“In the premises therefore those sums fall to be repaid to the Claimant as being monies paid by mutual mistake i.e. on the basis that both parties wrongly believed that the monies were claimed and paid for work and material which were covered by the arrangement between the parties when they were not alternatively the Claimant paid in mistaken belief that the sums were properly payable and the Defendant accepted payment which should not have been made and/or as monies paid for no consideration i.e. monies paid for work and materials from which the Claimant derived no benefit as the said work and materials were not for sites owned by him and the retention of the same would amount to unjust enrichment of the Defendant.”
“71. Whilst I have no doubt that Mr Leslie did trust Mr Farrar at the time, I am also satisfied that another equally important reason for Mr Leslie not seeking a breakdown was that he was not concerned so long as Farrar Construction was not claiming actual build costs in excess of the budget figure. Mr Farrar's evidence is that he did not seek payment in excess of the budget costs. That is what he said in his email of 1 March 12. It is also what he said in his evidence. It is also consistent with the contemporaneous documents. … 72. In short, I am satisfied that so long as Mr Leslie was happy that Farrar Construction was standing by the budget figure, and the profits were good, he saw no need to require Farrar Construction to take the time and trouble to provide supporting back-up, especially since he would doubtless have needed to pay someone to audit the material anyway if he was to make any use of it. … 266. In relation to the completed developments, the position as I find it to be is as follows: (1) Before work began the parties had agreed a cost budget. (2) During the course of the works Farrar Construction submitted requests for interim payments, on the basis of round sums which were not supported by any interim valuation or otherwise broken down or substantiated. (3) Mr Leslie was willing to make the interim payments requested, on the basis of a combination of factors, namely that: (a) they were within the budget; (b) they appeared reasonable; (c) he assumed that the request could be justified by reference to build costs already incurred or to be incurred specifically in relation to the Framework Agreement development(s) in respect of which they were requested (d) he trusted Mr Farrar and Farrar Construction not to request monies which it intended to use other than to fund build costs in relation to the Framework Agreement development(s). (4) Although I am satisfied that Mr Leslie did not, in fact, give the matter any real thought at the time, nor was there any discussion let alone agreement to this effect, I am also satisfied that if he had known that his assumption was wrong, and that Farrar Construction intended to use some or all the monies for other purposes, such as to fund other non Framework Agreement developments, or to fund Farrar Construction's general expenditure, including general head office overheads or purchases of items of plant and machinery which were not intended only for use in relation to the Framework Agreement development(s) in respect of which the monies were requested, he would have challenged that. The end result would either have been that he would have refused to make payments insofar as they were intended for those other purposes or, alternatively, he would have made it clear that he would not make any further or final payment in excess of the initial agreed budget without being provided with sufficient details to satisfy himself that it could be justified on the basis of build costs for the relevant Framework Agreement development(s) alone. (5) So far as Mr Farrar as the controlling mind of Farrar Construction is concerned, I am also satisfied that initially he did not give the matter any thought, but that had he been asked he would have accepted that Farrar Construction was not entitled to request monies which it intended to use other than to fund build costs in relation to the Framework Agreement development(s), although I consider that if he had been asked the specific question he would probably have answered that he considered it legitimate to use some proportion of those monies to fund some proportion of its general expenditure. I am satisfied however that all that he did in reality was to ask for round sum payments on account on the basis of a belief that it was needed to put and keep Farrar Construction in sufficient funds to continue with the relevant development(s), without giving any thought to whether or not the monies would actually be used for that specific purpose. Later on, I am satisfied that he came to believe that the extent and depth of the relationship was such that he was effectively justified in using the monies for Farrar Construction's general business purposes, on the basis that it did not matter because he would always be able either to stick to the budget and still make a reasonable profit, or persuade Mr Leslie to make an increased contribution without having to produce full supporting details. (6) Once each development had been completed, and the value of the completed development agreed, Mr Farrar was able to tell Mr Leslie that Farrar Construction would stick to its budget and, on the basis that this would produce a reasonable profit for both Farrar Construction and Mr Leslie, Mr Leslie was perfectly happy to agree to this. I am satisfied that Mr Leslie had no interest in requiring Farrar Construction to produce a detailed build cost substantiation in those circumstances, not least because he was being told by Mr Farrar on at least one if not more occasions that it had actually exceeded the budget, so that potentially going down that route would lead to Mr Leslie having to pay more. I am also satisfied that in such circumstances Mr Leslie had no reason to give the question as to what the funds had been used for any more thought than he had done when making the interim payments. He was quite happy in those circumstances for Farrar Construction to produce a simple invoice with no supporting details and, in relation to Dandy Mill Court, to agree the£50,000 extra payment on the basis that he was being told Farrar Construction had gone over budget and to record his appreciation for the hard work put in by Farrar Construction to deliver a successful outcome. (7) In relation to Cornlands the evidence from Farrar Construction is that£15,000 more than the budget costs was claimed, according to Mr Farrar's evidence under cross-examination to reflect the extra cost of constructing some garages, but there was no request for a detailed breakdown, I am satisfied because Mr Farrar had agreed to waive Farrar Construction's profit share on this development in any event. (8) Even in relation to Woodlesford, where Mr Leslie came to believe that Farrar Construction had wrongfully paid itself a profit share without first completing or notifying him that this was what it was doing, there was no challenge to the build costs, and although Mr Leslie complained vociferously about Mr Farrar having, as he perceived it, paying himself the profit on Woodlesford out of monies intended to fund Minsthorpe, there has been no challenge in these proceedings to the profit payment in relation to Woodlesford. 