"To commence the development of the land hereby transferred in accordance with the planning permission issued by Mole Valley District Council, reference MO/80/1214 and dated 11th December, 1980, within six months from the date hereof and thereafter to diligently pursue the development of the land hereby transferred to its completion complying with the said planning permission"
"Damages for a breach of contract committed by the defendant are a compensation to the plaintiff for the damage, loss or injury he has suffered through that breach"
"The fundamental basis is thus compensation for pecuniary loss naturally flowing from the breach"
"The general principle for the assessment of damages is compensatory"
"If, for social and economic reasons, the court does not see fit in the exercise of its discretion, to order demolition of the 14 houses, is it just that the plaintiffs should receive no compensation and that the defendants should be left in undisturbed possession of the fruits of their wrongdoing?"
"Damages for loss of bargaining power can be awarded if, but only if, the party in breach could have been restrained by injunction from committing the breach of contract or compelled by specific performance to perform the contract. Where no such possibility existed there was no bargaining power in reality and no right to damages for loss of it. Hence damages for loss of bargaining power cannot be awarded where there is for example a contract for the sale of goods or generally a contract of employment"
"If, for social and economic reasons, the court does not see fit in the exercise of its discretion, to order demolition of the 14 houses, is it just that the plaintiffs should receive no compensation and that the defendants should be left in undisturbed possession of the fruits of their wrongdoing?"