“(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose “dispute” includes any difference. (2) The contract shall- (a) enable a party to give notice at any time of his intention to refer a dispute to adjudication; (b) provide a timetable with the object of securing the appointment of the adjudicator and referral to the dispute to him within 7 days of such notice; (c) require the adjudicator to reach a decision within 28 days of referral or such longer period as is agreed by the parties after the dispute has been referred; (d) allow the adjudicator to extend the period of 28 days by up to 14 days, with the consent of the party by whom the dispute was referred; (e) impose a duty on the adjudicator to act impartially; and (f) enable the adjudicator to take the initiative in ascertaining the facts and the law. (3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement. The parties may agree to accept the decision of the adjudicator as finally determining the dispute. (4) The contract shall also provide that the adjudicator is not liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omissions is in bad faith, and that any employee or agent of the adjudicator is similarly protected from liability. (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply.”
“To enable a quick and interim, but enforceable, award to be made in advance of what is likely to be complex and expensive disputes.”
“The whole purpose of s.108 of the Act, which imports into construction contracts the right to refer disputes to adjudication, is that it provides a swift and effective means of resolution of disputes which is binding during the currency of the contract and until final determination by litigation or arbitration, s.108 (3). The provisions of s.109-111 are designed to enable the contractor to obtain payment of interim payments. Any dispute can be quickly resolved by the adjudicator and enforced through the courts. If he is wrong, the matter can be corrected in subsequent litigation or arbitration.”
“If he answered the right question in the wrong way his decision will be binding. If he has answered the wrong question, his decision will be a nullity.”
“Subject to the proviso to clause 38B.1, the decision of the adjudicator is binding until the dispute is finally determined by arbitration or agreement; and the parties do not agree to accept the decision of the adjudicator as finally determining the dispute.”
“Provided always, that where any dispute, difference or question has been referred to an adjudicator under Clause 38A and the adjudicator has issued his decision thereon, a Party shall not be entitled to refer such dispute, difference or question to arbitration, and the adjudicator’s decision thereon shall become unchallengeable, unless that Party serves the above notice within 42 days of receipt of notification of the adjudicators decision; and, for the avoidance of doubt, this proviso shall apply whether or not the adjudicator has notified his decision within the time limit specified in Clause 38A.5.”
“The Contractor and the Sub-contractor shall comply forthwith with any decision of the adjudicator; and shall submit to summary judgment/decree and enforcement in respect of all such decisions.”
“If it did, then (subject to a further argument about pay-when-paid clauses) the withholding was lawful and the Claimant’s case fails. If it did not comply, the Respondent was not entitled to withhold the payment and the Claimant’s case succeeds.”
“The necessary implication of the award which was a competent award within the Adjudicator’s jurisdiction and arose out of the terms of the reference is that the Claimant was entitled to suspend the works and that the purported determination based on wrongful suspension has no contractual effect.”
“If the contractor shall determine the Sub-Contract for any reason mentioned in clause 29.6 the following provisions shall apply: 1. All sums of money that may then be due or accruing due from the Contractor to the Sub-Contractor shall cease to be due or accrue due;”
“Until after completion of the Sub-Contract Works and the making good of defects as referred to in clause 14.3 the contractor shall not be bound by any provisions of the sub-contract to make any further payment to the sub-contractor.”
“(1) The decision of an adjudicator that money must be paid gives rise to a second contractual obligation on the paying party to comply with that decision within the stipulated period. This obligation will usually preclude the paying party from making withholdings, deductions, set-offs or cross-claims against that sum. (2) For a withholding to be made against an adjudicator’s decision, an effective notice to withhold payment must usually have been given prior to the adjudication notice being given, or possibly the decision being given, and which was ruled upon and made part of the subject matter of that decision. (3) However, where other contractual terms clearly have the effect of superseding, or provide for an entitlement to avoid or deduct from, a payment directed to be paid by an adjudicator’s decision, those terms will prevail. (4) Equally where a paying party is given an entitlement to deduct from or cross-claim against the sum directed to be paid as a result of the same, or another, adjudication decision, the first decision will not be enforced or, alternatively, judgment will be stayed.”
“Other rights under the contract which were not the subject of the decision remain available to the relevant party. If, therefore, by the time an adjudicator makes a decision requiring payment by a party to the contract, the contract has been lawfully terminated by that party (or that party has real prospects of success in supporting that termination) or some other event has occurred which under the contract entitles a party not to pay, then the amount required to be paid by the decision does not have to be paid.”
“It is open to the respondents (employment paying party) to set-off against the adjudicator’s decision any other claim they have against the appellants (contractor receiving party) which had not been determined by the adjudicator. The adjudicator’s decision cannot be re-litigated in other proceedings but, on the wording of this sub-contract, can be made the subject of set-off and counter-claim.”