“The nominated transport manager’s original certificate(s) of professional competence in passenger transport operations [is required]. The certificate submitted is confirmation of the overall qualification. Please upload the full page of the actual certificate to the online application.”
“…I note that the additional documentation listed in the attached annex remains outstanding. This letter is intended as a final attempt to resolve these issues by correspondence and you must now respond in full by no later than09/01/2025 . If on that date the application remains incomplete, itwill be refused… SUPPORTING DOCUMENTATION REQUIRED ◦ The nominated transport manager’s original certificate(s) of professional competence in passenger transport operations. The certificate previously submitted is not classed as the full CPC certificate. ◦ You must provide further details to satisfy the traffic commissioner regarding the suitability of the proposed site. We must be assured that this is an appropriate site for your 2 PSV vehicles. It is noted you have supplied evidence of the site and a contract for parking. However, the Traffic Commissioner must be satisfied with the specific area for your exclusive use. Please provide photo evidence of the specific/exclusive area and how this area will be kept clear at all times.” ◦ The nominated transport manager’s original certificate(s) of professional competence in passenger transport operations. The certificate previously submitted is not classed as the full CPC certificate. ◦ You must provide further details to satisfy the traffic commissioner regarding the suitability of the proposed site. We must be assured that this is an appropriate site for your 2 PSV vehicles. It is noted you have supplied evidence of the site and a contract for parking. However, the Traffic Commissioner must be satisfied with the specific area for your exclusive use. Please provide photo evidence of the specific/exclusive area and how this area will be kept clear at all times.”
“We have sent you a letter dated 26 December seeking further information to support your application. It is crucial you respond quickly so the application can be considered by the Traffic Commissioner. You will note within the final letter it highlights…failure to respond or provide a satisfactory response, the application will be refused.”
“…The deadline set in our last letter has now ended. As such, your application has been refused under Section 14 of the [1981 Act], as it remains incomplete. The documentation requested was not received and no explanation was offered as to why you were unable to submit the information. You have not provided evidence the nominated transport manager has the correct CPC. As such, you have not demonstrated that you meet the requirement for professional competence as set out on Section 14ZA(2) of the [1981 Act]. A traffic commissioner is not satisfied that you meet the requirement of arrangements for driving/operation of vehicles as set out in Section 14ZC(1)(b) of the [1981 Act]. This is because you have failed to provide satisfactory evidence that the nominated operating centre/area for parking is exclusive to you and is suitable for the requested authorisation.”
“(4) An application for a PSV operator's licence shall be made in such form as a traffic commissioner may require, and an applicant shall give the traffic commissioner dealing with the application such information as he or another traffic commissioner may reasonably require for disposing of the application.”
“I applied for the PSV operator license and received a reply on13/01/2025 requesting additional supporting documentation I called in and spoke to an assistant…advising me to send an email to him which he sent on December 4 2024…I have done everything that was advised to me. I have attached all supporting evidence and all correspondence regarding my licence.”