“(5) Proceedings under subsection (l)(a) must be brought before the end of - (a) the period of one year beginning with the date on which the act complained of took place; or (b) such longer period as the court or tribunal considers equitable having regard to all the circumstances …”
“We consider, therefore, that in legacy cases the issue of damages against any public authority for breach of the adjectival obligation inarticle 2 ECHR ought to be dealt with once the inquest has finally been determined. Each public authority against whom an award is sought should be joined. In order to achieve this it may be necessary to rely upon section 7(5)(b) of the 1998 Act. The principle that the court should be aware of all the circumstances and the prevention of even further litigation in legacy cases are compelling arguments in favour of it being equitable in the circumstances to extend time if required. Where the proceedings have been issued within 12 months of the conclusion of the inquest, time should be extended.”
“We find it difficult to envisage any circumstances in which there should be an exception to the approach set out in the preceding paragraph in such cases.”
“For the reasons given we consider that the claim for damages for delay should be assessed after the completion of the inquest but should be made within one year of the completion. Since we have ordered a fresh inquest in this case that period has not yet commenced. We will hear the parties on whether the appeal on the award of damages should be adjourned until after the inquest or allowed without adjudication on the merits to enable the issue of a fresh claim.”
“1. that the claim for damages for breach of the article 2 procedural requirement that an inquest be conducted ‘promptly’ should not be brought until the inquest has finally been determined. 2. that where a claim for damages for breach of the article 2 procedural requirement that an inquest be conducted ‘promptly’ is brought within 12 months of the conclusion of the inquest, time should be extended under section 7(5)(b) of the 1998 Act [ie the Human Rights Act]. 3. that the appeal be stayed until the conclusion of the inquest proceedings.”
“1. that the issue of delay at ground 7 on the cross-appeal be stayed until the conclusion of the inquest proceedings.”
“21. We accept that this passage created the impression that in every legacy case any application to pursue a remedy by way of damages for delay could only be dealt with at the end of the inquest. Indeed it is clear that that was the common understanding of the parties before the learned trial judge as a result of which the applicant decided to abandon the determination of his claim for damages in the proceedings and rely solely upon the claim for a declaration … 22. We consider, however, that this passage of the judgment ought to be interpreted in a rather more qualified manner. First, it has to be borne in mind that the court, having given the judgment in September 2015, decided of its own motion to relist the case for the determination of the damages claim in June 2017 having regard to the fact that the inquest had not yet concluded. Secondly, it needs to be borne in mind that this was a case management decision and was not intended to set forth any rule of law about the entitlement to damages in legacy cases. Thirdly, the case was concerned with circumstances in which there were active and ongoing inquest proceedings but where issues of delay in the course of those active proceedings arose. It was such cases that were being discussed in this passage of the judgment and we consider that the interpretation of para 27 [ie para 22 of the revised version] should be confined to cases in which those circumstances are present.”
“The inquest in this case has not taken place. No Coroner has been allocated to hear it and no materials have been provided to the Coroner’s Service by the police. It is impossible to estimate how many years it might take before the inquest might proceed …”