“There are a number of different types of conduit taking the water from the water intakes to the reservoir (or to watercourses which feed naturally into it by gravity). There are 4km of single or double buried pipes (mainly single or 25 double glass-reinforced plastic pipes, but some pre-fabricated in concrete); there are 6km of drilled and blasted underground conduit, lined with shotcrete; there is 1km of “cut and cover” concrete conduit (built on-site with reinforced concrete in a large trench which was then backfilled) and there are 800m of uncovered channels lined with rocks and/or concrete set into the ground surface. From the 30 photographs in the bundles, it is apparent that the pipes range in size from approximately 400mm to 2 metres in diameter. The underground conduit and the cut and cover concrete conduit into which it feeds have an internal diameter of between 2 and 3 metres (the concrete conduit having a flat base, vertical walls up to about 1.5 metres and a semi-circular “roof”). They are involved in 35 bringing the water collected from the water intakes in the adjacent catchment area into the catchment area of the main reservoir.”
“(but any reference in list C in subsection (4) of that section to “plant” does not include anything where expenditure on its provision is excluded by this 15 section).”
“Item 1 in List B comprises “a tunnel, bridge, viaduct, aqueduct, embankment or 10 cutting.”
“…I still consider that one essential, though not necessarily primary, purpose of 30 a tunnel is to facilitate access from one end to the other, either of persons or of means of transport. I therefore do not consider this conduit to comprise a tunnel within the ordinary meaning of that word or, therefore, for the purposes of Item 1 in List B; although it is of course large enough to allow a person to enter it (as was clearly done during the work of excavation) and pass from one end to the 35 other, that was not its intended purpose.”
“…its function is far more complex than simply transporting water from one place to another; it is designed to deliver the required 18.6 cubic metres per second of water at a pressure of 60 atmospheres to the turbine without allowing it to escape and dissipate or cause catastrophic damage to the power cavern and 15 the equipment in it.”
“We often say that we are looking for the intention of Parliament, that is not 5 quite accurate. We are seeking the meaning of the words which Parliament used.”
“The expression “floors” in this context and in the light of the word 10 “obstruction”, which means “blocking or being blocked, making or becoming more or less impassable”, is, in my view, limited to those parts of the factory floor on which workmen are intended or likely to pass and re-pass. Where a part of the factory floor is used for storing, as in this case, and properly use for storing, it seems to me that the articles which are stored there… are not 15 obstructions on the floor within the meaning of s 28 (1) of the Act of 1961.”
“… “installed” is not a word of art nor a word of precision. Indefiniteness 25 gives it, as it gives any word, a chameleon-like character so that associate words show through and give their colour and meaning to it… The word “install”, which in mediaeval times meant to perform a formal ceremony of induction to a position or office, has been taken in modern times for use in the mechanical and structural trades. There it means more than to bring 30 in or merely to place an article somewhere for service…. In those trades, the word is used in respect of a system of ventilation, lighting, plumbing, heating water or electrical service, or a fireplace, etc, to be put into a building, or of an engine, steering gear or carburettor into a motorcar; or other similar use… “Install” would seem to connote the doing of 35 something of some complexity, difficulty in importance, probably requiring some skill, involving the integration of an article or articles into the building or machine in which the installing takes place, and causing a change of some importance in the building or machine.”
“It conveys putting in place something already made so that it can be used. There may be an element of assembly required; but basically everything installed is ready to work when it is put in its place and, if necessary, connected up. Here I think it would be a complete misdescription to say that the boiler is installed in the framework or in this 35 building. It is the other way round: the framework is there to hold and cover the boiler. They form one unit which is a thermal power station. There is not one thing installed in another: the boiler has no previous existence… What is done… is the construction – and I use the word deliberately – on the spot out of manufactured elements … Installation seems to me to be very far from the reality of the facts.. I think it is truly 40 construction.”
“So the question is whether, if the dock is plant, the cost of making room for it is expenditure on the provision of the plant for the purposes of the trade of the dock 20 owner. In my view this can include more than the cost of the plant itself because plant cannot be said to have been provided for the purposes of the trade until it is installed: until then it is of no use for the purposes of the trade. This plant, the dock, could not even be made until the necessary excavating had been done. All the commissioners say in refusing this part of the claim is that this expenditure 25 was too remote from the provision of the dry dock. There, I think, they misdirected themselves. If the cost of the provision of plant can include more than the cost of the plant itself, I do not see how expenditure which must be incurred before the plant can be provided, can be too remote.”