“This Company is a specialist in “No dig” drainage repairs and as such virtually all our work is for major UK construction Companies who, regardless of our 30 day credit terms, pay us from 76 days to 90 days. Their payment dates are always after the month end and invariably between the 10 th and 15 th of the month probably to pay their VAT on time. To obtain payment from them at any time except when they choose is impossible. Our current situation is that we are due to receive and have received from two reliable major customers confirmation that we will be paid on 10 th April which will enable us to pay the VAT for the current quarter due for payment today. A further customer who promised a payment for today has failed to do so.”
“The Company is engaged on drainage and repair work and perhaps as high as 90% of this work is as a sub contractor to National Construction Companies. The Company is registered for the Contractor to make payment under deduction of tax at 20%. Under the scheme the tax deducted can be used to offset PAYE and NHI [ sic ] liabilities. The problem for this Company is that the tax deductions exceed the PAYE liability by a considerable sum, for example at the beginning of June the deductions were£53,000 more than the liability for PAYE and NHI contributions. The Company had therefore effectively paid in advance PAYE and NHI contributions on nearly three months wages and salaries which had not yet been paid. The 20% deductions are of course the money which would have been available to pay the VAT but which is already held in the hands of HMG by another department.”
“I would point out that we did remove the surcharges for the periods 11/13, 02/14 and 05/14 following you [ sic ] initial request for a review as the reviewing officers [ sic ] understanding was there had been a sudden and unexpected extension in the time being taken by your main customers to make payment. My investigations however lead me to conclude that this was not in fact the case and the situation had been ongoing for some time. The above notwithstanding I do not intend to reinstate those surcharges. Whilst HMRC cannot grant a discretionary agreement to extend you [ sic ] quarterly payment date you currently have you can apply to use Non Standard Tax Periods (NSTP’s) which would alter the quarterly end dates to a date chosen by you which would the [ sic ] alter the due date for submission of your returns and payments.”
“We have considered the position for both quarters. On the evidence, we are not satisfied that the Appellant had a reasonable excuse in respect of the payment due for 11/14. However, we consider that the circumstances relating to the Enfield contract (as mentioned to HMRC in the Appellant’s letter dated14 October 2015 ) were exceptional in their effect on the Appellant’s financial position in relation to the payment due for period 02/15. We therefore confirm the surcharge for period 11/14 and find that the Appellant had a reasonable excuse for the late payment of the tax due for period 02/15. Thus we dismiss the appeal in respect of the surcharge for 11/14 and allow the appeal in respect of the surcharge for period 02/15.”
“. . . if the exercise of reasonable foresight and of due diligence and a proper regard for the fact that the tax would become due on a particular date would not have avoided the insufficiency of funds which led to the default, then the taxpayer may well have a reasonable excuse for non-payment, but that excuse will be exhausted by the date on which such foresight, diligence and regard would have overcome the insufficiency of funds.”
“There were particularly severe problems in the two quarters 12/14 and 02/15. The Company undertook two major contracts through Ringway Jacobs, the completion of which required the use of Combination Tankers at a substantial cost to SDI. These tankers were hired from a Company Roe Environmental and at one time SDI owed Roe Environmental in excess of£112,000 . SDI had negotiated 60 day terms with Roe Environmental on the basis that SDI would be paid on similar terms. Interim payments were scheduled on these contracts but were not paid on the due dates. Vigorous efforts were made to collect the money even up as far as the Financial Director of Ringway Jacobs but without success until a substantial payment was received on 18 th May and then only after threatening to report the lack of payment to TFL. We also had to negotiate with Roe Environmental to pay them only when SDI had been paid. Meanwhile interim payments were made to HMRC on 11 th May and 28 th May.”