment, the language of the GPDO 2015 does not require the Court to conclude that limb (c) is an alternative only to limb (b). The specification of a time period in Schedule 2 (such as 56 days) for a decision on whether prior approval is required, linked to a restriction on commencement of development, is not incompatible with the possibility of extending time under limb (c). Limb (b) lays down a finite period of 8 weeks for decision-making, but that is to be read together with, and subject to, any extension under limb (c). The language of limb (a) does not preclude an extension of time under limb (c) simply because the time period is specified in Schedule 2 rather than in Article 7. Nor is any such extension precluded because the time period is used to control when development may lawfully commence. A provision such as paragraph W in Part 3 of Schedule 2 is capable of being read together with Article 7. Permitted development rights granted under schedule 2 are expressly subject to other provisions of GPDO 2015 including Article 7 (Article 3(1)). I accept [counsel for the Secretary of State’s] submission that limb (a) refers to a period specified in Schedule 2 but (like limb (b)) that is subject to any extension agreed under limb (c), and the time period stated in, for example, paragraph W(11) must be read and understood accordingly.”
“Article 7 has been framed in a completely different way to the earlier legislation. It now deals comprehensively with all permitted development rights which are subject to one of the prior approval procedures and deals with the time periods in each of those cases, allowing for any such time period to be extended by agreement.”
“whether it suffices for limb (c) of Article 7 that, as the Secretary of State contends, an agreement to extend the time for determination be made verbally but then evidenced or recorded subsequently in writing from one party or whether, as the Claimant submits, it is necessary that the applicant and the LPA [i.e. local planning authority] must both agree to the extension in writing”
“It may be good practice for emails or correspondence to be sent by both the applicant and the authority to each other setting out their agreement to an extension of time, or for them both to sign a single document in which they express their agreement to an extension. But I do not think that limb (c) necessarily insists upon an agreement being expressed by both parties in writing. Here the only party who argues that the time period was not lawfully extended, the Claimant, agrees that there was a verbal agreement between the LPA’s planning officer and himself to extend time. I accept the Secretary of State’s submission that in the present case it is sufficient that a verbal agreement was made by both parties which was then appropriately evidenced in writing. For example, that written evidence may simply be an email from the applicant (the Claimant) sent to the LPA to confirm what had been discussed and agreed verbally. Where both parties accept that they agreed an extension of time, albeit verbally, I do not accept that that agreement would be ineffective for the purposes of Article 7 (and Schedule 2) unless, in that scenario, the LPA responded in writing to confirm the content of the email which they received from the applicant.”
“The court should always resist over complication of concepts that are basically simple. Planning decision-making is far from being a mechanical, or quasi-mathematical activity. It is essentially a flexible process, not rigid or formulaic.”
“An acceptance is a final and unqualified expression of assent to the terms of an offer. The objective test of agreement applies to an acceptance no less than to an offer. On this test, a mere acknowledgement of the receipt of an offer does not amount to an acceptance ….”