“The following request relates to non-personal data only. Please provide an excel/CSV export of the F10 Notifications database since1/1/2016 , including the following information for each notification: - Date of Submission - Local Authority Name - Geographical Area - Client Organisation Name - Client Organisation Address & Postcode - Principal Designer Organisation Name - Principal Designer Address & Postcode - Principal Contractor Organisation Name - Principal Contractor Address & Postcode - Organisation Name, Address and Postcode for any other Designers and Contractors notified - Site Address, Street & Postcode - Type of Project - Project Category - Total weeks allocated for construction work (under reg 4(1)) - Construction Phase Planned Start Date - Construction Phase Planned End Date - Maximum planned number of people on site - Maximum planned number of contractors on site NB: Excluding: Any personal information – Please ONLY provide details where an organisation's name includes the word "Ltd", "plc", "LLP" or "Limited". We do not seek any personal information.”
‘Any person making a request for information to a public authority is entitled— (a) to be informed in writing by the public authority whether it holds information of the description specified in the request, and (b) if that is the case, to have that information communicated to him.’
‘Section 1(1) does not oblige a public authority to comply with a request for information if the authority estimates that the cost of complying with the request would exceed the appropriate limit.’
‘Section 1(1) does not oblige a public authority to comply with a request for information if the request is vexatious.’
‘In some cases, the burden of complying with the request will be sufficient, in itself, to justify characterising that request as vexatious, and such a conclusion is not precluded if there is a clear public interest in the information requested. Rather, the public interest in the subject matter of a request is a consideration that itself needs to be balanced against the resource implications of the request, and any other relevant factors, in a holistic determination of whether a request is vexatious.’
‘(1) If on an appeal under section 57 the Tribunal considers - (a) that the notice against which the appeal is brought is not in accordance with the law, or (b) to the extent that the notice involved an exercise of discretion by the Commissioner, that he ought to have exercised his discretion differently, the Tribunal shall allow the appeal or substitute such other notice as could have been served by the Commissioner, and in any other case the Tribunal shall dismiss the appeal. ‘(2) On such an appeal, the Tribunal may review any finding of fact on which the notice in question was based.’
‘the purpose of the request is to conduct a time-series analysis of the super-prime residential construction sector in Central London and the surrounding Home Counties - the information sought, and the detail requested, is entirely necessary in order to be able to perform this study, which is considered by the requester to be in the public interest.’