“During the early phase of operation, particular care must be taken to ensure that traffic does not damage the liner…. Particular care should be taken in placing the first lift of refuse, and build up of water and leachate should also be controlled…”
“No bulky items, even after crushing, should be present in the first lift of refuse deposited in a site lined with a polymeric membrane due to the risk of damaging the liner (see paragraph 4.64 [6] ). Similarly, bulky items should not be present in the final lift of waste in sites that are to be capped with a low permeability material since settlement of the refuse may result in large items piercing the cap. After-use of the land may also be adversely affected.”
“To assist in maintaining its integrity a cap should be protected on both its upper and lower surfaces. Accordingly, before a cap is emplaced the surface of deposited waste should be graded and any irregular objects should be removed. In providing a firm base to allow compaction of the cap and to minimise damage from below, a buffer layer should be installed. Where a synthetic material is to be used for capping, a buffer layer at least 0.5m thick is usually required. Inert material, which does not react with the waste or the cap, may be used as a buffer provided that it is free from large stones and lumps. At the same time it should not be so fine that it can permeate into the waste. Coarse or a mixture of coarse and fine gravel may be suitable.”
“7.47 Following the successful installation of the liner system there is a risk that damage will occur to the liner by a number of routes, such as · accidental damage… … 7.48 Accidental damage may arise where bulky difficult waste, for example, lighting columns or concrete lumps, is tipped carelessly onto the drainage or protection layer, and is able to puncture and damage a liner system, especially a flexible membrane… … 7.52 The designer should consider all possible causes of damage for the proposed site, and in conjunction with the operator ensure that appropriate measures are taken to avoid them. Precautionary measures may include · CQA [7] procedures for the initial waste infilling to minimise the risk of damage caused by waste …”
“…The first layer of waste placed in a cell is crucial for the landfill operation. This layer needs to be placed as a loose cushion layer, sometimes referred to as a ‘fluff’ layer… This loose first layer is essential in order to avoid damage to the liner and leachate collection system as a result of equipment tracking, or the waste itself penetrating the liner components during initial cell filling. Damage to the base liner system can very easily occur if initial cell filling is not carefully managed and such damage can soon negate good design and construction, and compromise the containment performance of a landfill. … The correct procedure for the construction of the first waste layer is as follows: · The access road to the working face must be constructed from the top of the cell to the bottom in a way that ensures that the landfill vehicles will traffic over soil ramps and not the bottom of the landfill cell. · At the end of the access road a relatively wide temporary area must be constructed for manoeuvring of trucks. · The first trucks must dispose of the waste at the end of the access road or a temporary movement area formed on the landfill base. · Bulky or hard wastes capable of puncturing the liner must be removed. · Depending on the waste type, the first waste should be deposited at a vertical layer thickness of at least 50 cm (often up to 1m or more if bagged street collection of waste is used), and this layer must not be compacted, so it then constitutes a protection layer to the liner and leachate drainage system. The above procedure ceases when the whole area of the landfill cell base is covered with waste to a depth of at least 50 cm (1m recommended), so that no landfill equipment can track in close proximity to the liner or the base drainage system of the landfill.”
“Where an HDPE liner is installed, the deposit of the first layer (2.0 metres) of waste above or against the liner protection layer shall be subject to strict and continuous supervision by the licence holder. Prior to any deposit of wastes an inspection procedure shall be submitted and agreed in writing by the Waste Disposal Authority. The following minimum conditions shall be included in the agreed procedure: - (i) only domestic wastes collected by or on behalf of a Waste Collection Authority or “soft” commercial wastes shall be deposited in the first 2.0 metres. The source of these wastes shall be agreed in writing by the Waste Disposal Authority. (ii) The first layer of wastes shall be subject to minimum compaction. (iii) Any solid objects with a single dimension greater than 300mm shall be removed from the layer and re-deposited above the first layer of wastes….”
