“11 General conditions as to availability of plant and machinery allowances (1) Allowances are available under this Part if a person carries on a qualifying activity and incurs qualifying expenditure. (2) “Qualifying activity” has the meaning given by Chapter 2. (3) Allowances under this Part must be calculated separately for each qualifying activity which a person carries on. (4) The general rule is that expenditure is qualifying expenditure if— (a) it is capital expenditure on the provision of plant or machinery wholly or partly for the purposes of the qualifying activity carried on by the person incurring the expenditure, and (b) the person incurring the expenditure owns the plant or machinery as a result of incurring it. (5) But the general rule is affected by other provisions of this Act, and in particular by Chapter 3.”
“22 Structures, assets and works (1) For the purposes of this Act, expenditure on the provision of plant or machinery does not include expenditure on – (a) the provision of a structure or other asset in list B, or (b) any works involving the alteration of land. LIST B – EXCLUDED STRUCTURES AND OTHER ASSETS … 5. A dock, harbour, wharf, pier, marina or jetty or any other structure in or at which vessels may be kept, or merchandise or passengers may be shipped or unshipped. … (2) The provision of a structure or other asset includes its construction or acquisition. (3) In this section – (a) “structure” means a fixed structure of any kind, other than a building (as defined by section 21(3)), and (b) “land” does not include buildings or other structures, but otherwise has the meaning given in Schedule 1 to theInterpretation Act 1978 . (4) This section is subject to section 23.”
“23 Expenditure unaffected by sections 21 and 22 … (3) Sections 21 and 22 also do not affect the question whether expenditure on any item described in list C is, for the purposes of this Act, expenditure on the provision of plant or machinery. … LIST C – EXPENDITURE UNAFFECTED BY SECTIONS 21 AND 22 1. Machinery (including devices for providing motive power) not within any other item in this list. … 22. The alteration of land for the purpose only of installing plant or machinery. … 24. The provision of any jetty or similar structure provided mainly to carry plant or machinery.”
“The Appellant 1. The Appellant, the Mersey Docks & Harbour Company Limited (‘MDHC’), operates the Port of Liverpool, including acting as the “Statutory Harbour Authority” and “Competent Harbour Authority” for the Port. As a Statutory Harbour Authority and Competent Harbour Authority, MDHC has the right to levy pilotage and ship’s dues on all vessels entering the harbour and goods’ dues on all goods imported and exported from the Port of Liverpool. 2. MDHC’s income from the Port of Liverpool includes statutory rates and dues, cargo handling (including containers, liquid bulks, bulk solids, agribulks and roll-on/roll-off vessels including cars), pilotage, mooring, towage and property rental income. MDHC is liable to corporation tax in respect of its income. 3. Between 2013 and 2017 MDHC developed Liverpool2, a new deep-water container terminal at the Port of Liverpool. 4. Liverpool2 is an extension of Liverpool’s Seaforth Dock container terminal, which opened in 1971. The new terminal was designed to accommodate the larger container vessels which have become more common globally since work to expand the Panama Canal was completed in 2016. These vessels are referred to as “Post-Panamax” vessels. Liverpool2 in outline 5. The following elements of Liverpool2 are material in relation to this appeal. The descriptions below are without prejudice to the Parties’ contentions as to how the relevant asset(s) should be identified for the purposes of the relevant legislation (and, in particular, are without prejudice to the Respondents’ contention that the Quay Wall does not have a distinct identity): (1) Berthing Pocket: The Berthing Pocket is an area of the riverbed adjacent to Liverpool2, dredged specifically to allow the berthing, unloading and loading of two “Post-Panamax” container vessels at Liverpool2 at all states of the tide. (2) Quay Wall: The Quay Wall refers to the structure which abuts the River Mersey up to the rear crane rail for the Ship to Shore Cranes (the “STS Cranes”). (3) Container Transition Area: Immediately behind the Quay Wall is the Container Transition Area. The Container Transition