267. What then is the legal position in such circumstances? In my judgment the position is as follows: (1) At the time that he paid over the monies by way of interim payments Mr Leslie was operating under an assumption, which is that the monies were not intended for purposes other than to fund build costs specifically in relation to the Framework Agreement development(s) for which they were requested. He did not hold this as a conscious belief at the time he paid the monies, but it was nonetheless a belief in the sense that it was a tacit assumption, as described in Goff & Jones The Law of Unjust Enrichment (8th edition) at §9-35. (2) That assumption was incorrect, at least in relation to some of the interim payments, and particularly the later ones, because Farrar Construction did not positively intend to use those monies only for those specific purposes. However the extent to which Farrar Construction did intend to use these monies for those specific purposes, and the extent to which it did so, must have varied in relation to each specific request for payment in relation to each specific development, depending on Farrar Construction's circumstances at the time, which it is impossible to reconstruct. (3) I am satisfied that it could be said, therefore, that Mr Leslie could be said to have paid at least some of the interim payments whilst under a mistaken assumption. It is no longer necessary for Mr Leslie to have to show that it was a mistake of fact or any other mistake of a particular type: Goff & Jones §9-01. Nor, in my judgment, is it a mistake or a "misprediction" about the future, since the mistake was about the present intention which Farrar Construction had when it requested interim payments from Mr Leslie: Goff & Jones §9-08, referring to the distinction drawn by the Privy Council in Dextra Bank v Bank of Jamaica[2001] UKPC 50 , at [29], to which Mr Myerson and Mr Ryan drew my attention. (4) If the Framework Agreement had been operated as intended, at the end of the development Mr Leslie would clearly have been entitled to call for Farrar Construction to substantiate its build costs. If or to the extent that it failed to do so, either by relying on payments made in relation to other developments, or on build costs which were not on a true interpretation of the Framework Agreement recoverable, or otherwise, then I have no doubt that Mr Leslie would have been entitled, as a necessary incident of the Framework Agreement, to recover any overpayment, no doubt in practice by deduction from the profit share otherwise payable, or if necessary by action. However, the existence of a contractual remedy would not, of itself, preclude Mr Leslie from pursuing a coterminous remedy in unjust enrichment, where there would be no question of such remedy running in any way counter to the contractual allocation of risk: Goff & Jones §3-10 and following. (5) However in fact what happened was that instead of operating the Framework Agreement as had been intended, the parties were happy to reach an agreement where both were content to agree that the build costs equated to the budget cost. In that way, there was no need for Farrar Construction to provide substantiation, or for Mr Leslie to have to consider it, and no need for a potential debate or dispute as to whether the actual build costs were less than or greater than the budget cost, and the parties could happily divide the agreed profit on that basis to mutual satisfaction. The effect of that, in my judgment, is that Mr Leslie assumed the risk of error and entered into a settlement to close off the transaction. This prevents a claimant from succeeding in an unjust enrichment claim: see Goff & Jones §9-27 to 30, and the dicta in the decisions in Maskell v Horner[1914] 3 KB 106 , 118 and Woolwich v IRC[1993] AC 70 , 165 cited by Mr Myerson and Mr Ryan, and noted in Goff & Jones at §10-57. (6) A separate analysis, leading to the same result, is that there was no causative link between the mistake and the payment, because Mr Leslie chose to complete the development and divide the profit on the basis of the budget price on the basis of his conscious decision not to undertake the enquiry as to whether or not the actual build costs were less, and thus waived his right to enquire: see Goff & Jones §9-22 & 23, and Kelly v Solari (1841) 9 M&W 54 and Barclays Bank v Simms[1980] QB 677 , cited by Mr Myerson and Mr Ryan, and noted by Goff & Jones. (7) Alternatively, Farrar Construction would be entitled to rely upon the defence of estoppel, as to which Mr Myerson and Mr Ryan have referred me to Chitty on Contracts (31st edition) §29-182 and Avon County Council v Howlett[1983] 1 WLR 605 . Having reached a clear agreement with Mr Leslie in relation to the build costs and profit share, with a clear implicit representation by Mr Leslie that he would not require it to undertake the process of ascertaining and substantiating its actual build costs for that particular development, or to repay any element of the budget in excess of substantiated actual build costs, Farrar Construction has acted to its detriment by agreeing that settlement, in circumstances where it appears that it may have been able to assert higher build costs than the budget. I am also prepared to accept that in general terms Farrar Construction undoubtedly expended monies on recruiting staff and improving its office facilities and purchasing plant and equipment on the basis that its build costs and profit entitlement had been agreed and paid. In the circumstances it is not now open to Mr Leslie to claim unjust enrichment on the basis of mistake.”
