"..instruct the Contractor to stop or not to start any work and .. later instruct him that he may re-start or start it"
"....you are hereby directed to reschedule your remaining works with immediate effect to complete the HSRG contract sequentially rather than in parallel. The schedule dates in your contract will be extended accordingly to allow for this change. We request that Shanahan Engineering review the resources on site and optimise those resources in line with the new schedule.
"(7) If in any case there are special circumstances which render it not reasonably practicable for the employer to comply with a requirement of subsection (1A), (2) or (4), the employer shall take all such steps towards compliance with that requirement as are reasonably practicable in those circumstances."
"(2) If the tribunal finds the complaint well-founded it shall make a declaration to that effect and may also make a protective award.
"(6) If on a complaint under this section a question arises- (a) whether there were special circumstances which rendered it not reasonably practicable for the employer to comply with any requirement of section 188, or (b) whether he took all such steps towards compliance with that requirement as were reasonably practicable in those circumstances,
"11. If there are special circumstances which render it not reasonably practicable to comply it is for the employer to establish that to the tribunal. It seems to us, that depending on the precise nature of the special circumstances, they may relieve the employer of the obligation to consult altogether. They may relieve the employer of the obligation to consult in respect of any of the requirements but still leave him under the duty to consult in relation to others. S.188(6) says:
"..not reasonably practicable for the employer to comply with any [our emphasis] requirement of s.188.."
"12. There is no link to be drawn between the period of 30 days specified in s.188(1A), being the period before which consultation must normally commence, and the protected period or any loss which may have been sustained by any particular individual."
"24. We do not interpret the letter from Alstom as expressly instructing Shanahan to dismiss employees. Quite plainly, however, the respondent was faced with the situation whereby all of a sudden, they no longer required as many employees as they had previously working on the site. It would be unrealistic to expect them to continue to employ 50 or thereabouts employees for whom they had no work. There was plainly a redundancy situation.
"26. We are not satisfied, however, that it relieved the respondent in any other respect from the obligation to consult. Quite plainly the situation of 50 or so employees for whom there was no work is not something an employer could countenance for very long. We are not blind to the economic realities of life, but on the other hand we have no evidence before us that the respondent's financial position was such that it had to dispense with the services of these individuals quite as quickly as it did. We see no reason why it would not have been open to the respondents to have carried out some consultation with the appropriate representatives so as to comply with the other requirements of s.188. Although the ordinary requirement would be that the consultation should start at least 30 days beforehand, there is no requirement that it should last for 30 days. Consultation may be quite adequately completed within a matter of only a few days, depending on the circumstances and we see no reason why in this situation, this respondent could not have consulted with the Union representatives commencing on 1 May and continuing perhaps only for a very few days thereafter, taking account of the fact that there was Bank Holiday. In the event the respondent was accepting liability to pay a week's wages in lieu of notice. We have no evidence to suggest that would have placed them in any great difficulty if that period has been extended, perhaps by no more than 2 or 3 days, whilst consultation took place. There was an agreed selection procedure in place and we do not think that the consultation process would have taken very long… certainly no more than a few days.
"Whenever a question arises as to whether a particular step or action was reasonably practicable or feasible, the injection of the qualification of reasonableness requires the answer to be given against the background of the surrounding circumstances and the aim to be achieved."
"16.3 Redundancy Consultation (a) Where a redundancy situation arises the employer shall commence consultation with the relevant signatory trades unions in line with statutory requirements, or as soon as reasonable practicable thereafter given the short-term changes in circumstances commonly experienced in engineering construction."
"45. I suggest that ETs, in deciding in the exercise of their discretion whether to make a protective award and for what period, should have the following matters in mind: