“we would play tunes on the contract price banding with both Cemex and Trackwork Moll, to try and get the best possible rate for Network Rail.”
“Please note a physical stock count was undertaken in 2020 showing a further ~100,000 sleepers. However, these stock counts are known to be inaccurate due to the nature of the activity.”
“4.51 NR's demand for concrete sleepers in the current 2024/2025 year is at a historically low level of demand which is due to a combination of factors: 4.51.1 High volumes of concrete sleepers being replaced between 2002 and 2018. 4.51.2 Modern sleepers, which are part of an improved overall track system, lasting longer than their predecessors. 4.51.3 NR ceasing to use Track Renewal Trains as a means of delivering high volumes of “strategic” track renewals. 4.51.4 Improved track condition data being routinely provided to local track engineers, enabling more precise specification of smaller scale “tactical” track renewals. 4.51.5 Within the track engineering discipline, rerailing, re-ballasting and certain switch and crossing renewals all being accorded a higher priority than the replacement of concrete sleepers. 4.51.6 A reduced spend on track renewals overall, due to an urgent need to increase the spend on other assets, at a time when the overall funding settlement is relatively constrained.”
“4.47 … in a No Scheme World, stockpiling would not have been required and would not have happened, because NR could have taken actions to maintain supply from the Washwood Heath factory. 4.48 Such a continuation of supply would have been achieved by the award of two contracts. Firstly, a short-term contract lasting only a few months from the end of the extended 2012 Contract until a new medium-term contract was in place. Secondly, just as in reality, NR would have prepared and issued an Invitation to Tender, ("ITT") in 2019, which would have sought offers for supply for a medium- term contract. This second contract would have commenced no earlier than April 2020 and most likely from June 2020 for a likely term of up to 8 years in duration via either a 4 year contract with the option to extend for an additional 4 years on a 1+1+1+1 basis or via a 5 year contract with the option to extend for an additional 3 years on a 1+1+1 basis. The ITT would have described NR’s supply requirements, in the same way as the P3 contract described in the Scheme World. 4.49 Given the availability and capabilities of the WWH factory and its workforce, it is a reasonable conclusion that Cemex would have bid for and been awarded both the short term contract and the subsequent medium-term contract. As a result, there should have been no gap in supply.”
“Network Rail shall purchase a minimum of 250,000 sleepers per annum”
“The decision as to which supplier to purchase sleepers from under their respective contracts was largely driven by volume constraints of supply from the respective suppliers. TWM could supply a maximum of up to around 380,000 to 400,000 G44 or EG47 sleepers per year. The other specialised sleepers plus the balance of G44 and EG47 sleeper demand was produced by CMX. The average requirement for NR each year was approximately 700,000 to 900,000, declining later in the period, and with the balance of what could not be produced by TWM met by the stockpile.”
“This assumes that HS2 does not serve a CPO order on Cemex to vacate [its] existing site at Washwood Heath and Cemex can continue to manufacture and supply sleepers to Network Rail from it.”
“just as in reality, NR would have prepared and issued an Invitation to Tender, ("ITT") in 2019 … The ITT would have described NR’s supply requirements, in the same way as the P3 contract described in the Scheme World.”