“If either Party does not comply with the decision of the Adjudicator the other Party shall be entitled to take legal proceedings to seek compliance pending any final determination of the referred dispute or difference pursuant to clause 39A.7.1.”
“83 Such matters [the grounds upon which liability was disputed] might be germane if the contract conditions were other JCT or alternative institutional standard forms, where applications in respect of interim statement or payments, employ terminology such as “amounts due”
“90. Thus, in my view, clauses 30.3.3, 30.3.4 and 30.3.5 taken together impose an absolute imperative obligation on the Employer to pay the Contractor the amount stated in the Application for Interim Payment, in the absence of the written notices specified. 91. Those written notices have not been given by the Employer, thus I decide that the Employer shall pay to the contractor the amounts stated in Application Nos 4, 5 and 6 for Interim Payment.”
“If or to the extent that a contract does not contain such provision as is mentioned in subsection (1) and (2) [Requirements as to how the amount of an interim payment is to be calculated and when it is to be made], the relevant provisions of the Scheme of Construction Contracts apply.”
“(i) a decision of an adjudicator whose validity is challenged as to its factual or legal conclusions or as to procedural error remains a decision that is both enforceable and should be enforced; (ii) a decision that is erroneous, even if the error is disclosed by the reasons, will still not ordinarily be capable of being challenged and should, ordinarily, still be enforced; (iii) a decision may be challenged on the ground that the adjudicator was not empowered by the Act to make the decision, because there was no underlying construction contract between the parties or because he had gone outside his terms of reference; (iv) the adjudication is intended to be a speedy process in which mistakes will inevitably occur. Thus, the Court should guard against characterising a mistaken answer to an issue, which is within an adjudicator’s jurisdiction, as being an excess of jurisdiction; (v) an issue as to whether a construction contract ever came into existence, which is one challenging the jurisdiction of the adjudicator, so long as it is reasonably and clearly raised, must be determined by the Court on the balance of probabilities with, if necessary, oral and documentary evidence.”
“If he answered the right question in the wrong way, his decision will be binding. If he has answered the wrong question, his decision will be a nullity.”
“the Adjudicator’s conduct in considering Clause 30.3.5 of the JCT Form rather than Part II of the HGCRA Scheme was in excess of jurisdiction.”