Area forms part of the land which was reclaimed from the River Mersey in the course of the construction of Liverpool2, and is used for the storage and handling of containers by the “Cantilever Rail Mounted Gantry Cranes” (the “CRMG Cranes”) which have been unloaded from ships or are to be loaded. (4) Ship-to-Shore Cranes: Containers are loaded onto and unloaded from ships by STS Cranes; five of which were installed as part of the Liverpool2 extension project and a further three in 2020. The STS Cranes overhang the docking area (extending over the water and the ships, adjacent to the Quay Wall). They run on rails founded on the Quay Wall. Containers which are unloaded are transferred by the STS Cranes to lorries which transport them to the Container Transition Area, where they are organised and stored by the CRMG Cranes. Similarly, when containers are loaded, they are transferred to lorries which transport them from the Container Transition Area to the Quay Wall, and then transferred by the STS Cranes to the relevant ship. (5) Cantilever Rail Mounted Gantry Cranes: Containers are handled within the Container Transition Area by 22 CRMG Cranes. Twelve were include in the Liverpool2 extension project with a further ten added in 2020. The CRMG Cranes run on rails in the Container Transition Area and perform operations such as stacking and organising the containers and loading/unloading them onto/from lorries. 6. There is no dispute between the parties as to the relevant tax treatment of the Berthing Pocket, the Container Transition Area, the CRMG Cranes or the STS Cranes, including the rear crane piles and crane rails referred to at paragraphs 9(3) and 9(8) below. (The parties were previously also in dispute as to the timing of the availability of capital allowances in respect of expenditure incurred by MDHC on the cranes at Liverpool2. On the facts of this case, however, HMRC no longerchallenges MDHC’s claim for capital allowances on expenditure incurred on the provision of the cranes in the accounting periods ending31 March 2015 and 2016.) Quay Wall Design 7. The design intent of the Liverpool2 development was a modern container terminal to allow the Port of Liverpool to expand its container operation and to serve large Post-Panamax size vessels at a tidal berth in the River Mersey. 8. Part of the Liverpool2 development project (‘Package 2’) consisted of the Berthing Pocket and the construction of the Quay Wall. Quay Wall Overview 9. The design phase resulted in the construction over a period from June 2013 to November 2016 of a long oblong structure running approximately South to North along the eastern bank of the River Mersey at Seaforth, made up of: (1) 40m long Steel tubular piling at 3.14 metre centres, on the river side of the Quay Wall, these piles, drilled into bedrock 20m and infilled by intermediate sheet piles (the ‘Outer Piling’). (2) a 831m long concrete coping beam sitting on the Outer Piling line. (3) 30m long concrete Continuous Flight Auger (“CFA”) piling at again 3.14 metre centres on the landward side of the Quay Wall drilled to bedrock (the ‘Inner Piling line’). (4) A 829m long concrete rear crane beam sitting on the Inner Piling line. (5) Steel tiebacks from the Outer Piling line to land anchors on the landward side of the Inner Piling line. (6) Sand infill between the Outer Piling line and Inner Piling line. (7) A 831m long, 30m wide and 0.3m deep concrete slab sitting above / on the sand infill. The slab provides the upper surface of the Quay Wall. (8) Crane rails set into the concrete coping beam to accommodate the front and rear wheels of the STS Cranes. (9) Bollards and fenders cast into the river side coping beam. Quay Wall Sections 10. The Quay Wall as constructed consists of three sections: (1) The North Tie-In which forms the transition between the Quay Wall and the existing riverbank. (2) The main section. (3) The South Tie-In which forms a return wall between the Quay Wall and the existing Gladstone River Entrance Lock. In the triangular area between the South Tie-In and the Gladstone Lock, rock armour has been installed. The rock armour prevents scour due to possible tidal current eddies and acts as passive resistance to the wall. The sheet pile wall at the South Tie-In is supported by a waling beam which is connected at one side to Gladstone Lock and at the other to a tubular pile providing additional resistance support.”
