“(1) Subject to and in accordance with the provisions of this part, it shall be the duty of [the Coal Authority] to take in respect of subsidence damage to any property remedial action of one or more of the kinds mentioned in subsection (2) below. (2) The kinds of remedial action referred to in subsection (1) above are – (a) the execution of remedial works in accordance with section 7 below; (b) the making of payment in accordance with sections 8 or 9 below in respect of the cost of remedial works executed by some other persons; (c) the making of a payment in accordance with section 10 or 11 below in respect of the depreciation in value of the damaged property.”
“(a) the works which the Authority consider to be remedial works in relation to the damage, that is to say, such works (including works of redecoration) as are necessary in order to make good the damage, so far as it is reasonably practicable to do so, to the reasonable satisfaction of the claimant and any other person interested; and (b) in the case of each item of those works, the amount of the cost which the Authority consider it would be reasonable for any person to incur in order to secure that the work is executed.”
“(1) In any case to which this section applies the Authority may elect to make a payment equal to the amount of the depreciation in the value of the damaged property caused by the damage (‘the depreciation 6 amount’) instead of executing any remedial works or making any payment in lieu. (2) This section applies to the following cases – (a) where the aggregate amount of the costs specified in the schedule of remedial works exceeds the depreciation amount by at least 20 per cent …”
“(3) Where in the case of any property affected by subsidence damage – (a) remedial works have been executed; but (b) there is a depreciation in the value of the property caused by any damage the making good of which to the reasonable satisfaction of the claimant and any other person interested was not reasonably practicable, The Authority shall make in respect of the property a payment equal to the amount of that depreciation.”
“2(1) For any purposes of section 10 or 11 of this Act, the value of the unit of property at any time shall be taken to be the amount which it might be expected to realise in the state in which it is at that time on a sale effected at that time. (2) In the case of property comprising land or buildings the sale referred to in sub-paragraph (1) above is the sale of the fee simple in the open market and with vacant possession … 3(1) For the purposes of section 10 or 11 of this Act the amount of the depreciation in the value of a unit of property caused by any subsidence damage shall be taken to be the amount by which the value of the property at the relevant time is less than what would have been its value at that time (determined in accordance with paragraph 2 above) if it had not been affected by the damage.”
“(1) Except as otherwise provided by or under this Act, any question arising under this Act shall, in default of agreement, be referred to and determined by the Lands Tribunal. 7 (2) Where in any proceedings under this Act the question arises whether any damage to property is subsidence damage, and it is shown that the nature of the damage and the circumstances are such as to indicate that the damage may be subsidence damage, the onus shall be on the Authority to show that the damage is not subsidence damage. (3) The tribunal, court or other person by whom any question is heard and determined under this Act may make such orders as may be necessary to give effect to its or his determinations and in particular may by order – (a) require the Authority to carry out any obligations imposed upon them by this Act within such period as the tribunal, court or person may direct; (b) award damages in respect of any failure of the Authority to carry out any such obligations.”
“The critical issue seems to me to be as to the scope of the Board’s duty. Is it as Mr Grime submits, only to execute remedial works, or as Peter Gibson LJ more precisely finds, a duty to execute remedial works, as soon as reasonably practicable after the occurrence of the subsidence damage (or perhaps, in the light of section 2, as soon as was reasonably practicable after receiving the damage notice)? Or is the Board’s duty, as I believe it to be, a duty either to repair, or, at their election, to pay compensation, the duty arising as soon after the receipt of the damage notice as is reasonably practicable for the Board to act? So to construe the duty does not deprive the Board of its specifically conferred right of election. My formulation acknowledges that right, but it also gives effect to the obligation to make the election within a reasonable time. If the Board elects to repair, it must repair; if it elects to make payment, it is then likewise required to make that payment. It cannot refuse to do the work and also refuse to pay compensation and then claim not to be amenable to the tribunal’s powers under section 13(3). I do not construe the words in section 13(3)(b) ‘any failure … to carry out any such obligations within a reasonable time’, as imposing a limited duty to repair within a reasonable time, for the breach of which damages are limited to any loss caused by delay. To me those words only define when the duty arises, not its scope. The scope of the duty is to be found in sections 1 and 2. A reasonable time is given for making the election and on taking that decision or on the expiration of the reasonable time, the Board comes under the duty to repair or, in the alternative, to pay. Thus, in my judgment, the tribunal are empowered to award damages for the loss caused by the subsidence. The Board is not confined to a loss caused by a delay in carrying out the repairs. Nor is it confined, as the Member held, to damages which are subsidiary to the primary remedy of remedial works.”
“In this case the question arises what order was necessary to give effect to the determination that the damage in dispute was subsidence damage. For the reasons which I have given it follows from that determination that if the Board had discharged its duty under the Act it would either have carried out the repairs by, say, Easter 1992 or it would have formed the opinion that the 13 reasonable cost of repairs would have exceeded the amount of the depreciation in the value of the property caused by the damage and exercised its option under section 1(4) to pay the amount of the depreciation. Thus by, say, Easter 1992 the claimants would have had their property repaired and the depreciation made good by the repairs or they would have received the amount of the depreciation and the depreciation would have been made good by payment. It would not have been necessary to sell the property and it seems clear on the findings of facts of the Lands Tribunal that the property would not have been sold. There is certainly no finding that it was unreasonable to sell the property in circumstances in which the Board had failed to discharge its statutory obligation. In these circumstances I am of the opinion that under section 13(3) of the Act the Lands Tribunal had jurisdiction to award damages in the amount of the depreciation because such an order was ‘necessary to give effect to its determination’ that the damage was caused by subsidence. By doing so it would have put the claimants in the same position in financial terms as if the Board had discharged its obligation under section 1 as it would no doubt have done if it had accepted that the damage was so caused from the outset. To my mind there is nothing in section 13(3) to limit the order which the Lands Tribunal can make in the way suggested by the Tribunal or the Board.”
“Brief description of damage (e.g. walls cracked, windows jammed, etc).”
“No evidence was seen of any disturbance of the ground between the rear scarp and the property”
“All the items have been treated as ‘Spot’ items as the full extent of the repair works are not clear or agreed at this stage. The pricing reflects the abnormal and commercial realities likely to be experienced in this type of scheme.”
“loss of one greenhouse and part of second greenhouse”, “loss of remaining greenhouses due to proposed re-grading of land”, and “loss of land”; in the case of number 45, “loss of garden land” and “loss of outbuilding through proposed re-grading of land”; and in the case of number 49, “loss of garden land” and “loss of outbuilding”
“The landslip is continuing and a slow progression of damage is occurring to No.69 New Station Road. We are unable to predict how much future movement will occur or the rate of progression. Having said this we think it most probable that No.69 New Station Road will eventually be damaged to the extent that demolition will be repaired [sc ‘required’], albeit that the dwelling is presently in a safe and general serviceable condition.”
“We suspect that in due course the dwelling will become unstable, or at the very least uneconomic to restore and will require demolition. If we are wrong e.g. if [the] landslip stops now then clearly the risk of landslip recommencing is very high and consequently the property would have little, if any, market value as a dwelling.”