“ . . . the construction of the civil works associated with the Black Rock hydro scheme as more comprehensively set out in Part 2 Works Information.”
“The key dates and conditions to be met are: . . . 3. Completion of pipeline testing24 November 2010 . . . 5. Completion of intake22 November 2010 .”
“Option X5 The completion date for each section of the works is section 1 2 3 description Completion of powerhouse, including installation of the overhead crane, sufficient to allow installation of the SSE switchgear. . . . Completion, including testing, of the intake, penstock pipeline and tailrace and the powerhouse (including building services) to allow Hydro Plant to be installed. Completion of all work not included in sections 1 and 2. completion date14 February 2011 27 May 2011 4 October 2011 Option X7 Delay damages for each section of the works are section 1 2 3 description Completion of powerhouse, including installation of the overhead crane, sufficient to allow installation of the SSE switchgear. . . . Completion, including testing, of the intake, penstock pipeline and tailrace and the powerhouse (including building services) to allow Hydro Plant to be installed. Completion of all work not included in sections 1 and 2. Amount per day£1,000.00 £2,544.00 £600.00 ” (Since the wording of Options X5 and X7 are for all material purposes identical, I shall not refer separately to Option X7 save where it is necessary to do so.) The completion date for each section of the works is section 1 2 3 description Completion of powerhouse, including installation of the overhead crane, sufficient to allow installation of the SSE switchgear. . . . Completion, including testing, of the intake, penstock pipeline and tailrace and the powerhouse (including building services) to allow Hydro Plant to be installed. Completion of all work not included in sections 1 and 2. completion date14 February 2011 27 May 2011 4 October 2011 Delay damages for each section of the works are section 1 2 3 description Completion of powerhouse, including installation of the overhead crane, sufficient to allow installation of the SSE switchgear. . . . Completion, including testing, of the intake, penstock pipeline and tailrace and the powerhouse (including building services) to allow Hydro Plant to be installed. Completion of all work not included in sections 1 and 2. Amount per day£1,000.00 £2,544.00 £600.00 ”
“6.2 Completion . . . Section 2 Completion, including testing, of the intakes, penstock pipelines and tailrace, and the powerhouse (including building services) to be completed to allow the hydro plant to be tested and commissioned. Completion of section 2 is defined as completion of the following items of the works: all of the intakes and associated facilities; all of the penstock pipelines and associated facilities, except for surface reinstatement; all of the tailrace; . . . ”