“(a) that the scheme of development underlying the acquisition had been cancelled on the launch date, (b) that no action has been taken (including acquisition of any land, and any development or works) by the acquiring authority wholly or mainly for the purposes of the scheme, (c) that there is no prospect of the same scheme, or any other project to meet the same or substantially the same need, being carried out in the exercise of a statutory function or by the exercise of compulsory purchase powers …”
“Opportunity areas are the capital’s major reservoir of brownfield land with significant capacity to accommodate new housing, commercial and other development linked to existing or potential improvements to public transport accessibility.”
“a new strategic public transport infrastructure hub at Old Oak Common on the HS2 line between London and Birmingham and beyond with an interchange with Crossrail, other national main lines and the London Overground. This should include a new branch of Crossrail 1 … Public transport accessibility and availability of amenity space should support high density development which could include a cluster of tall buildings around the interchange. Wormwood Scrubs would provide a major amenity to support this scale of development and improved access to the Scrubs is essential to deliver sustainable residential communities.”
“a. avoiding significant adverse noise effects on health and quality of life as a result of new development; b. mitigating and minimising existing and potential impacts of noise on, from, within, as a result of, or in the vicinity of new development without placing unreasonable restrictions on development or adding unduly to the costs and administrative burdens on existing businesses; … d. separating new noise sensitive development from major noise sources (such as road, rail, air transport and some types of industrial development) through the use of distance, screening or internal layout – in preference to sole reliance on sound insulation; e. where it is not possible to achieve separation of noise sensitive development and noise sources, without undue impact on other sustainable development objectives, then any potential adverse effects should be controlled and mitigated through the application of good acoustic design principles; …”
“a) apply the “agent of change” principles to attenuation of noise and vibration; b) submit a noise and vibration assessment to … i) demonstrate compliance with relevant and current building standards; and ii) identify unacceptable impacts and secure the appropriate delivery of mitigation measures; c) appropriately reduce exposure to existing noise generators such as waste sites…whilst ensuring the continued effective operation of those uses …” b) submit a noise and vibration assessment to … i) demonstrate compliance with relevant and current building standards; and ii) identify unacceptable impacts and secure the appropriate delivery of mitigation measures; c) appropriately reduce exposure to existing noise generators such as waste sites…whilst ensuring the continued effective operation of those uses …”
“However, it is also recognised that these guideline values are not achievable in all circumstances where development might be desirable. In higher noise areas… a compromise between elevated noise levels and other factors, such as the convenience of living in these locations or making efficient use of land resources to ensure development needs can be met, might be warranted. In such a situation, development should be designed to achieve the lowest practicable.”
“Tall and large buildings should: a generally be limited to sites in the Central Activity Zone, opportunity areas, areas of intensification or town centres that have good access to public transport b only be considered in areas whose character would not be affected adversely by the scale, mass or bulk of a tall or large building c relate well to the form, proportion, composition, scale and character of surrounding buildings, urban grain and public realm (including landscape features), particularly at street level d individually or as a group, improve the legibility of an area, by emphasising a point of civic or visual significance where appropriate, and enhance the skyline and image of London e incorporate the highest standards of architecture and materials, including sustainable design and construction practices f have ground floor activities that provide a positive relationship to the surrounding streets g contribute to improving the permeability of the site and wider area, where possible h incorporate publicly accessible areas on the upper floors, where appropriate i make a significant contribution to local regeneration.” f have ground floor activities that provide a positive relationship to the surrounding streets g contribute to improving the permeability of the site and wider area, where possible h incorporate publicly accessible areas on the upper floors, where appropriate
“i) tall buildings around North Acton Station, Old Oak Common Lane Station and key destinations along Old Oak High Street major town centre, North Acton neighbourhood town centre and other key routes that do not result in an overwhelming wall of development; iii) increased heights and massing adjacent to the A40 and railway lines to mitigate impacts on the public realm and residential amenity; and iv) generally lower heights adjacent to sensitive locations including existing residential neighbourhoods at Wells House Road and Midland Terrace…”