“The first 2.0m layer of waste will be only domestic or soft commercial and the source of the waste will [sic] subject to written approval by the EA. The EA will be notified prior to the placement of this waste. Any solid objects with a single dimension greater than 300mm shall be removed from the initial layer and re-deposited above the first layer of waste. Where on inspection the waste intended for the first 2.0m is thought to contain objects greater than 300mm, it will not be used in the first 2.0m layer and will be deposited in the usual manner described in Section 7. The soft waste will be spread using a tracked machine not a compactor to ensure it is subject to minimum compaction. A written and photographic record will be maintained to include: · Location · Vehicle types · Vehicle registration numbers · Types of waste and materials provided. This record shall be made available to the EA on request. A depth profile of the waste will be used to demonstrate that the thickness of low compacted material meets the required 2.0m thickness and the whole process will be carried out on [sic] the presence of a suitably qualified person.”
“6. FIRST LIFT OF WASTE The placement of the first lift onto the base and sideslopes shall be supervised. This waste should consist of selected light office industrial waste processed in REL [8] waste material [sic] and should be loosely tipped. The Engineer, with the aid of landfill operators will ensure that material will be removed from the first waste lift which could push through the protective cover and puncture the liner eg. bed posts, steel reinforcing bars. The Engineer could be an appointed Engineer or Cleanaways [9] civil engineer representative.”
“The final layer of wastes will be free from bulky items or other materials likely to give rise to damage to the capping layer.” (2) In section 4.520, headed “Waste Discharge and Emplacement” (and, in particular, under the heading “Waste Placement & Compaction”, which described the operational methods to be used): “The first layer of waste placed over the engineered parts of the site will not contain large or bulky items in order to ensure that upon compaction the integrity of the basal liner and leachate collection system is not jeopardised. Crude domestic, commercial waste or other similarly generally homogeneous waste types free from bulky items will be used in the first lift placed over engineered parts of the site. Waste containing large or bulky items will not be placed within 2m of the top of the basal liner or within 2m of the flanks of the site.”
“Measures shall be taken to ensure that there is no damage to the membrane at any time. This shall include the placement of ‘selected wastes’ to a depth of 1.0 metre on top of the protective sand layer. Selected wastes shall consist of domestic wastes or ‘soft’ commercial wastes, the source of which shall be agreed by the Authority prior to their deposit. The emplacement of this waste shall be under the strict and continuous supervision of the Resolution holder.” (2) In section 4, headed “Landfill Restoration”, under subheading 4.1, “Restoration Contours and Final Cover Layer”: “The final layer of waste deposited shall, to a depth of at least 1.0 metre, be kept free of materials likely to interfere with final restoration or subsequent after use.”
“Are waste deposit and emplacement procedures in place for the installation, which ensure the following? The first layers of waste in a new cell are selected and inspected during placement to ensure that these do not cause damage to the installed barriers and liners. … The final layers of waste are selected and inspected during placement to ensure that these do not cause damage to the final capping…”
“5.2.2 Selection, Inspection and Deposit of Initial Layer of Waste Only selected waste, which excludes large, bulky or sharp items will be used to form the initial lift of waste in each cell immediately above the liner system. … The selected waste will be subject to a minimal amount of compaction and will be used to form a “buffer” layer approximately 2 metres in depth. … Selection and placement of the first layer of waste will be carried out under the supervision of a suitably trained member of the operational team, whose role will be to: - · Visually inspect all waste to be used in the initial layer immediately following discharge; · Identify any unsuitable materials, which may comprise large bulky or sharp items and ensure that such items are segregated and not placed in the initial waste lift; · Observe the compaction and spreading activities to ensure there is no damage to the lining system; · Advise the site manager in the event of damage being observed; and · Ensure that waste deposit operations cease immediately in the event of any damage occurring. The site manager or nominated deputy will be responsible for recording the placement of the first layers of waste and ensuring that the work is undertaken to the correct standard. … 5.2.4 Prevention of Damage to Barriers, Liners, Leachate and Landfill Gas Management Systems Action that will be taken during the deposit of waste to prevent damage to the basal barrier, lining system and leachate management system is described in Section 5.2.2. The selected waste that is placed on the base of the site will be progressively extended up the sidewalls to protect the sidewall lining system. The selection, inspection and placement of these materials will be subject to the same procedures as outlined in Section 5.2.2. In order to avoid inadvertent damage to leachate extraction and monitoring wells, a layer of construction or other selected waste, which will act as a buffer against subsequent damage by mobile plant, will be placed around the wells. … 5.2.7 Selection and Inspection of Final Layer of Waste In order to prevent damage to the final capping system, only selected waste which excludes large and bulky or sharp items will be used to form the final lift of waste in each cell immediately below the final capping layer. …”
“A disposal is a taxable disposal if – (a) it is a disposal of material as waste, (b) it is made by way of landfill, (c) it is made at a landfill site, and (d) it is made on or after 1 st October 1996.”
“ 64 Disposal of material as waste (1) A disposal of material is a disposal of it as waste if the person making the disposal does so with the intention of discarding the material. (2) The fact that the person making the disposal or any other person could benefit from or make use of the material is irrelevant. (3) Where a person makes a disposal on behalf of another person, for the purposes of subsections (1) and (2) above the person on whose behalf the disposal is made shall be treated as making the disposal. (4) The references in subsection (3) above to a disposal on behalf of another person includes reference to a disposal – (a) at the request of another person; (b) in pursuance of a contract with another person.”
“ 65A – Prescribed landfill site activities to be treated as disposals (1) An order may prescribe a landfill site activity for the purposes of this section. (2) If a prescribed landfill site activity is carried out at a landfill site, the activity is to be treated – (a) as a disposal at the landfill site of the material involved in the activity, (b) as a disposal of that material as waste, and (c) as a disposal of that material made by way of landfill. … (9) In this section – … ‘landfill site activity’ means any of the following descriptions of activity, or an activity that falls within any of the following descriptions – (a) using or otherwise dealing with material at a landfill site; (b) storing or otherwise having material at a landfill site.”
“(a) the use of material to cover the disposal area during a short term cessation in landfill disposal activity; … (g) the use of material placed against the drainage layer or liner of the disposal area to prevent damage to that layer or liner;”
“The mere fact that you can deposit and emplace waste in a manner which serves a useful function does not lead to the conclusion that you do not intend to abandon it.”
“Whether or not there is a liability to landfill tax in respect of the materials to which this appeal relates depends on the proper interpretation and application of the provisions of Part III of the 1996 Act. We are bound by the decision of this court in Customs and Excise Comrs v Parkwood Landfill Ltd [15] in respect of the aspects of interpretation with which it dealt. But we are not concerned with the applicability to the facts of this case of the judgement of this court in the Parkwood case or of Moses J in Customs and Excise Comrs v Darfish Ltd. in my view the decisions of both the tribunal and Barling J are open to the criticism that too much time was taken up with the application of those judgements to the 11 categories which I have mentioned and not enough to the application of the legislation to the facts of this case.”
“[9] landfill tax was introduced as from1 October 1996 by theFinance Act 1996 . The tax is a creature of domestic statute in that it is not a tax required under any provisions of Community law. However the United Kingdom does have obligations in Community law to take appropriate steps to encourage the prevention, recycling and processing of waste under EC Council Directive 75/442 of15 July 1975 on waste (OJ L194 25.07.75 p 39).The Environmental Protection Act 1990 is the key piece of domestic legislation enacted to meet this obligation. Landfill tax can therefore be seen as a separate domestic initiative aimed at protecting the environment and securing the ambitions of the directive. [10] A government White Paper of December 1995 entitled Making Waste Work (CM3040) preceded the imposition of landfill tax. It examined the strategies to be adopted to reduce the environmental impact of waste disposal. So far as landfill was concerned, three main objectives were set out. First, to reduce the amount of waste, second to reduce the amount of material going to landfill and third to place the cost of landfill on the person disposing of the waste. In that way waste producers would become aware of the cost of their activities. The central purpose of the landfill tax was stated (at para 1.68) to be – ‘… to ensure that landfill costs reflect environmental impact thereby encouraging business and consumers, in a cost effective and non-regulatory manner, to produce less waste; to recover value from more of the waste that is produced; and to dispose of less waste in landfill sites.’”