“ISSUE 1 – SINGLE/MULTIPLE PLANT 15. As to what constitutes plant, as is well-established, and as the Court of Appeal noted in Cheshire Cavity Storage 1 Ltd v HMRC (at [32]), there is no statutory definition of “plant” but the meaning of the term has been discussed in a large number of cases. Reflecting the way the parties have argued their cases, we come on to focus on two in particular: IRC v Barclay Curle Co Ltd[1969] 1 WLR 675 (expenditure in relation to a dry dock) and Cole Brothers Ltd v Phillips[1980] STC 518 (expenditure in relation to electrical installation in a department store). 16. It is not in dispute that the considerable amount of expenditure on buying the wind turbines is qualifying expenditure and that the wind turbines and cables are items which are capable of being plant. The relevant issue here is whether each wind turbine and each connected array cable are single items of plant, as HMRC argue, or whether the wind turbines and array cables collectively (the “generation assets”) are an item of plant, as the taxpayers argue. This issue may affect the analysis of what study expenditure qualifies under Issue 2 as expenditure “on provision of plant”
“… taking into account the dry dock in Barclay Curle, [the Special Commissioners had] indicated that the component (or individual) parts need[ed] to be directed towards a single purpose” 18. The FTT noted the above test was: “endorsed by Lord Hailsham when he said that the analysis needs to be of the individual components regarding the nature and function of each.” 19. Accordingly, the FTT continued (at [112(2)]), that meant that: “…if, on the evidence, the component parts of the windfarm [were] directed towards a single purpose, then those assets [could] be treated as a single item of plant.” 20. The FTT also described the test this way at [112(4)]: “(4)… the test is whether, taking into account the nature and function of the individual components of a composite item, those components are directed towards a single purpose.” 21. Ms Wilson KC, who, along with Ms Parry, also appeared before the FTT, argues on behalf of HMRC that this “directed towards a single purpose” test was wrong and that the FTT therefore erred in its approach. The FTT ought to have adopted the test set out in Barclay Curle. That was whether the putative single item was “one integral item of plant” and whether it had a “distinct operational function”
“51. The correct approach therefore is one of ascertaining the facts and circumstances. In doing that it is relevant to look at the function of the item(s) under consideration. Whether that is described as “distinct operational function” or the item being “directed towards a single purpose” does not matter. The real point of difference between the parties here is, we consider, therefore about the level at which the purpose or function test is applied. This is revealed by the way Ms Wilson put her submission. She argued the FTT’s analysis (at the level of the trading operation as the sale of usable electricity to National Grid) was at too high a level. In her submission, the FTT started to err by seeing the test as a separate test for single/multiple items when there was just one test – “is it plant?”
“Since the question whether something is or is not plant is a question of fact, or a question of fact and degree, it is necessary to pay close attention to the facts of previous cases. In some cases the court has upheld the decision of the fact-finding tribunal on the basis that it was entitled to find as it did. In such a case, it does not follow that the fact-finding tribunal would have made an error of law if it had decided the question differently.”
“The taxpayer company say that the whole dock was part of their plant used by them for the purposes of their trade. "Plant" is nowhere defined in the Act, and they rely chiefly on what was said by Lindley L.J. in Yarmouth v France and on the statement of the question by Pearson L.J. in Jarrold v John Good & Sons Ltd: "… whether the partitioning is part of the premises in which the business is carried on or part of the plant with which the business is carried on?" As the Commissioners observed, buildings or structures and machinery and plant are not mutually exclusive, and that was recognised in Jarrold's case. Undoubtedly this concrete dry dock is a structure, but is it also plant? The only reason why a structure should also be plant which has been suggested or which has occurred to me is that it fulfils the function of plant in the trader's operations. And, if that is so, no test has been suggested to distinguish one structure which fulfils such a function from another. I do not say that every structure which fulfils the function of plant must be regarded as plant, but I think that one would have to find some good reason for excluding such a structure. And I do not think that mere size is sufficient. Here it is apparent that there are two stages in the Respondents' operations. First, the ship must be isolated from the water and then the inspection and necessary repairs must be carried out. If one looks only at the second stage it would not be difficult to say that the dry dock is merely the setting in which it takes place. But I think that the first stage is equally important, and it is obvious that it requires massive and complicated equipment. No doubt a small vessel could be got out of the water by the use of comparatively simple plant and machinery, but clearly that is impossible with a very large vessel. It seems to me that every part of this dry dock plays an essential part in getting large vessels into a position where work on the outside of the hull can begin, and that it is wrong to regard either the concrete or any other part of the dock as a mere setting or part of the premises in which this operation takes place. The whole dock is, I think, the means by which, or plant with which, the operation is performed.”
“In summary therefore, Barclay Curle does not impose a necessity test but makes the point that “provision of plant” may cover more than the cost of plant itself or its actual supply. It can also cover expenditure on installing the plant on the basis that without installation the plant cannot be said to have been provided for the purposes of the trade.”