“The safest rule however, is that if the party makes the payment with full knowledge of the facts, although under ignorance of the law, there being no fraud on the other side, he cannot recover it back again. There may also be cases in which, although he might by investigation learn the state of facts more accurately, he declines to do so, and chooses to pay the money notwithstanding; in that case there can be no doubt that he is equally bound.”
“I entirely agree in the opinion just pronounced by my Lord Chief Baron, that there ought to be a new trial. I think that where money is paid to another under the influence of a mistake, that is, upon the supposition that a specific fact is true, which would entitle the other to the money, but which fact is untrue, and the money would not have been paid if it had been known to the payer that the fact was untrue, an action will lie to recover it back, and it is against conscience to retain it; though a demand may be necessary in those cases in which the party receiving may have been ignorant of the mistake. ... If, indeed, the money is intentionally paid, without reference to the truth or falsehood of the fact, the plaintiff meaning to waive all inquiry into it, and that the person receiving shall have the money at all events, whether the fact be true or false, the latter is certainly entitled to retain it; but if it is paid under the impression of the truth of a fact which is untrue, it may, generally speaking, be recovered back, however careless the party paying may have been, in omitting to use due diligence to inquire into the fact. In such a case the receiver was not entitled to it, nor intended to have it.”
“(3) Where a sum has been paid which is not due, but it has not been paid under a mistake of fact or under compulsion as explained under (2) above, it is generally not recoverable. Such a payment has often been called a voluntary payment. In particular, a payment is regarded as a voluntary payment and so as irrecoverable in the following circumstances. (a) The money has been paid under a mistake of law: see (1) above. See e.g., Slater v. Burnley Corporation, 59 L.T. 636 and National Pari-Mutuel Association Ltd. v. The King, 47 T.L.R. 110. (b) The payer has the opportunity of contesting his liability in proceedings, but instead gives way and pays: see e.g., Henderson v. Folkestone Waterworks Co. (1885) 1 T.L.R. 329, and Sargood Brothers v. The Commonwealth, 11 C.L.R. 258, especially at p. 301, per Isaacs J. So where money has been paid under pressure of actual or threatened legal proceedings for its recovery, the payer cannot say that for that reason the money has been paid under compulsion and is therefore recoverable by him. If he chooses to give way and pay, rather than obtain the decision of the court on the question whether the money is due, his payment is regarded as voluntary and so is not recoverable: see e.g., William Whiteley Ltd. v. The King, 101 L.T. 741. (c) The money has otherwise been paid in such circumstances that the payment was made to close the transaction. Such would obviously be so in the case of a binding compromise; but even where there is no consideration for the payment, it may have been made to close the transaction and so be irrecoverable. Such a payment has been treated as a gift: see Maskell v. Horner [1915] 3 K.B. 106, 118, per Lord Reading C.J.” (a) The money has been paid under a mistake of law: see (1) above. See e.g., Slater v. Burnley Corporation, 59 L.T. 636 and National Pari-Mutuel Association Ltd. v. The King, 47 T.L.R. 110. (b) The payer has the opportunity of contesting his liability in proceedings, but instead gives way and pays: see e.g., Henderson v. Folkestone Waterworks Co. (1885) 1 T.L.R. 329, and Sargood Brothers v. The Commonwealth, 11 C.L.R. 258, especially at p. 301, per Isaacs J. So where money has been paid under pressure of actual or threatened legal proceedings for its recovery, the payer cannot say that for that reason the money has been paid under compulsion and is therefore recoverable by him. If he chooses to give way and pay, rather than obtain the decision of the court on the question whether the money is due, his payment is regarded as voluntary and so is not recoverable: see e.g., William Whiteley Ltd. v. The King, 101 L.T. 741. (c) The money has otherwise been paid in such circumstances that the payment was made to close the transaction. Such would obviously be so in the case of a binding compromise; but even where there is no consideration for the payment, it may have been made to close the transaction and so be irrecoverable. Such a payment has been treated as a gift: see Maskell v. Horner [1915] 3 K.B. 106, 118, per Lord Reading C.J.”
“Likewise, the circumstances in which a payment is made may show that the person who made the payment took the risk that, if the question was fully litigated, it might turn out that he did not owe the money. Payment under a compromise is an obvious example: see Brennan v Bolt Burdon[2005] QB 303 . I would not regard the fact that the person making the payment had doubts about his liability as conclusive of the question of whether he took the risk, particularly if the existence of these doubts was unknown to the receiving party. It would be strange if a party whose lawyer had raised a doubt on the question but who decided nevertheless that he had better pay should be in a worse position than a party who had no doubts because he had never taken any advice, particularly if the receiving party had no idea that there was any difference in the circumstances in which the two payments had been made. It would be more rational if the question of whether a party should be treated as having taken the risk depended upon the objective circumstances surrounding the payment as they could reasonably have been known to both parties, including of course the extent to which the law was known to be in doubt.”
“There may also be cases in which, although he might by investigation learn the state of facts more accurately, he declines to do so, and chooses to pay the money notwithstanding; in that case there can be no doubt that he is equally bound.”