“Member States shall take measures to ensure that all of the costs involved in the setting up and operation of a landfill site, including as far as possible the cost of the financial security or its equivalent referred to in Article 8(a)(iv), and the estimated costs of the closure and after-care of the site for a period of at least 30 years shall be covered by the price to be charged by the operator for the disposal of any type of waste in that site.”
“In the light of the foregoing, the answer to the first question must be that Article 10 of Directive 1999/31 must be interpreted as meaning that it does not preclude a national provision, such as that at issue in the main proceedings, which makes the operator of a landfill site subject to a levy to be reimbursed by the local authority depositing the waste and which provides for financial penalties to be imposed on that operator for late payment of the levy, on condition that those rules are accompanied by measures to ensure that the levy is actually reimbursed within a short time and that all the costs of recovery, and in particular, the costs resulting from late payment of amounts which that authority owes to the site operator on that account, including costs incurred in order to avoid any financial penalty which might be imposed on the site operator, are passed on in the price to be paid by the authority to that operator. It is for the national court to ascertain whether those conditions have been satisfied.”
“HMRC undertake that they will not, in these appeals, raise any argument to the effect that the relevant intention for the purposes ofFinance Act 1996, section 64 , was that of any person other than the Appellants. In particular, HMRC will not raise any argument to the effect that Local Authorities or other customers were the persons making the disposals for the purposes of section 64. This undertaking applies to all stages of these appeals, including any appeals to the Upper Tribunal, Court of Appeal or Supreme Court.”
“…they [i.e. Parkwood] submitted that the condition in subsection (2)(a) of section 40 was not satisfied as the disposal was not “as waste”
“For present purposes, the materials deposited at the recycling plant are first divided into waste and recyclable material. Those in the latter category are recycled into aggregates and fines. Aggregates are concrete and other materials sorted, crushed and mixed so as to form mixed aggregate in pieces of 70 mm, or less, in diameter. Fines are a soil like material produced by sorting and mixing suitable materials to form a product which has the appearance and many of the characteristics of soil, including the ability to support the growth of plants, and consists of pieces of material of 12 mm, or less, in diameter. (That diameter has now been increased to 25 mm or less).”
“…it is first sorted by hand to ensure that true waste materials such as plastic, wood and paper are removed from it. They are dispatched to landfill. Brick and tarmac are also removed by hand as they too are unsuitable for recycling purposes. (Crushed brick is however suitable as a base for informal footpaths, and crushed tarmac (planings) is predominantly used for under surfaces of footpaths. Consequently, there is a market for both materials of which Recycling takes advantage). The remaining material is then subjected to primary screening over the first screening station. That which is too big to pass through the screen is passed through the primary crusher, and is then fit for use as a coarse road sub-base. The material which has passed through the screen is separated into aggregates and fines…”
“The tribunal were correct to concentrate upon the disposal at Parkwood’s landfill site because it was that disposal which was made by way of landfill. They rightly held that that was not a disposal as waste. [19] ”
“The commissioners also submitted that there was nothing in the statute which suggested that material which had been discarded as waste ceased to be waste because it had been successfully recycled. That submission is contrary to common sense. Take material which is thrown away. That is waste. Melt it down and mould it into a spare part for a machine and it is not waste. There need be no change in chemical substance to convert waste into a useful product. It is the act of recycling which is important.”
