“… we now write to outline our understanding of the agreement for the National Housing Trust (NHT) to takeover the East Prospect Phase II housing project. The operational framework for the takeover of the project is set out for your review and agreement. (1) YP Seaton & Associates agreed to handover the project as is to the NHT as of 1999 January 18. (2) The NHT agreed to takeover the project as of 1999 January 18. (3) The project accounts prepared by the NHT and dated 1999 January 7 will be considered final subject to further agreement on the interest and profit items. a. The NHT & YPS will refer the items of interest cost beyond the contract time and profit to an arbitrator if no agreement is reached by 1999 January 31. b. The commitment fees on the project will not be for YP Seaton & Associates’ account. (4) YP Seaton & Associates has until 1999 January 18 to make full submissions to Geta Engineers of any items of final measurement. Geta Engineers’ certificate issued after 1999 January 18, will be considered final. (5) The NHT is to take possession of the site on 1999 January 18 and complete the housing project singly, without YP Seaton & Associates’ involvement. The NHT is to re-configure and sell housing solutions as it sees fit. (6) YP Seaton & Associates is to cease its involvement with the project at handover to the NHT and the final accounts are to reflect the status at handover. There will be no accounting to YP Seaton & Associates at completion of the project. (7) The NHT would be responsible for resolving the squatter difficulties on site. YP Seaton & Associates agreed to make additional lands, originally proposed, available to NHT to resettle the squatters. (8) A re-measurement of the works on the date of takeover is necessary to adjust the project accounts as part of the works has deteriorated while other aspects have been vandalized. This remeasurement adjustment is to be incorporated in the adjusted final project accounts. (9) YP Seaton & Associates will ensure that the NHT has a Power of Attorney to be able to deal with the utilities, the Tax Office and any other entities to complete all transactions on the project. (10) After the final accounts have been agreed and issued, any debt will be settled in a three-month timeframe. Until the agreement is prepared and signed by both parties, this letter will be evidence of our (NHT & YP Seaton & Associates) understanding. As the completion of the project is paramount, the NHT has full authority to take possession of the project lands on 1999 January 18 and proceed with the construction and complete the project.”
“TERMS OF REFERENCE THIS AGREEMENT is made the 8th day of April 2004 between [YPSA] … Page 10 of the ONE PART and … NHT [the Trust] of the OTHER PART. WHEREAS: 1. The parties entered into an agreement in or around July 1999, the purpose of which was to: (i) facilitate the handover of the East Prospect, Phase II housing project (the Project) by YPS to NHT for completion as NHT sees fit; and (ii) as far as possible enable NHT to be paid all sums that are due and payable to NHT by YPS and to fulfil NHT’s commitment to sell housing solutions in the Project to its contributors. 2. The agreement was set out in a letter dated 27 July, 1999 from Rattray Patterson Rattray - the Attorneys-at-Law for [YPSA] addressed to National Housing Trust and a copy of the said letter was signed by YPSA and [NHT] (and the Seal of each was affixed) as an indication of their agreement with the terms set out therein; 3. The letter sets out the agreement of the parties that the project account prepared by NHT and dated January 7, 1999 will be considered final SAVE AND EXCEPT for the following issues: (a) INTEREST YPS and NHT have agreed to refer to arbitration the interest portion of this statement shown as [J$27,255,919.92 ] as at the 18th day of January 1999; (b) PROFIT YPS and NHT have also agreed to refer to arbitration the issue of the contractor’s profit which is provided for in the agreement at a rate of 14.8%; (c) CERTIFICATE 19 YPS and NHT have agreed that GETA or an agreed Consulting Engineer is to be called upon to clarify this certificate; (d) RE-MEASUREMENT OF WORKS A remeasurement of the works on the date of and over will be done to adjust the project account, which re-measurement will be incorporated in the adjusted final account for the Project. 4. Accordingly, as set out at para 3 above, the parties agreed that the following two unresolved matters should be referred to arbitration. (a) Interest; and (b) Profit 5. It was further agreed that: (a) Once the adjusted final account has been prepared and issued and the issues of interest and profit referred to arbitration have been settled, any debt owed by YPS and NHT will be settled within a six (6) months time frame. (b) Sums not in dispute must be settled within six (6) months of the issue of the final accounts. (c) The sums declared outstanding based on the arbitration proceedings shall be settled within six months of the arbitration decision. 6. Pursuant to the agreement of the parties referred to above, the following two matters are hereby referred for arbitration: (a) The interest portion of this statement shown as J$27,255,919.92 as at the 18th day of January, 1999; (b) The issue of the contractor’s profit which is provided for in the agreement at a rate of 14.8%; 7. The parties hereby further agree as follows: (a) The arbitrator shall have all the powers given to arbitrators by virtue of the Arbitration Act and shall be requested to make his award on or before the day of … 2004. (b) The arbitrator shall have the power to proceed ex parte in case either party fail after reasonable notice to attend before him. (c) The provisions of the Arbitration Act in so far as they are consistent with the provisions hereunder shall be deemed to be incorporated herein. (d) The parties shall do and cause to be done all such things necessary and convenient for enabling the arbitrator to make his award without delay.”
