“Landscaping, footpaths, new access, roadway and four new buildings to provide National Cycling Activities Centre on Sustrans Route 43.”
“As a result of the laying of the water main, all of the buildings comprised within the original scheme have had to be moved by a distance of approximately 16 metres. This has resulted in a loss of developable area of 0.92 acres. Part of this area will however be incorporated into the car park and it may well be that our clients will be able to hard surface this area notwithstanding that the water main runs underneath this area. Clarification will be required from you on this point. On the basis that their land is worth something in the region of£60,000 to£65,000 per acre, we calculate that our clients’ loss lay in the region of£40,000 representing a loss of approximately two-thirds of an acre.”
“A. As regards disturbance this case has been protracted through no fault of my clients, it has involved them in considerable inconvenience and frustration and the figure claimed is considered to be fair and reasonable as a result. It is also in line with other settlements that had been agreed between my firm and Dwr Cymru’s agents and valuers. Disturbance needs to reflect occupation for two and a half years. B. As regards the residual damage, I accept that from the original Schedule of Condition it can be seen generally the area was in use as rough grazing land. It has to be remembered however that we are of the opinion that the reinstatement works undertaken by Dwr Cymru’s contractors is inadequate as evidenced by the flooding that has occurred. Whilst I understand that Dwr Cymru would be involved as third party claimants in the event of any claim ever being made by neighbours in respect of flooding, this nevertheless is a relatively nominal sum to reflect and recognise the problems that have been encountered. In addition, the access point from my client’s land to the highway is incomplete. C. I am firmly of the opinion that in the minds of any purchaser, the restriction as a result of the sterilisation of an area of land would impact on their thinking. A capital value per acre has been agreed in principle between the respective valuers and the amount being claimed represents 25% of that value which is in my opinion more than fair.”
“I understand from the correspondence and documents I have seen ... and in particular a note dated1 January 2003 that the claimant was not in physical occupation of the land, but was in fact renting it out for grazing for ‘£40 to£50 per month’. I have not seen anything in the documents I have to suggest that the tenant was in any way disturbed or refused to pay her rent. 4 The claimant did however clearly suffer some disturbance in as much that it spent time dealing with the compulsory acquisition. This, in my experience, means it would be entitled to make a claim for its reasonable time spent dealing with Dwr Cymru, their agent and solicitor and also monitoring the scheme and overseeing the reinstatement. They have not broken down their claim for£1,500 , and in my view, for a scheme of this size, I would not expect to get as much under the disturbance head of claim. I have to consider, however, that the land is owned by a limited company, and hence dealing with compulsory purchase (from a claimant’s point of view) is going to be more time consuming than dealing as an individual. Nonetheless, I would not expect to get more than£1,000 under this head of claim especially as they were not in physical occupation. There is also the question of flooding caused to the neighbouring property, although as I am not a drainage expert, I can only base my opinion on the evidence found by Dwr Cymru (unless the claimant can show evidence to the contrary) and hence I have not included anything in either the disturbance or depreciation figures for this. Clearly if there was evidence to prove to the contrary, an allowance would have to be made (preferably under the disturbance head of claim) for rectifying the problem if it were shown to exist.”
“Unfortunately the project is no longer considered viable, due to the more advanced development of a similar project at Afan Argoed near Port Talbot.”