‘The Department of Health & Social Care (DHSC) paid£42 million compensation to Royal Liverpool’s investors to terminate the PFI contract. The contract required the Trust to pay compensation to the PFI company’s lenders, based largely on the estimated cost to complete the hospital, before the actual cost to complete the hospital was known. Had the Department and Trust better understood the cost to complete the hospital, they may not have paid anything to the lender’
‘C) New Hospital Committee – 5 August and2 September 2021 Whilst concern was raised surrounding a potential delay of materials related to cladding work, it was noted that any delay would not affect the readiness to move to the New Hospital. Board members discussed additional concerns relating to risks about several services scheduled to move to the New Hospital. A workshop has been scheduled to take place in October for assurance to be presented about operational readiness for the move alongside anticipated workforce issues,’