“[31] His powers not being in any way circumscribed by the Act, the arbitrator had the jurisdiction to make an award of compound interest in accordance with the general law applicable to the dispute submitted to him. He was required to utilize his experience and expertise and to exercise his discretion to do what was just and equitable in resolving the dispute between the parties.”
“The settlement of differences in connection with the Loan Agreement was thus effected with the exception of two issues referred to above: (1) INTEREST: … (2) PROFIT: …”
“27. By letters dated23 June 2006 and13 March 2007 , the respondent’s bankers, Scotiabank wrote to the respondent setting out the base rate for the period 1994 to 2005 and stating that the applicable rate to the respondent was Base plus 3%. Copies of the said letters are attached hereto for completeness. 28. Following from the above using the commencement date of30 October 1997 and applying the prevailing commercial rates of interest (base + 3%), the interest owed to the respondent may be calculated as follows:- [There followed a month by month computation of compound interest on the sum of J$24,325,000 from October 1997 to January 2007, leading to the total of J$214,512,232.76 ] 29. Notwithstanding the foregoing, the issue of the appropriate rate of interest remains solely an issue for the discretion of the learned arbitrator.”
“That expression does not necessarily involve personal turpitude on the part of the arbitrator, and any such suggestion has been expressly disclaimed in this case. The term does not really amount to much more than such a mishandling of the arbitration as is likely to amount to some substantial miscarriage of justice.”
“‘Misconduct’ is often used in a technical sense as denoting irregularity, and not any moral turpitude. But the term also covers cases where there is a breach of natural justice. Much confusion is caused by the fact that the expression is used to describe both these quite separate grounds for setting aside an award; and it is not wholly clear in some of the decided cases on which of these two grounds a particular award has been set aside.”
“… if there is an order which on its face is unusual there is a rebuttable presumption that the arbitrators are wrong. In this case it is said that the award is unusual on its face. That is right. … It is said that … it is unusual that the sellers, the main beneficiaries [of the award] should be expected to pay the costs. That also is right. It calls, therefore, not for an explanation of what the board had in mind but it calls for the buyers, if they wish to hold this award, to point to factors which in the exercise of a judicial discretion the arbitrators could have relied upon as justifying their award.”
“Now the question of interest is quite different in its application, although the principle is, I think, the same. ... [The board] have made what, to me, is a most unusual order in respect of interest on the carrying charges.”
“Further, respondents submitted detailed statements of how interest payments and the basis of their claim had been computed. No commensurate calculations were submitted by the claimants.”
“In all cases of reference to arbitration the court or a Judge may from time to time remit the matters referred, or any of them, to the reconsideration of the arbitrators or umpire.” and “Where an arbitrator or umpire has misconducted himself or an arbitration or award has been improperly procured the court may set the award aside.”
“An error in law on the face of the award means, in their Lordships’ view, that you can find in the award or a document actually incorporated thereto, as for instance a note appended by the arbitrator stating the reasons for his judgment, some legal proposition which is the basis of the award and which you can then say is erroneous. It does not mean that if in the narrative a reference is made to a contention of one party that opens the door to seeing first what that contention is, and then going to the contract on which the parties’ rights depend to see if that contention is sound.”
“In my judgment the remission jurisdiction extends beyond the four traditional grounds to any cases where, notwithstanding that the arbitrators have acted with complete propriety, due to mishap or misunderstanding, some aspects of the dispute which has been the subject of the reference has not been considered and adjudicated upon as fully or in a manner which the parties were entitled to expect and it would be inequitable to allow any award to take effect without some further consideration by the arbitrator.”
“In so expressing myself I am not seeking to define or limit the jurisdiction … subject to the vital qualification that it is designed to remedy deviations from the route which the reference should have taken towards its destination (the award) and not to remedy a situation in which, despite having followed an unimpeachable route, the arbitrators have made errors of fact or law and as a result have reached a destination which was not that which the court would have reached. … The qualification is … of fundamental importance. Parties to arbitration, like parties to litigation, are entitled to expect that the arbitration will be conducted without mishap or misunderstanding and that, subject to the wide discretion enjoyed by the arbitrator, the procedure adopted will be fair and appropriate. What they are not entitled to expect of an arbitrator any more than of a judge is that he will necessarily and in all circumstances arrive at the ‘right’ answer as a matter of law. That is why there are rights of appeal in litigation and no doubt would be in arbitration were it not for the fact that in English law it is left to the parties, if they so wish, to build a system of appeal into their arbitration agreements and few wish to do so, preferring ‘finality’ to ‘legality’. …”