“(i) A property will be roofed, glazed, plastered; exterior doors installed, floors and ceilings in place, although any of this work may not be fully completed. (ii) In the normal pattern of construction electrical wiring and plumbing work will be installed prior to plastering but final fittings not necessarily completed. (iii) Normally by the time a property has been plastered the electricity, mains water, gas supplies and drainage will be available but not necessarily connected.”
“Where a rating authority are of opinion – (a) that the erection of a building within their area has been completed; or (b) that the work remaining to be done on a building within their area is such that the erection of the building can reasonably be expected to be completed within three months, and that the building is, or when completed will be, comprised in a relevant hereditament, the authority may serve on the owner of the building a notice (hereafter in this paragraph referred to as ‘a completion notice’) stating that the erection of the building is to be treated for the purposes of this Schedule as completed on the date of service of the notice or on such later date as may be specified by the notice.”