“3. The claim relates to works carried out by DCL at IIL’s unit at Delves Lane Industrial Estate, Consett, County Durham. The Project (as defined in Annexe A) consisted of the construction of Phase 1 of a camera factory. 4. IIL is a Company based in the British Virgin Isles. Mr Medhesh Al-Suhaim is its Managing Director. 5. A total of 7 contractors were employed for the project each of whom [was] on site for a different specified time. The works were carried out in sequence such that there was only one contractor on site at the time. 6. DCL were specialist roofing and cladding constructors. They were the third (or perhaps the fourth) contractor on site and were followed by a number of others including the contractor who fitted the windows. 7. In early 2008 Mr Al-Suhaim invited DCL to quote for roofing and cladding works at a proposed factory in Consett designed by Mammut Building Systems in Dubai. At the time Mr Al-Suhaim was advised by Solicitors Swinburn Maddison and engineers Peter Eaton Associates (Alan Wagstaff). 8. DCL’s revised quotation of£61,225 was submitted to the Claimant’s engineer, Alan Wagstaff, and subsequently accepted by Mr Al-Suhaim. The parties negotiated a formal contract.”
“The Client appoints the Contractor to act as Roofing and Cladding Contractor in relation to the Project to perform the services set out in Schedule 1 (‘the Services’) and on the terms and conditions set out in this Agreement and the Contractor agrees to perform the Services exercising reasonable skill and carefully and faithfully in the best interests of the Client. Where in the performance of the Services, the Contractor seeks or is obliged to seek the Client’s approval or agreement to any matter or thing, the giving or confirming of the same by the Client shall not in any way derogate from the Contractor’s obligations hereunder.”
“1.1 Assume the role of Principle (sic) Contractor for the period during which the Services are provided 1.2 Erection of fall arrest netting 1.3 Erection of roof edge protection scaffold 1.4 Erection of access tower at one corner of the building 1.5 Supply and fixing of double skin trapezoidal roof sheeting including insulation 1.6 Supply and fix microrib composite panels to the walls. Fixed horizontal 1.7 Supply and fix trimline gutters and down corner pipe 1.8 Contractor will be responsible for ensuring that the building passes its air pressure test and correcting any defects relating to the cladding at no cost to the client. 1.9 Remove all scaffolding and clear all rubbish and surplus material from site. 1.10 Contractor to be responsible for the security of his materials and equipment on site.”
“1.6. The Contractor shall at all times keep the Client fully and properly informed on all aspects of the progress and performance of the Services and shall further provide the Client with all such other information in connection with the Project as the Client may reasonably require. The contractor will meet with the Client to report on the Services at least fortnightly, but with Project meetings monthly and in addition as and when the Client or the Project CDM Co-ordinator shall reasonably require. 1.7. The Contractor shall use reasonable professional skill care and diligence to inspect the Works in accordance with the requirements of Schedule 1.”
“17.4 No action or proceedings under or in respect of this Agreement shall be brought against the Contractor after: (a) the expiry of 1 year from the date of Practical Completion of the Services or; (b) where such date does not occur, the expiry of 1 year from the date the Contractor last performed Services in relation to the Project.”
“15. DCL carried out the work on site between November and December 2008. On8th January 2009 Mr Wagstaff visited the site and took the opportunity to carry out a visual inspection of the low level cladding. He sent DCL an e-mail in which he expressed the view that the workmanship was of poor quality and that little care had been taken with the fitting of the panels generally. He expressed the view that problems would occur with the pressure test. He identified 5 separate areas of defects and stated that when the obvious faults have been corrected he would carry out a full inspection including the high level gutters. 16. On9 February 2009 Mr Beal (DCL’s quantity surveyor) sent e-mails to Mr Wagstaff and Mr Al-Suhaim in which he asserted that the building was complete and had been accepted by Mr Wagstaff. 17. On27th March 2009 Mr Al-Suhaim sent an e-mail which referred to “a few technical issues … mainly by loud noise caused by vibration of the cladding panels” 18. On5th May 2009 Swinburne Maddison, the solicitors then acting for IIL wrote to DCL. Much of the letter deals with the moneys allegedly due to DCL. At that time some£47,315.50 had been paid and DCL were claiming the moneys outstanding. However the letter also makes a vague reference to “various snagging items that need to be resolved” without going into detail. Swinburne Maddison asked DCL to deal with the snagging items to an acceptable standard within two weeks. 19. DCL replied to this letter on19th June 2009 . Much of the letter deals with the amounts allegedly due to DCL. However it also contains an assertion by DCL that all the work has been completed and that payment is due. 20. On27th July 2009 Swinburne Maddison wrote a further letter to DCL. The letter is headed “Without Prejudice”
“43. Mr Winser contends that DCL performed services in relation to the Project on31st March 2010 when it attended the meeting on site on that date. He referred me in particular to Item 8 in Schedule 1 (which defines the Services to be performed under the contract). It will be recalled under that item DCL were to be responsible for ensuring that the building passes its air pressure test and correcting any defects relating to the cladding. 44. Mr Winser points out that in order to correct defects in the cladding DCL must assess the extent of the defects. This will be done by an inspection. The inspection on31st March 2010 was such an inspection and was accordingly the performance of a service in relation to the project. Equally the report of15th April 2010 containing, as it did, an offer to return to site was also the performance of a service under the Contract.”
“45. …. I agree with Ms Franklin that the inspection on31st March 2010 and the subsequent offers have to be seen in the context that they occurred. In the course of her submissions Ms Franklin made a number of points: 1. The meeting took place as part of without prejudice negotiations following a pre-action protocol letter sent by TBI to DCL in October 2009. Ms Franklin referred me to paragraph 5 of the Pre-Action Protocol which expressly contemplates that parties to a Construction dispute should normally meet as part of the protocol. 2. She accepted that any privilege relating to the negotiations had been waived with the result that it was open to the parties to refer to the meeting and the subsequent offer. However she submitted the meeting remained a “without prejudice” meeting. Accordingly the meeting did not prejudice or create rights under the contract. In particular it did not create a new date for time to start running for limitation purposes. 3. She pointed out that DCL’s open position, as set out in the letter of26th February 2010 was an outright denial of liability. 4. She pointed out that the offer to carry out work contained in the report of15th April 2010 was rejected by Mr Al-Suhaim. If it had been accepted and further work had been carried out then no doubt there would have been a fresh limitation period in relation to that work. 46. To my mind these points are unanswerable. In my view the meeting and the subsequent offer were part of the without prejudice negotiations which were being conducted in accordance with the Pre-Action Protocol in an attempt to avoid litigation. They were not the performance of services under the Contract.”
“17.4 No action or proceedings under or in respect of this Agreement shall be brought against the Contractor after: (a) the expiry of 1 year from the date of Practical Completion of the Services or; (b) where such date does not occur, the expiry of 1 year from the date the Contractor last performed Services in relation to the Project.”
“where such date does not occur because time for occurrence is no longer expected to be achieved by the client ..”