“Land which is identified for the purposes of relevant public functions by a development plan document for the area in which the land is situated …”
“(c) a development plan document which has been submitted to the Secretary of State for independent examination under section 20(1) of the [Planning and Compulsory Purchase Act 2004 (“the 2004 Act”)]; (d) a revision of a development plan document in pursuance ofsection 26 of the 2004 Act if the document has been submitted to the Secretary of State for independent examination under section 20(1) of that Act.”
“(b) the development plan documents (taken as a whole) which have been adopted or approved in relation to that area.”
“A development plan document is a local development document which is specified as a development plan document in the local development scheme.”
“The local planning authority’s local development documents must (taken as a whole) set out the authority’s policies (however expressed) relating to the development and use of land in their area.”
“(za)1 which descriptions of documents are, or if prepared are, to be prepared as local development documents; (a) which descriptions of local development documents are development plan documents…”
“The production of an IDP is an essential part of the evidence base in developing and delivering a sound Local Plan.”
“the IDP adopts a categorisation for each infrastructure item, to reflect its importance to the delivery of the Local Plan in terms of the level of risk it poses to the Local Plan.”
“The critical piece of infrastructure for the overall strategy is the improvements to the A5 … it is the A5 which is central to delivering the overall strategy of the plan. The delivery of the A5 is critical because as stated in AD47 (A5 Dualling Summary Note) there is a limit of 800 dwellings which can be completed within the A5 corridor without substantial improvements to the strategic road. As you will recall the reason for the delay between your letter of October 2019 and our reply of February 2020 was due to awaiting the outcome of the HIF bid. This bid was for the completion of Phases 1 and 2 of the improvements to the A5. The funding of this scheme now lies with MHCLG who have committed funds of£79.5m to ensure that improvements as outlined in the HIF bid are carried out with further improvements to the A5 being part of RIS 3. This is great news and indicates the Government’s commitment to ensuring that the A5 is improved and to ensure the delivery of housing along the corridor. We are working with Homes England, Highways England, Warwickshire County Council, Department of Transport and MHCLG on [a] detailed project delivery time line. It will be between 2024 and 2026. We are looking to agree a position statement/statement of common ground to show the commitment to the delivery of the A5 improvements, this will then inform the actual stepped trajectory to be applied to the Plan.”
“While no detailed design work appears [to] have been published and the Draft Local Plan is still under examination by the inspector appointed by the Secretary of State, the necessary access and infrastructure works are expected to have significant implications for the Green Acres site.”