“(1) For the purposes of sections 299 to 304, the time limit for expenditure on the construction of a building on a site in an enterprise zone is- (a) 10 years after the site was first included in the zone, or (b) If the expenditure is incurred under a contract entered into within those 10 years, 20 years after the site was first included in the zone.”
“… the design, construction and commissioning work comprising an industrial unit to accommodate the manufacture of an eight inch board on Site C for which works the Employer has issued to the Contractor its requirements (hereinafter referred to as the ‘Works Option 1 Employer’s Requirements’).”
“… the design and construction works comprising an office business park on Site A for which works the Employer has issued to the Contractor its requirements (hereinafter referred to as the ‘Works Option 3 Employer’s Requirements’).”
“The document referred to in Appendix 14 Appendix 15 Appendix 16 Appendix 17 Appendix 18 Appendix 19 (as the case may be) setting out the requirements of the Employer in relation to the relevant Works Option.”
“to give the statutory provision a purposive construction in order to determine the nature of the transaction to which it was intended to apply and then to decide whether the actual transaction (which might involve considering the overall effect of a number of elements intended to operate together) answered to the statutory description.”
“The ultimate question is whether the relevant statutory provisions, construed purposively, were intended to apply to the transaction, viewed realistically.”
“(1) For the purposes of sections 299 to 304, the time limit for expenditure on the construction of a building on a site in an enterprise zone is- (a) 10 years after the site was first included in the zone, or (b) if the expenditure is incurred under a contract entered into within those 10 years, 20 years after the site was first included in the zone.” (a) 10 years after the site was first included in the zone, or (b) if the expenditure is incurred under a contract entered into within those 10 years, 20 years after the site was first included in the zone.”
“… the general rule is that an amount of capital expenditure is treated as incurred as soon as there is an unconditional obligation to pay it.”
“The Chancellor of the Exchequer has announced proposals for setting up, on an experimental basis, about half-a-dozen ‘enterprise zones’. Within small sites of up to 500 acres, private enterprise will be positively encouraged by reducing the burden of government supervision and fiscal demands. The sites chosen will be in areas of physical and economic decay where conventional government policies have not succeeded in regenerating self-sustaining economic activity. … Measures The Enterprise Zones will be designated for an initial period of ten years, subject to renewal. Both the new and existing firms in the zones will benefit from the following measures: 1. Exemption from development land tax. 2. 100 per cent. capital allowances (for income and corporation tax purposes) on industrial and commercial property. 3. Exemption from general rates on industrial and commercial property. 4. Simplification of planning procedures… The aim is to stimulate economic activity by removing the hand of government as far as possible.”
“4…Since the aim of setting up an Enterprise Zone is to achieve a significant impact by way of new development, improvement of existing property, or increased economic activity within a reasonable timescale, the Government proposes that the designation orders for Enterprise Zones should run for a period of ten years. Designation will bring into effect the fiscal and other measures listed below. 5. During the ten year period both new and existing firms within the Enterprise Zone will benefit from the following measures…”
“it is a matter of fact and degree as to whether the instruction for a variation goes beyond a change envisaged by the contract and instructs something over and above that which was expected and contracted for. … As with all matters of fact and degree it is easier to demonstrate at the extremes than it is at the margin. So, for example, a contract to build a beach house will have implicit within the variations clause a right to change the colour of the external paintwork. It will not extend to the right to order that the contractor build a lighthouse alongside.”
“The Employer may subject to the proviso hereto and to clause 12.2.2 issue instructions effecting a Change in the Employer’s Requirements. No Change effected by the Employer shall vitiate this Contract. Provided that the Employer may not effect a Change which is, or which makes necessary, an alteration or modification in the design of the Works without the consent of the Contractor which consent shall not be unreasonably delayed or withheld.”
“The term ‘Change in the Employer’s Requirements’ or ‘Change’ means: 12.1.1. a change in the Employer’s Requirements which makes necessary the alteration or modification of the design, quality or quantity of the Works, otherwise than such as may be reasonably necessary for the purposes of rectification pursuant to clause 8.4, including 1.1 the addition, omission or substitution of any work, 1.2 the alteration of the kind or standard of any of the materials or goods to be used in the Works, 1.3 the removal from the site of any work executed or materials or goods brought thereon by the Contractor for the purposes of the Works other than work materials or goods which are not in accordance with this Contract;”
“‘Employer’s Requirements’ means the document referred to in Appendix 14 Appendix 15 Appendix 16 Appendix 17 Appendix 18 Appendix 19 (as the case may be) setting out the requirements of the Employer in relation to the relevant Works Option.” “Works Option” is defined, also in clause 1.3, as follows: “‘Works Option’ means Works Option 1 or Works Option 2 or Works Options 3 or Works Option 4 or Works Option 5 or Works Option 6 (as the case may be).”
“‘Works Option 1’ means the design, construction and commissioning work comprising an industrial unit to accommodate the manufacture of an eight inch board on Site C for which works the Employer has issued to the Contractor its requirements (hereinafter referred to as the Works Option 1 Employer’s Requirements).”
“‘Works Option 1 Employer’s Requirements’ means the documents referred to in Appendix 14 as Ref: ER WOl.”
“‘Works’ means the design, construction and commissioning the Employer wishes to obtain for the Works Option stated in the Notice to Proceed which for the avoidance of doubt shall either be Works Option 1 Works Option 2 Works Option 3 Works Option 4 Works Option 5 or Works Option 6 and referred to in the Employer’s Requirements and the Contractor’s Proposals for that Works Option and including any work needed to ensure that the Tests on Completion and the Performance Tests are passed and any changes made to these works in accordance with this Contract” (our italics). 1.1 the addition, omission or substitution of any work, 1.2 the alteration of the kind or standard of any of the materials or goods to be used in the Works, 1.3 the removal from the site of any work executed or materials or goods brought thereon by the Contractor for the purposes of the Works other than work materials or goods which are not in accordance with this Contract;”
“[t]he question is whether there is an intention in any event to rescind, independent of any further intention which may exist to substitute a second contract”; see also p 19: “[w]hat is … essential is that there should have been made manifest the intention [sc of the parties] in any event of a complete extinction of the first and formal contract, and not merely the desire of an alteration, however sweeping, in terms which still leave it subsisting”
“The criterion [determining whether effect will be given to the later oral contract] is in the question whether what is intended to be effected by the second contract is rescission or variation”
“The variation may be a new contract, so as to make writing … indispensable to its admissibility, for this is a matter of form and of the words of the statute, but the discharge of the old contract must depend on intention …”
“what … was the intention of the parties” in substituting a later date for delivery; “did they intend to substitute a new contract for the old one, the same in all other respects except those of the day of delivery [and another term which was changed] with the old one?”
“Both parties enjoyed freedom to contract or not to contract and both parties exercised that freedom by contracting on the terms set forth in the written agreement and on no other terms. But the consequences in law of the agreement, once concluded, can only be determined by consideration of the effect of the agreement. If the agreement satisfied all the requirements of a tenancy, then the agreement produced a tenancy and the parties cannot alter the effect of the agreement by insisting that they only created a licence. The manufacture of a five pronged implement for manual digging results in a fork even if the manufacturer, unfamiliar with the English language, insists that he intended to make and has made a spade.”