“9. In early 2014, the Furniture Renovations Contract was re-tendered between the four contractors on the framework agreement. The tender was described as Lot 4 Renovation and Repair of Defence Furniture. The first respondent was unsuccessful in this re-tender and instead the contract was awarded to the second respondent [Amaryllis].”
“11. … a significant number of the employees of [Millbrook] had, over varying periods of employment but some quite lengthy, been engaged in carrying out renovations work under what they would generally describe as the MOD contract. It is right to say that not all of the work being carried out by those employees for MOD related to “renovations” which is the relevant work applicable to the contract in question, but also included on occasion construction of new furniture. The claimants’ evidence and witness statements, however, confirmed that they regarded the greater part of their duties as relating to renovation work. 12. It is also averred and emphasised on behalf of the second respondent, and conceded by the first respondent to an extent which is in dispute, that the area of the factory where renovation work was carried out by the employees in question also incorporated work being carried out on inter-company projects as well as contracts which had been secured from customers other than MOD.”
“14. … purported to show that, over the six months period, an average of 69.1% of the employees’ time was spent on the renovations contract and 68.5% over the three month period. …”
“37. I also accept… that the fact that the spreadsheet … shows that almost 70% on average of the time spent by the relevant employees on the MOD renovations contract showed that MOD was the departments [sic] “biggest customer”, that did not mean that it was “dedicated” to MOD or that its principal purpose was to service the contract with MOD.”
“38. Compelling as Mr Hogarth’s arguments were, however, I formed the conclusion that I had to look at the reality of the situation as it existed “immediately” before the alleged transfer. … [This was] going back over a period which could reflect typical activity, which I accepted could properly be covered by the six month/three month periods covered by the spreadsheet at 1113 as well as the evidence relating to the past. 39. In the event, I was satisfied from the evidence present to me, on the balance of probabilities, that the department in which these claimants (and indeed others) worked had originally been set up with the specific purpose of servicing the MOD contract relating to renovations. …”
“40. Any commercial enterprise looking to maximise profit and utilisation of resources will and can quite properly seek and, in this case, secure contracts from other sources …”
“41. Nevertheless … on the evidence … the department had not “morphed” from being one dedicated principally to servicing the MOD renovations contract into one operated principally to service the needs of all customers, which happened to include the MOD as its major customer. 42. I was satisfied therefore, that there was at the material time an organised grouping of employees within the respondent organisation which had at its principal purpose the carrying out of the activities concerned on behalf of MOD. …”
“42. … Although there may have been some doubt as to whether the “in situ” activities referred to above were included in the contract awarded to [Amaryllis], I was satisfied that those activities were “fundamentally” the same as the activities carried out by [Millbrook] within the meaning of Regulation 3(2A) of the Regulations. …”
“41. … The Renovations Contract was, however, the primary contract and by far the largest contract. Having the Renovation Contract did however mean that we had the skilled workforce who could then be used for other smaller pieces of renovations work.”
“18. … may in practice, but without any deliberate planning or intent, be found to be working mostly on tasks which benefit a particular client. The paradigm of an “organised grouping” is indeed the case where the employees are organised as “the [Client A] team”, though no doubt the definition could in principle be satisfied in cases where the identification is less explicit.”
“18. … Taking it first and foremost by reference to the statutory language, regulation 3(3)(a)(i) does not say merely that the employees should in their day-to-day work in fact (principally) carry out the activities in question; it says that carrying out those activities should be the (principal) purpose of an “organised grouping” to which they belong. In my view that necessarily connotes that the employees be organised in some sense by reference to the requirements of the client in question. …”
“36. … In Mr Hogarth’s submission, the same is applicable here - namely that, even if, historically, the first respondent could be said to have had an organised grouping of employees which had as its principal purpose the carrying out of the relevant activities on behalf of the MOD, the evidence shows that that was no longer the case at the relevant time and that accordingly the statutory provisions are not applicable. 37. I also [emphasis added] accept, as advanced by Mr Hogarth, that the fact that the spreadsheet at document 1113 shows that almost 70% on average of the time spent by the relevant employees on the MOD renovations contract showed that MOD was the departments [sic] “biggest customer”, that did not mean that it was “dedicated” to MOD or that its principal purpose was to service the contract with MOD.”