“‘Commencement Date’ means the date on which the Treatment Plant is first capable of processing 250,000 US gallons per day of Influent for transfer to the Effluent Transfer Point, such date to be agreed in writing between the Government and the Company and shall become an integral part of this Agreement.”
“When the Company has completed the installation of the Treatment Plant, including the testing and commissioning thereof, such that it may be used for the purposes for which it is intended (‘Substantial Completion’) the Government shall issue a Taking over Certificate transferring ownership of the Treatment Plant to the Government. Thereafter, the Company [GWA] shall issue a ‘Commencement Notice’ no later than ten days after receipt of the Taking Over Certificate, indicating the commencement of the management, operation and maintenance phase of the Treatment Plant.” (Emphasis added)
“(1) A prepared project site suitable for installation of Water Reclamation Facility to include paved parking, fencing, lighting, landscaping and excavation. (2) A boundary and topographic survey of the property. …”
“Breach of the DBA prevented the fulfilment of a condition precedent to the performance of a distinct and separate contract; it prevented the MOMA from commencing. But there was no promise in the DBA to satisfy the requirement for commencement of the MOMA. Without the MOMA commencing [GWA] did not have the opportunity or any right to make a profit. It could have these only under the MOMA. Damages for loss of profit from the MOMA would flow from breach of the MOMA. They did not flow from breach of the DBA. It is, therefore, our conclusion that the loss of profits resulting from the failure to commence the MOMA, although the indirect consequence of the breach of the DBA, may not be recovered by way of an award of damages for breach of the DBA. They are too remote in law.”
“[T]he proper rule in such a case as the present is this:- Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, ie, according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it.” (Emphasis added)
“Now, if the special circumstances under which the contract was actually made were communicated by the plaintiffs to the defendants, and thus known to both parties, the damages resulting from the breach of such a contract, which they would reasonably contemplate, would be the amount of injury which would ordinarily follow from a breach of contract under these special circumstances so known and communicated.”
“But it is obvious that, in the great multitude of cases of millers sending off broken shafts to third persons by a carrier under ordinary circumstances, such consequences would not, in all probability, have occurred; and these special circumstance were here never communicated by the plaintiffs to the defendants.” (Emphasis added)
“It is also a question of what the contracting parties must be taken to have had in mind, having regard to the nature and object of their business transaction. If a manufacturer of lightning conductors sells a defective conductor and the customer’s house burns down as a result, the manufacturer will not escape liability by proving that only one in a hundred of his customers’ buildings had actually been struck by lightning. … Arguably a vague expression (such as ‘real possibility’) is actually preferable, because it is more flexible, once it is understood that what is most important is the common expectation, objectively assessed, on the basis of which the parties are entering into their contract.”
“The general rule is that loss is too remote if that type of loss could not reasonably have been contemplated by the defendant as a serious possibility at the time the contract was made assuming that, at that time, the defendant had thought about the breach.” (Emphasis added)
“Breach of the DBA prevented the fulfilment of a condition precedent to the performance of a distinct and separate contract; it prevented the MOMA from commencing.”
“It must be taken as given that the parties would have contemplated at the time the Design and Build Agreement was concluded that if a treatment plant was never built, the respondent [GWA] would be deprived of the opportunity to reap the profits expected to be derived from the fulfilment of its obligations under the Management Agreement.”