“You have so many thousand miles of coast-line to defend by your torpedo-boat destroyers; what would four torpedo-boat destroyers do for that purpose? How could you say you are damaged by their non-delivery? How many filibustering expeditions could you have stopped by the use of four torpedo-boat destroyers?”
“When a single lump sum is made payable by way of compensation, on the occurrence of one or more or all of several events, some of which may occasion serious and others but trifling damage, the presumption is that the parties intended the sum to be penal, and subject to modification. The payments stipulated in article 12 are not of that character; they are made proportionate to the extent to which the respondent company may fail to implement their obligations, and they are to bear interest from the date of the failure. I can find neither principle nor authority for holding that payments so adjusted by the contracting parties with reference to the actual amount of damage ought to be regarded as penalties.”
“I know of no authority for holding that a payment agreed to be made under such conditions as these is to be regarded as a penalty only; and I see no sound reason or principle, or even convenience, for so holding.”
“I hold it to be part of our law on this subject that, even where parties stipulate that a sum of this kind shall not be regarded as a penalty, but shall be taken as an estimate and ascertainment of the amount of damage to be sustained in a certain event, equity will interfere to prevent the claim being maintained to an exorbitant and unconscionable amount.”
“But, of course, the question whether it is exorbitant or unconscionable is to be considered with reference to the point of time at which the stipulation is made between the parties.”