“The settlement involved the parties entering into a 25 year option agreement which provides that the Acquiring Authority will, if required as a result of the scheme design, and provided that there is no adverse impact on the tunnels, grant rights for the Claimant to insert piles into the acquired sub- soil.”
“4. Costs (A1) In any proceedings on a question referred to the Upper Tribunal under section 1 of this Act – (a) the following subsections apply in addition tosection 29 of the Tribunals, Courts and Enforcement Act 2007 (costs or expenses) and provisions in Tribunal Procedure Rules relating to costs; and (b) to the extent that the following subsections conflict with that section or those provisions, that section or those provisions do not apply (1) Where either – (a) the acquiring authority have made an unconditional offer in writing of any sum as compensation to any claimant and the sum awarded by the Upper Tribunal to that claimant does not exceed the sum offered; or (b) the Upper Tribunal is satisfied that a claimant has failed to deliver to the acquiring authority, in time to enable them to make a proper offer, a notice in writing of the amount claimed by him, containing the particulars mentioned in subsection (2) of this section; the Upper Tribunal shall, unless for special reasons it thinks proper not to do so, order the claimant to bear his own costs and to pay the costs of the acquiring authority so far as they were incurred after the offer was made or, as the case may be, after the time when in the opinion of the Upper Tribunal the notice should have been delivered. (2) The notice mentioned in subsection (1) of this section must state the exact nature of the interest in respect of which compensation is claimed, and give details of the compensation claimed, distinguishing the amounts under separate heads and showing how the amount claimed under each head is calculated.”
“This, together with the length of option period requested by the Claimant, goes to demonstrate that submitting a claim for circa£18m and referring it to the Tribunal when it did was premature and ill-conceived and therefore a total waste of time and money. All that was needed was a discussion between engineers. Crossrail has always been open to such discussions. Similar negotiations have been successfully concluded with other landowners across London without any need for a reference to the Tribunal.”
“On the basis of LCC v Tobin the claimant ought to receive, as part of its compensation, any costs that it reasonably incurred before the date of the reference in preparing its claim for compensation, since those costs represent part of what it has lost through compulsory acquisition of its land. Costs incurred after the date of reference are governed by s 4 of the 1961 Act; and, under subs (1), where a claimant has failed to deliver a claim in time to enable the acquiring authority to make a proper offer, the claimant must, in the absence of special reasons, bear its own costs and pay those of the acquiring authority. This provision relates specifically to the costs of proceedings before the Lands Tribunal. The purpose is to ensure that the acquiring authority is not liable for the claimant’s costs, and gets its own costs, up to the time when it could have made a proper offer. There is clearly an underlying policy purpose in ensuring that the acquiring authority is in a position to make an offer before it incurs, or becomes liable for, any costs in the proceedings. As far as pre-reference costs are concerned, however, provided that they were reasonably incurred in preparing the claim, it does not seem to us that there is any reason for disallowing them, simply because no claim or no suitably quantified claim was submitted to the authority before the reference was made to the Lands Tribunal. The reasonableness of such costs is to be judged in relation to the need for them to have been incurred for the purpose of determining the compensation to which the claimant is entitled, and the policy purpose underlying s 4(1) has no application.”
“This provision relates specifically to the costs of proceedings before the Lands Tribunal. The purpose is to ensure that the acquiring authority is not liable for the claimant’s costs, and gets its own costs, up to the time when it could have made a proper offer.”
“All that was needed was a discussion between engineers. Crossrail has always been open to such discussions. Similar negotiations have been successfully concluded with other landowners across London without any need for a reference to the Tribunal.”