“[33] In those circumstances, in my view, it is clear that, assuming there to have been a disposal at all, the disposal relevant for the purposes of s 40(2)(a) was made by WRG on its own behalf. So the question posed by s 64(1) is whether WRG then intended to discard the materials. The word ‘discard’ appears to me to be used in its ordinary meaning of ‘cast aside’, ‘reject’ or ‘abandon’ and does not comprehend the retention and use of the material for the purposes of the owner of it. I agree with counsel for WRG that s 64(2) does not apply in such circumstances because there is, at the relevant time, either no disposal or no disposal with the intention of discarding the material. [34] It follows from this conclusion that the relevant intention may well not be that of the original producer of the materials. There is no principle that material once labelled as ‘waste’ is always ‘waste’ just because the original producer of it threw it away. That is not the relevant time at which the satisfaction of the condition imposed by s 40(2) is to be considered. Recycling may indicate a change in the relevant intention but it is not an essential prerequisite; re-use by the owner of the material for the time being may do likewise.”
“One [licence] condition which, I understood, applies in every case is that the operator must keep sufficient stocks of inert material or suitable substitutes for use as daily cover…”
“I do not read the Court of Appeal’s decision in WRG as requiring that some act of ‘retention’ or separation out of a part from the rest of the whole must be identified before an operator can be said not to be discarding the waste for the purposes of s 64.”
“In my judgement, the concept of intending to use something, as the antithesis of intending to cast it aside or abandon it, involves some action to harness the properties of an item and direct them towards a purpose of the user.”
“In so agreeing I would not however wish it to be thought that I do not recognise that a consideration of ‘use’ may in some circumstances be a valuable point in determining whether, per s 64(1), a disposal has been made ‘with the intention of discarding it’. WRG is an example of the importance of this.”
“Although the question is certainly not without difficulty, I would, on balance, conclude that Patersons cannot be said to use the material, the biomass, by virtue of harvesting methane produced in the course of its decomposition. As I see it, Patersons was intending to get rid of the material by way of landfill and the methane came naturally, and inevitably, as a later by-product of that activity. To revert to the seed example, they were not planting the seed but dumping it.”
“No factors which serve to indicate as a matter of fact whether material is being discarded by the person concerned should be excluded from consideration unless such an interpretation of the provision is unavoidable.”
“…it is not known at the point of deposit whether in fact the material that has been deposited can be used as fluff. The material that comes through the gate is only potentially useful, this is the core of the appellants' case. It is only potentially useful because it is of no use to these appellants if it contains large, hard or sharp objects. That is the very reason that they remove them. So at the point of deposit, at the point of making the disposal, the deposit into the cell, it is … not known whether it will be useful, it will be put to use or could benefit the appellants. It could. It depends what is in the bag. That is why it is said that there are checkers or spotters or whatever they are called. The gentleman to which Mr Hodges referred at Ling Hall was in the cell, asking himself the question essentially: is this material right for fluff? Some of it was, some of it wasn't. So with respect, the appellants can't have their cake and eat it. They were either selecting and inspecting to take out the large, hard and sharp objects so as to make the fluff usable, or they were using all of the waste which means they are simply putting landfilled waste to a useful purpose.”
“It is not discarded because if you didn't have the bubble wrap, you would nonetheless have to find some other material with which to wrap the broken glass and protect whoever picks up the bin bag from the bin from cutting themselves on the side of the glass. So you are not discarding it and you are using it.”
“WRG concedes that the material with which this appeal is concerned was disposed of by way of landfill as defined in s 65 because the provisions of sub-s (1) were literally complied with. Whether that concession is rightly made I leave to another case. For my part I entertain some doubt because although the definition in sub-s (1) is, in terms, exhaustive and unqualified it is coloured by the qualification introduced into the defined term itself by the words ‘by way of landfill’, see, for example, Delaney v Staples[1992] 1 All ER 944 at 947,[1992] 1 AC 687 at 692 and 44(1) Halsbury’s Laws (4 th edn reissue) para 1389. Indeed sub-s (4), though primarily dealing with timing, might be thought to draw a distinction between the material deposited as waste and the earth or other inert material with which it was covered so as to exclude the letter from being deposited by way of landfill. If that is so then why should material used for daily cover be regarded as disposed of by way of landfill, particularly if so used more than once? Material used in road building might be regarded as more obviously not disposed of by way of landfill notwithstanding that it is necessarily deposited on the surface of the landfill site.”